A project has three sequences of activities (paths), two of which are critical. The critical paths of this project can be characterized in the following way:
a. The slack times for each task in the entire project are zero.
b. The chain of activities (from start to finish) that has the largest sum of activity durations.
c. The early start date and early finish date are always the same for each activity on the critical path.
d. To reduce the project duration, you must reduce the slack time of a task on the critical path.
e. None of the above are correct.
As a project manager of a Software project, you have received given data about the different type of Issues identified in the project: –
Issue 1 – 85 occurrences; Issue 2 – 125 occurrences; Issue 3 – 28 occurrences; Issue 4 – 395 occurrences; Issue 5 – 185 occurrences; Issue 6 – 128 occurrences; Issue 7 – 85 occurrences; Issue 8 – 169 occurrences; Issue 9 – 148 occurrences; Issue 10 – 209 occurrences.
Which diagram you will use to prioritize the Issues? Generate the diagram using any tool and paste it here.
Which one of the following are true statements about a critical path in a project?
Knowledge of the critical path can be used to decide if any tasks in a project can
be delayed without extending the length of time of the project.
All tasks on the critical path must be completed before any other task in the
same project can be started.
Decreasing the times of tasks not on the critical path will not decrease the
length of time of the project.
There is only one critical path in any project.
Knowledge Booster
Similar questions
- set of concurrent activities are meant to pass a course. The process is as the following: 1- Student has to attend all classes and not to miss more than 25% of the classes. 2- Students selects a paper for presentation and gives a presentation on an assigned date. 3- Student has to choose a project topic and submits at the end of the course Draw a State Machine Diagram. Make sure to define events, conditions, actions for transitions in your diagram, where appropriate.arrow_forwardAt Riverside Financial, where you work as a project manager, you have been asked to conduct user training sessions during the implementation phase for a new information system. You must develop a specific schedule for the tasks (the estimated task duration for each is shown in parentheses): First, you need to send an e-mail message to all department managers announcing the training sessions (3 days). After the e-mail message goes out, two tasks can begin at the same time: You can develop the training material (7 days) and confirm arrangements for the training facility you plan to use (15 days). As soon as the training material is complete, you can work on two tasks at once: Arrange to have copies of handout material printed (7 days) and develop a set of PowerPoint slides (8 days). When the PowerPoint slides are ready, you conduct a practice training session with the instructor who will assist you (3 days). Finally, when the practice session is over, the handout material is ready, and…arrow_forward17 The entical path method (CPM) calculates the theoretical early start and fish dates, and late start and finish dates. The difference between the late and early start of a task is called A Free float B. Feeding buffer C Danger zone D Total float 18 Which of the following is NOT a characteristic of a project? A Ongoing nature B Uniqueness C Clear objectives D Integration of interrelated tasks and resources 19. Which of the following is NOT managed by the project manager? A. Time, cost and scope B. The project team C. The project sponsor D Expectations of the stakeholders 20 When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented? -A Human resource management plan B RACI chart C Resource calendar D Resource Breakdown Structure (RBS) 21. Which of these is not a component of the scope baseline that is contained in the project management plan? A Work…arrow_forward
- 133. Model suitable for project requiring shorter development times is a. Waterfall model b. RAD model c. Incremental model d. Decremented modelarrow_forwardSuppose an iteration in Elaboration is 2 weeks and you are the leader of the team. Also assume that Elaboration has 20 iterations and you are now in the 5th iteration of Elaboration. (a) What are the activities that would typically happen in this iteration? (b) What is the order of these activities? (c) Roughly how much time and on which day(s) should you spend on each of the activities?arrow_forwardTask Effort (person-days) Duration(days) Dependencies T1 5 5 T2 11 24 T1 T3 5 10 T4 15 5 T2 T5 10 10 T3 What is the total effort ?What will be the shortest duration of the project, if you can have multiple people working on it ? a. Effort: 44, Duration: 34 b. Effort: 34, Duration: 34 c. Effort:46, Duration: 46 d. Effort: 46, Duration: 34 e. Effort: 45, Duration: 34arrow_forward
- Which of the following statements is false? A work breakdown structure is a hierarchical structure that identifies the project’s resources by category and type. Duration and effort are not synonymous terms. A three-point estimate includes an optimistic, most likely, and pessimistic estimate. A Gantt chart is a common tool for displaying project schedule information.arrow_forwardWhich of the following are true, regarding Estimation practice? Longer programs have a smaller margin of error. As a general rule, in a most basic scenario, the following two estimation methods should be used in this order: first, "analogy," and second, "decomposition." Precision with which estimates are communicated should be at least two orders of magnitude greater than the accuracy of these estimates. The logical order of initial project activities is to start with commitment then proceed into scheduling and finish with estimating. Estimates should never be provided by the people who will do the work that is being estimated. "Anchoring" is a prudent planning poker strategy, since it allows influencing all members of the scrum team to the greatest extent. The order, in which these two estimation methods most commonly used, is as follows: first "Monter Carlo Simulation", and second, "T-shirt sizing". The…arrow_forwardGenerate a schedule of project in Gantt chart to observe the task timeline and progress.arrow_forward
- A company specializing in custom-engineered equipment is planning to submit a proposal to the National 5. Aeronautics and Space Administration (NASA) to build an assembled component for a new space station that NASA plans to launch into orbit. The winning proposal will be selected on the basis of both cost and timely delivery. Also, there will be a penalty clause in the NASA contract for late delivery. The company has developed the schedule of activities that are required to produce the assembled component. The activities and precedence requirements are presented in the table below. Three time estimates (in weeks) are given for each activity: optimistic time, most likely time, and pessimistic time. (a) What completion time should the company specify in its proposal in order to be 85% sure that it will complete the project on time? ij Activity Immediate predecessor Optimistic time (weeks) a b d. h b e, d d e,f f,g h, i a a a 15 8 10 20 17 4 10 Most likely time (weeks) 24 16 10 14 26 23…arrow_forward11. A model-based technique for estimation wherein standard parameters based on prior projects are applied to the new project is known as a. COCOMO b. decomposition c. resource leveling d. function pointsarrow_forward"High requirements stability at the beginning of the project" describes requirements freeze requirements creep requirements elicitation requirements transformationarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Information Technology Project ManagementComputer ScienceISBN:9781337101356Author:Kathy SchwalbePublisher:Cengage Learning
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337101356/9781337101356_smallCoverImage.jpg)
Information Technology Project Management
Computer Science
ISBN:9781337101356
Author:Kathy Schwalbe
Publisher:Cengage Learning