Interpretation:
Expected completion time of project.
Concept Introduction: The critical path is the arrangement of project activities which gives an estimated time duration under which the project will be completed. The project activities may include float activities which can be delayed focusing on the shortest time duration.
a
Explanation of Solution
Calculate the estimated task time:
Task | Immediate predecessors | Optimistic time | Most likely time | Pessimistic time | Estimated task time | Variance |
A | None | 1 | 2 | 3 | 2 | 0.11 |
B | A | 2 | 4 | 6 | 4 | 0.44 |
C | None | 2 | 4 | 6 | 4 | 0.44 |
D | B and C | 1 | 2 | 9 | 3 | 1.78 |
Calculate the estimated task time for task A:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task A is 2 hours.
Calculate the estimated task time for task B:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task B is 4 hours.
Calculation of estimated task time for Task C:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for Task C is 4 hours.
Calculate the estimated task time for Task D:
It is calculated by dividing the value attained by adding optimistic time, pessimistic time and four times of most likely time with the value 6.
Hence, the estimated task time for task D is 3 hours.
Calculate the variance for Task A:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Calculate the variance for Task B:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for task B is 0.44
Calculate the variance for Task C:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task C is 0.44
Calculate the variance for Task D:
It is calculated by dividing the value attained subtracting the optimistic time from the pessimistic time with the value of 6. Then, square the attained value.
Hence, the variance for Task D is 1.78
Project network diagram for given information:
The below image shows the project network with the early start, early finish, late start and late finish:
A
The critical path in the project network:
The paths in the given project network are as follows:
A-B-D
C-D
There are two paths in the project network.
Out of the above-mentioned path, the path has the equal early start and late start at the same time early finish and late finish are the critical path.
Hence, the critical path is A-B-D and the project completion time is 9 days.
b
Interpretation:
Time duration in the beginning of reconfiguration.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
b
Explanation of Solution
The late start time for activity C:
According to the project network, the late start time for activity C is 2 day.
c
Interpretation:
Probability that warehouse will finish the project.
Concept Introduction: Early start time: The rule for the early start time of a task is that it is equal to the largest early finish time of the task’s immediate predecessors.
Early finish time: The early finish time of a task is the addition of both task time and early start time of the task.
c
Explanation of Solution
The probability to finish the operation, which started at 1:00 a.m. and finished at 11:00 a.m. on the same day:
The value of Z should be calculated to find the probability to find the operation.
It is calculated by dividing the value attained by subtracting the completion time from the time (time gap from 1:00 a.m. to 11:00 a.m.) with the square root of the variance of critical path (sum of the variance of critical path).
Hence, the value of Z is 0.6551
For Z= 0.6551, the
Want to see more full solutions like this?
Chapter 7 Solutions
Practical Operations Management
- Suppose that the project team has arrived at the following time estimates for activity B (Select site and survey) of the St. John’s Hospital project: a = 7 weeks, m = 8 weeks, and b = 15 weeks a. Calculate the expected time and variance for activity B. b. Calculate the expected time and variance for the other activities in the project.arrow_forwardRoss Hopkins, president of Hopkins Hospitality, has developed the tasks, durations, and predecessor relationships in the following table for building new motels. Draw the AON network and answer the questions that follow. a) What is the expected (estimated) time for activity C?b) What is the variance for activity C?c) Based on the calculation of estimated times, what is the criticalpath?d) What is the estimated time of the critical path?e) What is the activity variance along the critical path?f) What is the probability of completion of the project before week 36?arrow_forwardPlease explain how to solve this chart in terms of engineering project managment How can I draw the network diagrams?How can I list the network paths?How can I determine the critical paths? How can I determine the float for each activity?arrow_forward
- Suppose you are a project manager, and you have to manage a project with activities and their respective durations in weeks as listed in Table below. Construct a precedence network diagram to analyze your project. please do it hand writtenarrow_forwardKen Johnston, the data processing manager for Stanley Morgan Bank, is planning a project to install a new management information system. He is ready to start the project, and wishes to finish in 20 weeks. After identifying the 14 separate activities needed to carry out this project, as well as their precedence relationships and estimated durations (in weeks), Ken has constructed the following project network: 1. Create the network diagram for the project highlighting the critical path. 2. Identify the tasks in the critical path. 3. Find the earliest start and earliest finish, latest start, latest finish, and slack for each activity. Will Ken be able to meet his deadline if no delays occur? 4. Use the information generated to determine the following: a. What would be the duration of the project if Activity-I takes 2 extra weeks? b. What would be the duration of the project if Activity-H takes 2 extra weeks? c. What would be the duration of the project if Activity-J takes 2 extra weeks?arrow_forwardOffice Automation, has developed a proposal for introducing a new computerized office system that will improve word processing and interoffice communications for a particular company. Contained in the proposal is a list of activities that must be ac- accomplished to complete the new office-system project. Information about the activities is shown below where times are in weeks and costs are in thousands of dollars. NOTE: The crashing cost given in the last (seventh) column of the table below is the total cost to finish an activity by its minimum time given in the fifth column.arrow_forward
- Maladroit Cosmetics Company The plant manager of the Maladroit Cosmetics Company must replace several of her filling machines that have become obsolete. She is about to take delivery of six machines at a total cost of $4 million. These machines must be installed and fully tested in time to be used on a new production line scheduled to begin operation in 6 months. Because this project is important, the plant manager would like to devote as much time as possible to the job, but she is currently handling several other projects. She thinks she has three basic choices: (1) she can handle the project informally out of her office; (2) she can assign the project to a member of her staff; or (3) the company that manufactures the machines can handle the installation project for a fee close to what the installation would cost Maladroit. Questions A. Would you classify the work of installing the six machines as a project? B. Why or why not? C. Explain how the PM might trade off one of the…arrow_forwardDave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 7 - E 4 BB 8 - F 7 BC 4 A G 11 C, ED 1 A H 6 D , F Dave's earliest start (ES) and earliest finish (EF) are: Activity ES EF A 0 7 B 0 8 C 7 11 D 7 88 E 8 12 Part 7 F ? ? G ? ? H ? ?arrow_forwardYou are creating a customer database for the Hillsboro Hops minor league baseball team. Draw a project network given the information in the table that follows. Complete the forward and backward pass, compute activity slack, and identify the critical path. How long will this project take? How sensitive is the network schedule? Calcu-late the free slack and total slack for all noncritical activities.ID Description Predecessor Time (days)A Systems design None 2 B Subsystem A design A 1C Subsystem B design A 1D Subsystem C design A 1E Program A B 2F Program B C 2G Program C D 2H Subsystem A test E 1I Subsystem B test F 1J Subsystem C test G 1K Integration H, I, J 3L Integration test K 1arrow_forward
- Draw the network diagram. Determine the normal time itwill take to complete this project. Determine the critical path forthe project. Calculate the cost of completing the project in normaltime.arrow_forwardConsider the following data for a project to reorganize the office space at Platinum Financial Advisors:a. Draw the network diagram for this project. b. Identify the critical path and estimate the project’s duration. c. Calculate the slack for each activity.arrow_forwardConsider the following data for a project to reorganize the office space at Platinum Financial Advisors: a. Draw the network diagram for this project.b. Identify the critical path and estimate the project’s duration.c. Calculate the slack for each activity.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.