GEN COMBO LOOSELEAF INTERMEDIATE ACCOUNTING; CONNECT ACCESS CARD
GEN COMBO LOOSELEAF INTERMEDIATE ACCOUNTING; CONNECT ACCESS CARD
9th Edition
ISBN: 9781260089042
Author: J. David Spiceland
Publisher: McGraw-Hill Education
bartleby

Videos

Textbook Question
Book Icon
Chapter 5, Problem 5.19E

Long-term contract; revenue recognition over time; loss projected on entire project

• LO5–9

On February 1, 2018, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2018, costs of $2,000,000 were incurred with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000.

In 2019, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2019 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2020 after additional costs of $3,800,000 were incurred. The company’s fiscal year-end is December 31. Arrow recognizes revenue over time according to percentage of completion.

Required:

  1. 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years.
  2. 2. Prepare journal entries for 2018 and 2019 to record the transactions described (credit “various accounts” for construction costs incurred).
  3. 3. Prepare a partial balance sheet to show the presentation of the project as of December 31, 2018 and 2019.

Requirement – 1

Expert Solution
Check Mark
To determine

Contract

Contract is a written document that creates legal enforcement for buying and selling the property. It is committed by the parties to performing their obligation and enforcing their rights.

Revenue recognized point of long term contract

A long-term contract qualifies for revenue recognition over time. The seller can recognize the revenue as per percentage of the completion of the project, which is recognized by revenue mines cost of completion until date.

A contract does not meet the performance obligation norm. The seller cannot recognize the revenue till the project complete.

The revenue recognition principle

The revenue recognition principle refers to the revenue that should be recognized in the time period, when the performance obligation (sales or services) of the company is completed.  

To calculate: The amount of revenue and gross profit or loss to be recognized in the year 2018, 2019, and 2020.

Explanation of Solution

Recognized revenue

In the year 2018:

Here,

Contract price is $8,000,000,

Actual cost to date is $2,000,000,

Total estimated cost is $6,000,000.

Now, calculate the revenue recognition:

Revenue recognition =Contract price×(Actual cost to dateTotal estimated cost)=$8,000,000×$2,000,000$6,000,000=$8,000,000×33.33%=$2,666,667

Hence, the calculated revenue recognition is $2,666,667.

In the year 2019:

Here,

Contract price is $8,000,000,

Actual cost to date is $4,500,000,

Total estimated cost is $8,100,000,

Revenue recognition in 2018 is $2,666,667.

Now, calculate the revenue recognition:

Revenue recognition =((Contract price×(Actual cost to dateTotal estimated cost))Revenue recognition in 2018)=(($8,000,000×$4,500,000$8,100,000)$2,666,667)=(($8,000,000×55.5556%)$2,666,667)=$4,444,448$2,666,667

=$1,777,778

Hence, the calculated revenue recognition is $1,777,778.

In the year 2020:

Here,

Contract price is $8,000,000,

Revenue recognition in 2018 is $2,666,667,

Revenue recognition in 2019 is $1,777,778.

Now, calculate the revenue recognition:

Revenue recognition =Contractprice(Revenue recognition in 2016+ Revenue recognition in 2017)=$8,000,000($2,666,667+$1,777,778)=$8,000,000$4,444,445=$3,555,555

Hence, the calculated revenue recognition is $3,555,555.

Recognized gross profit

In the year 2018:

Here,

Revenue recognition in 2018 is $2,666,667

Actual cost to date is $2,000,000.

Now, calculate the gross profit recognition:

Gross profit recognition =(Revenue recognition in 2016 Actual cost to date)=$2,666,667$2,000,000=$666,667

Hence, the calculated gross profit recognition is $666,667.

In the year 2019:

Here,

Revenue recognition in 2019 is ($100,000)

Gross profit recognition in 2018 is $666,667.

Now, calculate the gross profit recognition:

Gross profit recognition =(Revenue recognition in 2017 Gross profit recognition in 2016)=($100,000)$666,667=($766,667)

Hence, the calculated gross loss recognition is ($766,667).

In the year 2020:

Here,

Revenue recognition in 2020 is ($300,000)

Revenue recognition in 2019 is ($100,000).

Now, calculate the gross profit recognition:

Gross profit recognition =(Revenue recognition in 2018 Revenue recognition in 2017)=($300,000)($100,000)=($200,000)

Hence, the calculated gross loss recognition is ($200,000).

Working note:

Calculate the value of gross profit (in millions)

Particulars201820192020
Contract price$8$8$8
Actual costs to date$2$4.5$8.3
Estimated costs to complete$4$3.6$0
Total estimated cost$6$8.1$8.3
Estimated gross profit$2($0.1)($0.3)

Table (1)

(1)

Requirement – 2

Expert Solution
Check Mark
To determine

To record: The journal entry for the year 2018 and 2019.

Explanation of Solution

In the year 2018:

DateAccount Title and ExplanationPost Ref.DebitCredit
 Construction in progress $2,000,000 
      Various accounts   $2,000,000
 (To record construction cost)   

Table (2)

  • Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
  • Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Account receivable $2,500,000 
          Billings on construction contract $2,500,000
 (To record progress billings)   

Table (3)

  • Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
  • Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Cash $2,250,000 
      Account receivable  $2,250,000
 (To record cash collection)   

Table (4)

  • Cash is an asset. There is an increase in asset value. Therefore, it is debited.
  • Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Construction in progress $666,667 
 Cost of construction $2,000,000 
        Revenue from long-term contracts   $2,666,667
 (To record gross profit)   

Table (5)

  • Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
  • Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
  • Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.

In the year 2019:

DateAccount Title and ExplanationPost Ref.DebitCredit
 Construction in progress $2,500,000 
      Various accounts   $2,500,000
 (To record construction cost)   

Table (6)

  • Construction in progress is an asset. There is an increase in asset value. Therefore, it is debited.
  • Various accounts are revenue. There is an increase in liability value. Therefore, it is credited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Account receivable $2,750,000 
          Billings on construction contract $2,750,000
 (To record progress billings)   

Table (7)

  • Account receivable is an asset. There is an increase in asset value. Therefore, it is debited.
  • Billings on construction contract is revenue. There is a decrease in liability value. Therefore, it is debited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Cash $2,475,000 
      Account receivable  $2,475,000
 (To record cash collection)   

Table (8)

  • Cash is an asset. There is an increase in asset value. Therefore, it is debited.
  • Account receivable is an asset. There is a decrease in asset value. Therefore, it is credited.
DateAccount Title and ExplanationPost Ref.DebitCredit
 Cost of construction (2) $2,544,445 
      Revenue from long-term contracts  $1,777,778
      Construction in progress  $766,667
 (To record expected loss)   

Table (9)

  • Cost of construction is an expense. There is a decrease in liability value. Therefore, it is debited.
  • Revenue from long-term contracts is revenue. There is an increase in liability value. Therefore, it is credited.
  • Construction in progress is an asset. There is a decrease in asset value. Therefore, it is credited.

Working note:

Calculate the cost of construction

Given,

Revenue recognition in 2019 is $1,777,778

Loss recognition in 2019 is $766,667.

Now, calculate the gross profit recognition:

Gross profit recognition =(Revenue recognition in 2017+ Loss recognition in 2017)=$1,777,778+$766,667=$2,544,445

(2)

Requirement – 3

Expert Solution
Check Mark
To determine

To prepare: A partial balance sheet to show the presentation of the project as of December 31, 2018 and 2019.

Explanation of Solution

In the year ended 2018:

Balance sheet

At December 31,2018

Current assetsAmount
Account receivable$250,000
Cost and profit in excess of billings (3)$166,667
  

Table (10)

Working note:

Calculate the costs and profit in excess of billings:

Given,

Profit is $2,666,667 ($2,000,000 + $666,667)

Billing profit is $2,500,000.

Now, calculate the costs and profit in excess of billings:

Costs and profit in excess of billings =(Profit  Billing profit)=$2,666,667 $2,500,000 =$166,667

(3)

In the year ended 2019:

Balance sheet

At December 31,2019

Current assetsAmount
Account receivable$525,000
  
Current liabilityAmount
Cost and profit in excess of billings (4)$850,000
  

Table (11)

Working note:

Calculate the costs and profit in excess of billings:

Given,

Profit is $5,250,000

Billing profit is $4,400,000.

Now, calculate the costs and profit in excess of billings:

Costs and profit in excess of billings =(Profit  Billing profit)=$5,250,000$4,400,000=$850,000

(4)

Want to see more full solutions like this?

Subscribe now to access step-by-step solutions to millions of textbook problems written by subject matter experts!
Students have asked these similar questions
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $410 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 2024 $ 50 200 2025 $ 150 2026 $ 45 50 31 Required: 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify…
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $230 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: Required 1 Required 2 Required 3 Year 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming this project does not qualify…
Exercise 6-20 (Algo) Long-term contract; revenue recognition over time vs. upon project completion [LO6-9] On June 15, 2024, Sanderson Construction entered into a long-term construction contract to build a baseball stadium in Washington, D.C., for $320 million. The expected completion date is April 1, 2026, just in time for the 2026 baseball season. Costs incurred and estimated costs to complete at year-end for the life of the contract are as follows ($ in millions): Costs incurred during the year Estimated costs to complete as of December 31 Required: Required 1 Required 2 Required 3 2024 2025 2026 Construction revenue Construction expense Gross profit (loss) 1. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income statements related to this contract, assuming Sanderson recognizes revenue over time according to percentage of completion. 2. Compute the revenue and gross profit that Sanderson will report in its 2024, 2025, and 2026 income…

Chapter 5 Solutions

GEN COMBO LOOSELEAF INTERMEDIATE ACCOUNTING; CONNECT ACCESS CARD

Ch. 5 - Prob. 5.11QCh. 5 - Is a customers right to return merchandise a...Ch. 5 - Prob. 5.13QCh. 5 - Under what circumstances should sellers consider...Ch. 5 - When should a seller view a payment to its...Ch. 5 - What are three methods for estimating stand-alone...Ch. 5 - When is revenue recognized with respect to...Ch. 5 - In a franchise arrangement, what are a franchisors...Ch. 5 - When does a company typically recognize revenue...Ch. 5 - Prob. 5.20QCh. 5 - Prob. 5.21QCh. 5 - Prob. 5.22QCh. 5 - Must bad debt expense be reported on its own line...Ch. 5 - Explain the difference between contract assets,...Ch. 5 - Explain how to account for revenue on a long-term...Ch. 5 - Prob. 5.26QCh. 5 - Prob. 5.27QCh. 5 - What are the two general criteria that must be...Ch. 5 - Explain why, in most cases, a seller recognizes...Ch. 5 - Revenue recognition for most installment sales...Ch. 5 - Prob. 5.31QCh. 5 - How does a company report deferred gross profit...Ch. 5 - Prob. 5.33QCh. 5 - Briefly describe the guidelines for recognizing...Ch. 5 - Prob. 5.35QCh. 5 - Briefly describe the guidelines provided by GAAP...Ch. 5 - Revenue recognition at a point in time LO52 On...Ch. 5 - Timing of revenue recognition LO53 Estate...Ch. 5 - Prob. 5.3BECh. 5 - Allocating the transaction price LO54 Sarjit...Ch. 5 - Existence of a contract LO5-5 Tulane Tires wrote...Ch. 5 - Prob. 5.6BECh. 5 - Prob. 5.7BECh. 5 - Performance obligations; warranties LO55 Vroom...Ch. 5 - Prob. 5.9BECh. 5 - Prob. 5.10BECh. 5 - Performance obligations; construction LO55...Ch. 5 - Prob. 5.12BECh. 5 - Prob. 5.13BECh. 5 - Variable consideration LO56 Leo Consulting enters...Ch. 5 - Variable consideration LO56 In January 2018,...Ch. 5 - Prob. 5.16BECh. 5 - Prob. 5.17BECh. 5 - Payment s by the seller to the customer LO56...Ch. 5 - Estimating stand-alone selling prices: adjusted...Ch. 5 - Estimating stand-alone selling prices: expected...Ch. 5 - Estimating stand-alone selling prices; residual...Ch. 5 - Timing of revenue recognition; licenses LO57 Saar...Ch. 5 - Prob. 5.23BECh. 5 - Prob. 5.24BECh. 5 - Timing of revenue recognition; franchises LO57...Ch. 5 - Timing of revenue recognition; bill-and-hold LO57...Ch. 5 - Prob. 5.27BECh. 5 - Prob. 5.28BECh. 5 - Contract assets and contract liabilities LO58...Ch. 5 - Prob. 5.30BECh. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Prob. 5.32BECh. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Long-term contract; revenue recognition; loss on...Ch. 5 - Installment sales method On July 1, 2018, Apache...Ch. 5 - Prob. 5.36BECh. 5 - Cost recovery method Refer to the situation...Ch. 5 - Prob. 5.38BECh. 5 - Prob. 5.39BECh. 5 - Revenue recognition; software contracts under IFRS...Ch. 5 - Prob. 5.41BECh. 5 - Prob. 5.1ECh. 5 - Prob. 5.2ECh. 5 - Allocating transaction price LO54 Video Planet...Ch. 5 - Prob. 5.4ECh. 5 - Prob. 5.5ECh. 5 - Prob. 5.6ECh. 5 - Prob. 5.7ECh. 5 - Prob. 5.8ECh. 5 - Prob. 5.9ECh. 5 - Variable considerationmost likely amount; change...Ch. 5 - Variable considerationexpected value; change in...Ch. 5 - Prob. 5.12ECh. 5 - Approaches for estimating stand-alone selling...Ch. 5 - FASB codification research LO56, LO57 Access the...Ch. 5 - Franchises; residual method LO56, LO57 Monitor...Ch. 5 - FASB codification research LO58 Access the FASB...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Income (loss) recognition; Long-term contract;...Ch. 5 - Long-term contract; revenue recognition over time;...Ch. 5 - Installment sales method Charter Corporation,...Ch. 5 - Installment sales method; journal entries [This is...Ch. 5 - Installment sales; alternative recognition methods...Ch. 5 - Journal entries; point of delivery, installment...Ch. 5 - Prob. 5.27ECh. 5 - Prob. 5.28ECh. 5 - Prob. 5.29ECh. 5 - Prob. 5.30ECh. 5 - Prob. 5.31ECh. 5 - Prob. 5.32ECh. 5 - Prob. 5.33ECh. 5 - Prob. 5.34ECh. 5 - Prob. 5.35ECh. 5 - Prob. 5.1PCh. 5 - Prob. 5.2PCh. 5 - Prob. 5.3PCh. 5 - Prob. 5.4PCh. 5 - Prob. 5.5PCh. 5 - Variable consideration; change of estimate LO53,...Ch. 5 - Prob. 5.7PCh. 5 - Prob. 5.8PCh. 5 - Prob. 5.9PCh. 5 - Long-term contract; revenue recognition over time ...Ch. 5 - Long-term contract; revenue recognition upon...Ch. 5 - Long-term contract; revenue recognized over time;...Ch. 5 - Long-term contract; revenue recognition over time...Ch. 5 - Income statement presentation; installment sales...Ch. 5 - Prob. 5.15PCh. 5 - Installment sales; alternative recognition methods...Ch. 5 - Installment sales and cost recovery methods...Ch. 5 - Prob. 5.18PCh. 5 - Franchise sales; installment sales method Olive...Ch. 5 - Prob. 5.1BYPCh. 5 - Judgment Case 52 Satisfaction of performance...Ch. 5 - Judgment Case 53 Satisfaction of performance...Ch. 5 - Prob. 5.4BYPCh. 5 - Prob. 5.5BYPCh. 5 - Prob. 5.6BYPCh. 5 - Prob. 5.8BYPCh. 5 - Prob. 5.9BYPCh. 5 - Prob. 5.10BYPCh. 5 - Prob. 5.11BYPCh. 5 - Prob. 5.12BYPCh. 5 - Prob. 5.13BYPCh. 5 - Prob. 5.14BYPCh. 5 - Prob. 5.15BYPCh. 5 - Prob. 5.16BYPCh. 5 - Prob. 5.19BYPCh. 5 - Prob. 1CCTC
Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
SWFT Individual Income Taxes
Accounting
ISBN:9780357391365
Author:YOUNG
Publisher:Cengage
Depreciation -MACRS; Author: Ronald Moy, Ph.D., CFA, CFP;https://www.youtube.com/watch?v=jsf7NCnkAmk;License: Standard Youtube License