17 The entical path method (CPM) calculates the theoretical early start and fish dates, and late start and finish dates. The difference between the late and early start of a task is called A Free float B. Feeding buffer C Danger zone D Total float 18 Which of the following is NOT a characteristic of a project? A Ongoing nature B Uniqueness C Clear objectives D Integration of interrelated tasks and resources 19 Which of the following is NOT managed by the project manager? A. Time, cost and scope B. The project team C. The project sponsor D Expectations of the stakeholders

Information Technology Project Management
8th Edition
ISBN:9781285452340
Author:Kathy Schwalbe
Publisher:Kathy Schwalbe
Chapter4: Project Integration Management
Section: Chapter Questions
Problem 5E
icon
Related questions
Question
17 The entical path method (CPM) calculates the theoretical early start and fish
dates, and late start and finish dates. The difference between the late and early
start of a task is called
A Free float
B. Feeding buffer
C Danger zone
D Total float
18 Which of the following is NOT a characteristic of a project?
A Ongoing nature
B Uniqueness
C Clear objectives
D Integration of interrelated tasks and resources
19. Which of the following is NOT managed by the project manager?
A. Time, cost and scope
B. The project team
C. The project sponsor
D Expectations of the stakeholders
20 When writing the roles and responsibilities for team members, you should
document the role, authority, responsibility and competency for each team
member. Where must this information be documented?
-A Human resource management plan
B RACI chart
C Resource calendar
D Resource Breakdown Structure (RBS)
21. Which of these is not a component of the scope baseline that is contained in
the project management plan?
A Work Breakdown Structure (WBS)
B Requirements documentation
C WBS Dictionary
D Project Scope Statement
now software for a well-known car
Transcribed Image Text:17 The entical path method (CPM) calculates the theoretical early start and fish dates, and late start and finish dates. The difference between the late and early start of a task is called A Free float B. Feeding buffer C Danger zone D Total float 18 Which of the following is NOT a characteristic of a project? A Ongoing nature B Uniqueness C Clear objectives D Integration of interrelated tasks and resources 19. Which of the following is NOT managed by the project manager? A. Time, cost and scope B. The project team C. The project sponsor D Expectations of the stakeholders 20 When writing the roles and responsibilities for team members, you should document the role, authority, responsibility and competency for each team member. Where must this information be documented? -A Human resource management plan B RACI chart C Resource calendar D Resource Breakdown Structure (RBS) 21. Which of these is not a component of the scope baseline that is contained in the project management plan? A Work Breakdown Structure (WBS) B Requirements documentation C WBS Dictionary D Project Scope Statement now software for a well-known car
Expert Solution
steps

Step by step

Solved in 5 steps

Blurred answer
Knowledge Booster
Project Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781285452340
Author:
Kathy Schwalbe
Publisher:
Cengage Learning
Information Technology Project Management
Information Technology Project Management
Computer Science
ISBN:
9781337101356
Author:
Kathy Schwalbe
Publisher:
Cengage Learning