Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
Operations Management (McGraw-Hill Series in Operations and Decision Sciences)
12th Edition
ISBN: 9780078024108
Author: William J Stevenson
Publisher: McGraw-Hill Education
bartleby

Concept explainers

Question
Book Icon
Chapter 7.S, Problem 9P

a)

Summary Introduction

To determine: The unit cost for 20 units.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

a)

Expert Solution
Check Mark

Answer to Problem 9P

The unit cost for 20 units is $80.31.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of unit cost for 20 units:

The time to compute the unit cost for 20 units is to compute the average cost for 20 units. It can be computed by finding labor cost, material cost, overhead cost and total cost. From the total cost, the average cost is computed.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 20 unit is 14.608 (using learning curve coefficient table)

T120=T1×14.608=5×14.608=73.04hours

The time for completing the 20 units is calculated by multiplying 5 with the unit factors 14.608 which yields 73.04 hours.

Laborcost=73.04hours×8.50perhour=$620.84

The labor cost is calculated by multiplying 73.045 hours with 8.50 which yields $620.84.

Materialcost=20units×$20perunit=$400.00

Material cost is calculated by multiplying 20 units with $20 per unit which yields $400.

Overheadcost=0.50×($620.84+$400.00+$50.0)=$535.42

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $535.42

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$620.84+$535.42+$400.00=$1,606.26

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $620.84, $535.42 and $400.00 which yields $1,606.26.

Averagecostperunit=$1,606.2620=$80.31

The average cost per unit is calculated by dividing $1,606.26 with 20 which yields $80.31.

Hence, the unit cost for 20 units is $80.31.

b)

Summary Introduction

To determine: The minimum production quantity necessary to make the production cost less than the purchase cost.

Introduction: Learning curve is referred as the cost curve, experience curve, efficiency curve or productivity curve. The leaving curve gives information about the cost, efficiency, productivity and performance of an organization.

b)

Expert Solution
Check Mark

Answer to Problem 9P

The minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Explanation of Solution

Given information:

Laborcost=$8.50perhourSetupcost=$50.00Materialcost=$20.00perunitLearningcurve=90%

Overhead=50%oflabor,materialsandsetupcostT1=5hoursPurchasecost=$88.50perunit

Formula:

Tn=T1×Unitfactor

Calculation of minimum production quantity necessary to make the production cost less than the purchase cost:

The production cost per unit is $80.31 per unit for 20 units and it is less than the purchase cost which is $88.50 per unit. By trial and error approach the numbers which accounts to less than the purchase cost is computed which are 10 units.

Estimation of labor, material, overheads and total cost:

At 90% learning curve, the unit factor for 10 unit is 7.994 (using learning curve coefficient table)

T110=T1×7.994=5×7.994=39.97hours

The time for completing 10 units is calculated by multiplying 5 with the unit factors 7.994 which yields 39.97 hours.

Laborcost=39.97hours×8.50perhour=$339.75

The labor cost is calculated by multiplying 39.97 hours with 8.50 which yields $339.75.

Materialcost=10units×$20perunit=$200.00

Material cost is calculated by multiplying 10 units with $20 per unit which yields $200.

Overheadcost=0.50×($339.75+$200.00+$50.0)=$294.88

The overhead cost calculated by taking 50% of labor, material and setup cost which accounts to $294.88

Totalcost=Setupcost+Laborcost+Materialcost+Overheadcost=$50+$339.75+$294.88+$200.00=$884.63

The total cost is calculated by summing up labor cost, material cost and overhead cost which is adding $50, $339.75, $294.88 and $200 which yields $884.63.

Averagecostperunit=$884.6310=$88.46

The average cost per unit is calculated by dividing $884.63 with 10 which yields $88.46 which is less than $88.50.

Hence, the minimum production quantity necessary to make the production cost less than the purchase cost is $88.46.

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
You have been asked to estimate the selling price per unit of a new production line of a certain product. Pertinent data are as follows: Direct labor rate Production material Factory overhead Packing costs Desired profit RO 15.00 per hour RO 375 per 100 items 125% of direct labor 25% of direct cost 30% of total manufacturing cost Past experience has shown that 83% learning curve applies to the labor required for production these items. The time to complete the first item has been estimated to be 1.86 hours. Use the estimated time to complete the 50h item as your standard time for the purpose of estimating the unit selling price.
National Company is planning to introduce a new product with an 85 percent learning rate for production for batches of 1,000 units. The variable labor costs are P30 per unit for the first 1,000-unit batch. Each batch requires 100 hours. There are P10,000 in fixed costs not subject to learning.   What is the cumulative average time per batch using the incremental unit-time learning curve for 2,000 units?
The labor cost to produce a certain item is $8.50 per hour. Job setup costs $50 and material costsare $20 per unit. The item can be purchased for $88.50 per unit. The learning rate is 90 percent.Overhead is charged at a rate of 50 percent of labor, materials, and setup costs.a. Determine the unit cost for 20 units, given that the first unit took 5 hours to complete.b. What is the minimum production quantity necessary to make production cost less than purchasecost?

Chapter 7 Solutions

Operations Management (McGraw-Hill Series in Operations and Decision Sciences)

Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.