FINANCIAL ACCOUNTING
6th Edition
ISBN: 9781618533111
Author: DYCKMAN
Publisher: Cambridge Business Publishers
expand_more
expand_more
format_list_bulleted
Concept explainers
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Sandhill Construction, which follows ASPE entered into a contract to construct a bridge for a contract price of $2.8 million.
Construction began in 2022 and was completed in 2024. Below are the details of the transactions related to the contract:
Costs incurred during the year
Estimated costs to complete
Revenue
Expenses
$
Gross Profit $
2022
2022
$637,000
1,489,000
$844,000
Calculate the gross profit to be recognized each year using the completed-contract method.
2023
$
$
713,000
2024
$715,900
2023
0
$
$
2024
SUPPORT
A&B Construction enters into a contract to construct a bridge for $1,400,000. At the outset, A&B estimates that it will
cost $1,200,000 to build the bridge. Actual costs in 2017 are $540,000. Actual costs in 2018 are less than expected and
amount to $600,000. The profits reported under the completed contract and percent of completion methods for each
year would be:
Select one:
Completed Contract
Percentage of Completion
○ a.
2017
2018
2017
2018
$0
$200,000
$90,000
$170,000
O b.
Completed Contract
Percentage of Completion
2017
2018
2017
2018
$0
$260,000
$90,000
$170,000
Completed Contract
Percentage of Completion
2017
2018
2017
$0
$260,000
$123,000
2018
$197,000
○ d.
Completed Contract
Percentage of Completion
2017
2018
2017
$0
$260,000
$90,000
2018
$110,000
GinebraCorporation recognizes construction revenue and cost using the percentage of completion method. During 2021, a single long-term project was begun which continued through 2021. Information on the project follows:
2021. 2022
Partial billing on contract 1,000,000. 4,200,000
Accounts receivable 1,000,000 3,000,000
Construction cost 1,050,000 1,920,000
Construction in progress 1,220,000 3,640,000
What is the gross profit recognized from this long-term construction contract in year 2021 and 2022, respectively?
2021 2022
A.220,000. 2,280,000
B.170,000. 500,000
C.220,000. 1,000,000
D.170,000. 1,280,000
Chapter 6 Solutions
FINANCIAL ACCOUNTING
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- On March 1, 2019, Elkhart enters into a new contract to build a specialized warehouse for 7 million. The promise to transfer the warehouse is determined to be a performance obligation. The contract states that if the warehouse is usable by November 30, 2019, Elkhart will receive a bonus of 600,000. For every week after November 30 that the warehouse is not usable, the bonus will decrease by 150,000. Elkhart provides the following completion schedule: Required: 1. Assume that Elkhart uses the expected value approach. What amount should Elkhart use for the transaction price? 2. Assume that Elkhart uses the most likely amount approach. What amount should Elkhart use for the transaction price? 3. Next Level What is the purpose of assessing whether a constraint on the variable consideration exists?arrow_forwardBartov Corporation agreed to build a warehouse for $2,500,000. Expected (and actual) costs for the warehouse follow: 2019, $400,000; 2020, $1,000,000; and 2021, $500,000. The company completed the warehouse in 2021. Compute revenues, expenses, and income for each year 2019 through 2021 assuming that Bartov’s performance obligation for the warehouse is fulfilled over time and that the costs incurred provide a close approximation of the value conveyed to the customer. Round percentages to the nearest whole percent. Use rounded percentages to calculate subsequent answers.arrow_forwardPharoah Construction entered into a contract to construct a bridge for a contract price of $2.95 million. Construction began in 2019 and was completed in 2021. Below are the details of the transactions related to the contract: 2019 2020 2021 Costs incurred during the year $649,000 $836,000 $693,900 Estimated costs to complete 1,427,800 515,000 0 Calculate the revenue, expenses and gross profit to be recognized each year using the percentage-of-completion method. (Round the percentage completion to 2 decimal places, e.g. 52.75% and other answers to 0 decimal places, e.g. 1,525.) 2019 2020 2021 Revenue $ $ $ Expenses Gross Profit $ $ $arrow_forward
- On February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forwardArizona Desert Homes (ADH) constructed a new subdivision during 2023 and 2024 under contract with Cactus Development Company. Relevant data are summarized below: Contract amount Cost: Gross profit: Contract billings: 2023 2024 2023 2024 2023 2024 $ 3,405,000 1,290,000 690,000 935,000 490,000 1,702,500 1,702,500 ADH recognizes revenue upon completion of the contract. What is the journal entry in 2024 to record revenue?arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forward
- Assume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forwardAssume Avaya contracted to provide a customer with Internet infrastructure for $2,200,000. The project began in 2024 and was completed in 2025. Data relating to the contract are summarized below: Costs incurred during the year Estimated costs to complete as of 12/31 Billings during the year Cash collections during the year Required: 1. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming Avaya recognizes revenue over time according to percentage of completion. 2. Compute the amount of revenue and gross profit or loss to be recognized in 2024 and 2025, assuming this project does not qualify for revenue recognition over time. 3. Prepare a partial balance sheet to show how the information related to this contract would be presented at the end of 2024, assuming Avaya recognizes revenue over time according to percentage of completion. 4. Prepare a partial balance sheet to show how the information related to this contract would be presented at…arrow_forwardHow much is the Gross Profit/Loss Realized in 2018? Celestial Holdings Co. began constructing a condominium on January 1, 2017 for a contract price of P1,250,000. The entity has assured collection of its contract and the costs can be reliably estimated. For the year ended December 31, 2018, Celestial billed its client an additional 60% of the contract price. Data relating to the construction are as follows: 2017 2018 2019 Construction in Progress Estimated Cost to Complete 300,000 Cost Incurred 250,000 600,000 112,500 Excess of CIP over PB 25,000 (125,000)arrow_forward
- Assume that Ivanhoe Construction Company has a non-cancellable contract to construct a $4,600,000 bridge at an estimated cost of $4,140,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year Contract price Estimated total cost Estimated gross profit Estimated loss 2023 $1,035,000 3,105,000 *$2,980,800+$1,676,700 955,000 788,000 2025 $2,980,800 $4,657,500 1,676,700 2024 The revised estimates for the bridge contract are as follows. 2,443,000 1,801,000 2023 Original Estimates 2024 Revised Estimates $4,600,000 $4,600,000 4,140,000 4,657.500* $460,000 1,202,000 2,011,000 0 $(57,500)arrow_forwardRequired information [The following information applies to the questions displayed below.] In 2021, the Westgate Construction Company entered into a contract to construct a road for Santa Clara County for $10,000,000. The road was completed in 2023. Information related to the contract is as follows: Cost incurred during the year Estimated costs to complete as of year-end Billings during the year Cash collections during the year Westgate recognizes revenue over time according to percentage of completion. Revenue Gross profit (loss) 2021 2022 $2,610,000 $3,162,000 6,390,000 2,028,000 2,100,000 1,850,000 2021 2022 Required: 1. Calculate the amount of revenue and gross profit (loss) to be recognized in each of the three years. (Do not round intermediate calculations. Loss amounts should be indicated with a minus sign.) 2023 $2,230,800 2023 0 3,672,000 4,228,000 5,150,000 3,000,000arrow_forwardAssume that Crane Construction Company has a non-cancellable contract to construct a $4,640,000 bridge at an estimated cost of $4,176,000. The contract is to start in July 2023, and the bridge is to be completed in October 2025. The following data pertain to the construction period. (Note that, by the end of 2024, Crane has revised the estimated total cost from $4,176,000 to $4,228,200.) Assume that progress billings are non-refundable. Costs to date (12/31) Estimated costs to complete (12/31) Progress billings during the year Cash collected during the year (a1) Account Titles and Explanation (To record cost of construction) (To record progress billings) (To record collections) (To record revenues) 2023 (To record construction expense) 3,173,760 $1,002,240 $2,959,740 $4,228,200 994,000 2024 834,960 1,268,460 2,483,000 Prepare all journal entries required for Crane to account for this contract for 2023. (Credit account titles are automatically indented when the amount is entered. Do not…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Intermediate Accounting: Reporting And AnalysisAccountingISBN:9781337788281Author:James M. Wahlen, Jefferson P. Jones, Donald PagachPublisher:Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:Cengage Learning