Concept explainers
a. Calculate the
b. Calculate the NPV of the project using the single future value calculated in the previous step and the initial outlay. It is easy to verify that you will gel the same NPV as in your original calculation only if you use the required return as the reinvestment rate in the previous step.
Want to see the full answer?
Check out a sample textbook solutionChapter 9 Solutions
Fundamentals of Corporate Finance
- True or False A project will have multiple internal rates of return if its future net cash flows alternate between negative and positive values.arrow_forwardIf a project with conventional cash flows has an IRR equal to the required return, then: O The profitability index is one. O The IRR must be zero. O The project should be accepted, as the NPV is greater than zero. O The payback period is less than the maximum acceptable period. The NPV is negative.arrow_forwardWhenever the present value of the project is greater than the initial cash outlay then both the NPV and PI are positive. Select one: True Falsearrow_forward
- If a project has a positive net present value, then which of the following statements are correct? I. The present value of all cash inflows must equal the costs of the project. The IRR is equal to the required rate of return. II. A increase in the project's initial cost will cause the project to have a higher positive NPV. III. Any delay in receiving the projected cash inflows will cause the project to have a higher positive NPV. IV. IRR must equal zero. Only II Only III All None of themarrow_forwardYou have determined the profitability of a planned project by finding the present value of all the cash flows from that project. Which of the following would cause-the project to look less appealing in terms of the present value of those cash flows? O The discount rate decreases. The cash flows are extended over a longer period of time, but the total amount remains the same. O The discount rate increases. O Statements B and C are correct. O Statements A and B are correct.arrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. a. If a project's IRR is greater than its WACC, then the MIRR will be greater than the IRR. b. If a project's IRR is greater than its WACC, then the MIRR will be less than the IRR. c. A project's MIRR is always greater than its regular IRR. d. To find a project's MIRR, we compound cash inflows at the IRR and then discount the terminal value back to t = 0 at the WACC. e. A project's MIRR is always less than its regular IRR.arrow_forward
- What is the Modified Internal Rate of Return (MIRR) Select one: The opposite of NPV A reinvestment rate to account for positive cash flows reinvested into a project An approach to discounting The finance rate of a projectarrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one outflow followed by a series of inflows. O A project's regular IRR is found by compounding the initial cost at the WACC to find the terminal value (TV), then discounting the TV at the WACC. A project's IRR is the discount rate that causes the PV of the inflows to equal the project's cost. O If a project's IRR is smaller than the WACC, then its NPV will be positive. O A project's regular IRR is found by compounding the cash inflows at the WACC to find the present value (PV), then discounting the TV to find the IRR.arrow_forwardWhich one of the following statements is correct concerning the payback rule? a. The payback period is computed using the present value of each of the cash flows. b. The rule says that you should accept a project if the payback period is greater than 1.0. c. The rule is biased in favour of long-term projects. d. The rule is flawed because it ignores all cash flows after some arbitrary point in time.arrow_forward
- What do you know about the mathematical value of the internal rate of return of a project under each of the following conditions? a.The future worth of the project is equal to zero. b. The future worth of the project is less than zero.arrow_forward1] Payback and Internal Rate of Return: A project has perpetual cash flows of C per period, a cost of I, and a required return of r. What is the relationship between the project’s payback and its IRR? What implications does your answer have for long-lived projects with relatively constant cash flows? 2] WHAT ARE THE PROBLEMS WITH IRR APPROACH TO CAPITAL BUDGETING? 3] COMPARE IRR WITH MIRR METHOD.arrow_forwardWhich of the following statements is CORRECT? Assume that the project being considered has normal cash flows, with one cash outflow at t = o followed by a series of positive cash flows. a. To find a project's MIRR, we compound cash inflows at the regular IRR and then find the discount rate that causes the PV of the terminal value to equal the initial cost. b. To find a project's MIRR, the textbook procedure compounds cash inflows at the WACC and then finds the discount rate that causes the PV of the terminal value to equal the initial cost. c. A project's MIRR is always greater than its regular IRR. d. If a project's IRR is greater than its WACC, then its MIRR will be greater than the IRR. e. A project's MIRR is always less than its regular IRR.arrow_forward
- Intermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningEBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENT
- Financial & Managerial AccountingAccountingISBN:9781285866307Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage LearningAccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Financial & Managerial AccountingAccountingISBN:9781337119207Author:Carl Warren, James M. Reeve, Jonathan DuchacPublisher:Cengage Learning