Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
7th Edition
ISBN: 9781259666094
Author: Erik W. Larson, Clifford F. Gray
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Textbook Question
Chapter 9, Problem 3E
Use the information contained below to compress one time unit per move using the least cost method. Reduce the schedule until you reach the crash point of the network. For each move identify what activity(ies) was crashed and the adjusted total cost.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Use the information contained below to compress one time unit per move using
the least cost method. Reduce the schedule until you reach the crash point of
the network. For each move identify what activity(s) was crashed the adjusted
total cost.
Eating
Act
A
Crash Cost (Slope)
Maximum Crash Time
Normal Time
Normal Cost
0
0
100
100
88828
2
150
1
200
1
3
200
2
200
1
3
150
A
1x
B3
D
3
F
Initial
project duration 12
3
E
4
4
Total
direct cost $
Case Study
Read the case study given below and answer ALL the questions given at the end of the case.
MEF: End full lockdown immediately
Wednesday, 23 June 2021
PETALING JAYA: MEF has urged the government to end the Full Movement Control Order (FMCO) with immediate effect to stop causing further damage to the national economy and individual livelihoods.
MEF President Dato’ Dr Syed Hussain Syed Husman J.P. said the lockdown has had a negative compounding effect on businesses since the MCO 1.0 in March 2020 with many companies being forced to shut down, thus causing higher retrenchments and loss of income.
“There has to be a reasonable balance between the saving of lives and livelihoods. The restrictions under the FMCO and confusion over the SOPs are killing businesses with many SMEs and micro enterprises severely impacted.
“Employers are prepared to endure even tighter restrictions under FMCO and even higher penalties for breaking the rules to end the lockdown, but the issue of…
Case Study
Read the case study given below and answer ALL the questions given at the end of the case.
MEF: End full lockdown immediately
Wednesday, 23 June 2021
PETALING JAYA: MEF has urged the government to end the Full Movement Control Order (FMCO) with immediate effect to stop causing further damage to the national economy and individual livelihoods.
MEF President Dato’ Dr Syed Hussain Syed Husman J.P. said the lockdown has had a negative compounding effect on businesses since the MCO 1.0 in March 2020 with many companies being forced to shut down, thus causing higher retrenchments and loss of income.
“There has to be a reasonable balance between the saving of lives and livelihoods. The restrictions under the FMCO and confusion over the SOPs are killing businesses with many SMEs and micro enterprises severely impacted.
“Employers are prepared to endure even tighter restrictions under FMCO and even higher penalties for breaking the rules to end the lockdown, but the issue of…
Chapter 9 Solutions
Project Management: The Managerial Process (Mcgraw-hill Series Operations and Decision Sciences)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, management and related others by exploring similar questions and additional content below.Similar questions
- Given the network shown above, what is the earliest start time for activity F? Given the network shown above, what is the earliest start time for activity F? 6 16 13 8 10arrow_forwardPrepare a plan for a small project of moderate complexity (at least 12 activities, with some interdependencies between activities). Your plan should identify the activity by their beginning and ending nodes and by short, descriptive titles. Estimate the times to complete the activities. Prepare a PERT/CPM network. Determine critical path and the expected time for completing the project (Activity Analysis and Event Analysis). Choose a project of some personal interest and knowledge (e.g. building a house, selling a house, political campaign etc.) Your project will be judged by how completely it identifies all activities, the reasonableness of your time estimates and the correctness of your analysis. UPLOAD YOUR ANSWER HERE AS IMAGE/PDF.arrow_forwardDuration and requirement of workforce for each activity is tabulated below for a network Activity Duration Number of men 1-2 3 5 2-4 2 3 2-3 3 7 3-4 0 0 3-5 3 2 4-5 7 2 3-6 2 1 5-6 6 6 4-6 5 5 (i) Draw the network and comment on the scheduling of activities to smoothen the development of the workforce (ii) Indicate the maximum crew size in each case (iii) Re-schedule the activities for smooth development (iv) Find the project schedule if only 4 men are availablearrow_forward
- please answer all parts of the question within 30 minutes with detailed explanation. Make sure calculation form part of the answer and are in details for better understanding. If calculations are not shown or are poorly done i will surely give negative ratings.arrow_forwardYour CEO at Telkom has appointed you as the lead project manager. For the duration of the project, your CEO wants you to report directly to him so that he can acquire first-hand information on the project as it progresses. The minister of telecommunications has given your CEO an ultimatum to deliver the project within 6 months. The scope of the project is to provide internet connectivity to KwaMashu, Kwa-Zulu Natal. Due to the large number of students that have to work from home in order to continue their studies, during COVID-19, the unavailability of internet connectivity has affected the students’ ability to access study content online, which has been escalated to the minister. Your job as the project manager is to ensure that the planning of the infrastructure (fibre) is undertaken, and then the installation is completed within the 6 month period, including the closure of the project. You will handle the full life cycle of the project and you will provide the necessary reports to…arrow_forwardIn making a forward pass through a network, three activities are immediate predecessors for activity T and one following activity. What is the late start time for activity T? Group of answer choices: - the LS of the following activity plus the activity time of T - the smallest EF for the three activities that are immediate predecessors for activity T - the LF of the following activity minus the activity time of T - the LS of the following activity minus the activity time of T - the largest EF for the three activities that are immediate predecessors for activity Tarrow_forward
- Please provide information in a short paragraph format for the Mt. Kumar Road project in Grenada. (1) State the name of the project and give a brief description of the project. (2) Outline the problem(s) that the project was initiated to solve or the opportunity it exploited. (3) Identify and describe the technique or method used by the sponsor to originally select the project among competing or multiple projects ideas within the organization.arrow_forwardThe table below represents a IS project set of activities, its expected completion time (weeks) and preceding activities. Activity Expected Time (weeks) Preceding activities A 5 None B 4 None C 10 A D 8 B E 14 B F 6 C, D G 7 D, E, F H 3 F, G Draw a network diagram for the IS project shown above. For each activity, calculate its earliest completion time (TE) and latest completion time (TL). Label TE and TL on the network diagram. Calculate the slack time for each activity.arrow_forwardHelp?arrow_forward
- I need a detailed explanation and assistance to solve the this problem: A company decides to plan a project, with activities, precedences and deterministic durations given in the following table: Activity i Duration (days) Immediate Predecessors A 32 none B 21 none C 30 none D 45 A E 26 A, B F 28 C G 20 E, F a) What method should be used? Using only one pseudo-activity, draw the project network, with arcs labeled by the activity name and duration. b) Compute and display in a table the earliest and latest starting and finishing times, as well as slack, for each activity, and identify the critical path(s). C) Draw a Gantt chart of the schedule, based on earliest starting times d) Which activities must be completed by day 60 to ensure that the project is not delayed?arrow_forwardUse the network below to answer the following questions 16 to 23. Note that projects start on Day 0. 0 0 0 X (4) 4 A (5) B (2) P (8) W (9) 16. What is the earliest day the contractor can start Activity P? 17. What is the latest day the contractor can finish Activity B? 18. What is the latest day the contractor can start Activity C? 19. What is the latest day the contractor can finish Activity A? 20. What is the EF for Activity W? 21. What is the LF for Activity C? 22. XAPC is NOT the critical path of the network. 23. What is the total duration of this project? Use this node notation: ES FF EF LS Activity (Duration) TF (1) LFarrow_forwardPROJECT IS ONLINE NEWS PORTAL Plan your project activities and draw network model. Perform forward pass to find earliest start date and earliest finish date for each activity.Find Critical path, Perform backward pass to find latest start date and latest finish datefor each activity.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY