Which of the following are true, regarding Estimation practice?     Longer programs have a smaller margin of error.     As a general rule, in a most basic scenario, the following two estimation methods should be used in this order: first, "analogy," and second, "decomposition."     Precision with which estimates are communicated should be at least two orders of magnitude greater than the accuracy of these estimates.     The logical order of initial project activities is to start with commitment then proceed into scheduling and finish with estimating.     Estimates should never be provided by the people who will do the work that is being estimated.     "Anchoring" is a prudent planning poker strategy, since it allows influencing all members of the scrum team to the greatest extent.     The order, in which these two estimation methods most commonly used, is as follows: first  "Monter Carlo Simulation", and second, "T-shirt sizing".     The logical order of initial project activities is to start with estimating then proceed into scheduling and finish with commitment.

Database System Concepts
7th Edition
ISBN:9780078022159
Author:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Chapter1: Introduction
Section: Chapter Questions
Problem 1PE
icon
Related questions
Question

Which of the following are true, regarding Estimation practice?

   

Longer programs have a smaller margin of error.

   

As a general rule, in a most basic scenario, the following two estimation methods should be used in this order: first, "analogy," and second, "decomposition."

   

Precision with which estimates are communicated should be at least two orders of magnitude greater than the accuracy of these estimates.

   

The logical order of initial project activities is to start with commitment then proceed into scheduling and finish with estimating.

   

Estimates should never be provided by the people who will do the work that is being estimated.

   

"Anchoring" is a prudent planning poker strategy, since it allows influencing all members of the scrum team to the greatest extent.

   

The order, in which these two estimation methods most commonly used, is as follows: first  "Monter Carlo Simulation", and second, "T-shirt sizing".

   

The logical order of initial project activities is to start with estimating then proceed into scheduling and finish with commitment. 

Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 3 steps

Blurred answer
Knowledge Booster
Project Analysis
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, computer-science and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Database System Concepts
Database System Concepts
Computer Science
ISBN:
9780078022159
Author:
Abraham Silberschatz Professor, Henry F. Korth, S. Sudarshan
Publisher:
McGraw-Hill Education
Starting Out with Python (4th Edition)
Starting Out with Python (4th Edition)
Computer Science
ISBN:
9780134444321
Author:
Tony Gaddis
Publisher:
PEARSON
Digital Fundamentals (11th Edition)
Digital Fundamentals (11th Edition)
Computer Science
ISBN:
9780132737968
Author:
Thomas L. Floyd
Publisher:
PEARSON
C How to Program (8th Edition)
C How to Program (8th Edition)
Computer Science
ISBN:
9780133976892
Author:
Paul J. Deitel, Harvey Deitel
Publisher:
PEARSON
Database Systems: Design, Implementation, & Manag…
Database Systems: Design, Implementation, & Manag…
Computer Science
ISBN:
9781337627900
Author:
Carlos Coronel, Steven Morris
Publisher:
Cengage Learning
Programmable Logic Controllers
Programmable Logic Controllers
Computer Science
ISBN:
9780073373843
Author:
Frank D. Petruzella
Publisher:
McGraw-Hill Education