To calculate: Cost per square feet of finished product.
2.
To determine
In which department the most production cost occurred whether in Finishing Department or Polishing Department.
3.
To determine
Gross profit per square foot of company G during the month of May.
4.
To determine
Total gross profit on countertops produced in May.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Northern Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow:
(Click icon to view data)
Requirement
Calculate the total variable costs of producing 2, 4, and 8 units.
Begin by calculating the cumulative total time in labor-hours using the cumulative average-time learning model. (Round the cumulative average time per unit to the nearest whole number.)
Cumulative number of Cumulative average time
Cumulative total time:
per unit: Labor-hours
Labor-hours
3700
units
2
4
8
3700
←
Data table
Direct material cost
Direct manufacturing labor time for first unit
Learning curve for manufacturing labor time per radar system
Direct manufacturing labor cost
Variable manufacturing overhead cost
Using the formula for an 85% learning curve, b =
In 0.85
In 2
Print
=
$
$
$
-0.162519
0.693147
81,000 per unit of RS-32
3,700 direct manufacturing labor-hours
85% cumulative average timeª
Done
28 per direct…
Average labor cost for the first 700 units of a product is RO 50 and the average labor cost of first 1400 units is RO 45. Average time per unit is 100 minutes. The learning ratio and the average labour cost for first 2800 units will be:
a.
80% and RO 36.000
b.
90% and RO 40.500
c.
85% and RO 38.250
d.
95% and RO 42.750
Your company has received an order for 20 units of aproduct. Th e labor cost to produce the item is $9.50 per hour. Th esetup cost for the item is $60 and material costs are $25 per unit. Th e item is sold for $92. Th e learning rate is 80 percent. Overheadis assessed at a rate of 55 percent of unit labor cost.(a) Determine the average unit cost for the 20 units if the fi rstunit takes four hours.(b) Determine the minimum number of units that need to bemade before the selling price meets or exceeds the averageunit cost.
Chapter 5 Solutions
Managerial Accounting (5th Edition)
Ch. 5 - (Learning Objective 1) Which of the following is...Ch. 5 - (Learning Objective 2) Conversion costs consist of...Ch. 5 - (Learning Objective 2) Which of the following is...Ch. 5 - (Learning Objective 3) Which of the following is...Ch. 5 - Prob. 5QCCh. 5 - (Learning Objective 4) The journal entry needed to...Ch. 5 - (Learning Objective 4) A company has two...Ch. 5 - Prob. 8QCCh. 5 - Prob. 9QCCh. 5 - Prob. 10QC
Ch. 5 - Compare job costing and process costing (Learning...Ch. 5 - Prob. 5.2SECh. 5 - Prob. 5.3SECh. 5 - Determine the physical flow of units (process...Ch. 5 - Compute equivalent units (process costing Step 2)...Ch. 5 - Compute equivalent units (process costing Step 2)...Ch. 5 - Summarize total costs to account for (process...Ch. 5 - Prob. 5.8SECh. 5 - Prob. 5.9SECh. 5 - Prob. 5.10SECh. 5 - Prob. 5.11SECh. 5 - Prob. 5.12SECh. 5 - Prob. 5.13SECh. 5 - Prob. 5.14SECh. 5 - Prob. 5.15SECh. 5 - Prob. 5.16SECh. 5 - Continuation of S5-16: Record journal entry and...Ch. 5 - Compute equivalent units in second department...Ch. 5 - Prob. 5.19SECh. 5 - Prob. 5.20SECh. 5 - Prob. 5.21SECh. 5 - Prob. 5.22SECh. 5 - Analyze flow of costs through inventory T-accounts...Ch. 5 - Summarize physical units and compute equivalent...Ch. 5 - Prob. 5.25AECh. 5 - Prob. 5.26AECh. 5 - Continuation of E5-26A: Journal entries (Learning...Ch. 5 - Complete the production cost report in first...Ch. 5 - Prob. 5.29AECh. 5 - Analyze costs and gross profit in a process...Ch. 5 - Prob. 5.31AECh. 5 - Compute equivalent units and assign costs...Ch. 5 - Complete five-step procedure in first department...Ch. 5 - Sustainability and process costing (Learning...Ch. 5 - Complete five-step procedure and journalize result...Ch. 5 - Complete five-step procedure in second department...Ch. 5 - Exercises Group B E5-37B Analyze flow of costs...Ch. 5 - Summarize physical units and compute equivalent...Ch. 5 - Prob. 5.39BECh. 5 - Complete five-step procedure in first department...Ch. 5 - Prob. 5.41BECh. 5 - Prob. 5.42BECh. 5 - Prob. 5.43BECh. 5 - Prob. 5.44BECh. 5 - Record journal entries (Learning Objective 4)...Ch. 5 - Compute equivalent units and assign costs...Ch. 5 - Prob. 5.47BECh. 5 - Sustainability and process costing (Learning...Ch. 5 - Complete five-step procedure and journalize result...Ch. 5 - Complete five-step procedure in second department...Ch. 5 - Process costing in a single processing department...Ch. 5 - Process costing in a first department (Learning...Ch. 5 - Prob. 5.53APCh. 5 - Prepare a production cost report and journal...Ch. 5 - Prob. 5.55APCh. 5 - Process costing in a single processing department...Ch. 5 - Process costing in a first department (Learning...Ch. 5 - Prob. 5.58BPCh. 5 - Prepare a production cost report and journal...Ch. 5 - Prob. 5.60BPCh. 5 - Prob. 5.61SCCh. 5 - Discussion Questions 1. What characteristics of...Ch. 5 - Prob. 5.63ACTCh. 5 - Prob. 5.64ACTCh. 5 - Process costing and hybrid costing issues...
Knowledge Booster
Similar questions
- Bordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardI have the following information: direct materials $250 and total manufacturing cost $700. Overhead applied to jobs at a rate of 200% of direct labor cost. This is for Chapter 2 job costing in managerial accounting. I am supposed to figure out conversion cost, direct labor cost, and manufacturing overhead. I know the formula for conversion cost= direct labor + manufacturing OH Prime cost= direct labor + direct materials How do I figure out direct labor cost with the given information? The learning objective states calcualte predetermined overhead rate, but I do not have estimated manufacturing cost and estimated labor. Can you please help? Thanks, Erica Gordonarrow_forwardLearning CurveBordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On aver-age, the first unit of a new design takes 600 hours. Direct labor is paid $25 per hour. Required:1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total pro-duction of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours,…arrow_forward
- The following information is provided to you: Time taken to produce first 8 shock pads 640 hours Time taken to produce first 16 shock pads 1200 hours Calculate the learning curve The following information is provided to you: Direct labour needed to make first machine. 1000 hoursLearning curve. 80%Direct labour cost. R300 per hourDirect materials cost. R180000 per machine Fixed cost for machines at each cumulative production R800000 Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all theunits) Calculate the total costs to manufacture 4 machinesarrow_forwardNorthern Defense manufactures radar systems. It has just completed the manufacture of its first newly designed system, RS-32. Manufacturing data for the RS-32 follow: Home Insert Page Layout Formulas Data Review View 1 Direct material cost 2 Direct manufacturing labor time for first unit 3 Learning curve for manufacturing labor time 4 Direct manufacturing labor cost 5 Variable manufacturing overhead cost $ 84,000 per unit of RS-32 4,400 direct manufacturing labor-hours 85% cumulative average time 27 per direct manufacturing labor-hour 13 per direct manufacturing labor-hour per radar system 2$ In 0.85 -0.162519 7 "Using the formula (page 391), for an 85% learning curve, b= In 2- 0.693147 =-0234465 Calculate the total variable costs of producing 2, 4, and 8 units.arrow_forwardto complete the first setup on a new machine took an employee 250 minutes. using 72% cumulative average - time learning curve indicated that the second setup on the new machine is expected to take. answer choices: a.) 110 minutes b.) 90 minutes c.) 180 minutes d.) 215 minutesarrow_forward
- Assume that at the beginning of 20x2, Cicleta trained the 2 assembly workers in a new approach that had the objective of increasing the efficiency of the assembly process. Cicleta also began moving toward a JIT purchasing and manufacturing system. When JIT is fully implemented, the demand for expediting is expected to be virtually eliminated. It is expected to take two to three years for full implementation. Assume that receiving cost is a step-fixed cost with steps of 1,500 orders. The other three activities employ resources that are acquired as used and needed. At the end of 20x2, the following results were reported for the four activities: Required: 1. Prepare a trend report that shows the non-value-added costs for each activity for 20x1 and 20x2 and the change in costs for the two periods. Discuss the reports implications. 2. Explain the role of activity reduction for receiving and for expediting. What is the expected value of SQ for each activity after JIT is fully implemented? 3. What if at the end of 20x2, the selling price of a competing product is reduced by 27 per unit? Assume that the firm produces and sells 20,000 units of its product and that its product is associated only with the four activities being considered. By virtue of the waste-reduction savings, can the competitors price reduction be matched without reducing the unit profit margin of the product that prevailed at the beginning of the year? If not, how much more waste reduction is needed to achieve this outcome? In this case, what price decision would you recommend?arrow_forwardHarriman Industries manufactures engines for the aerospace industry. It has completed manufacturing the first unit of the new ZX-9 engine design. Management believes that the 1,000 labor hours required to complete this unit are reasonable and is prepared to go forward with the manufacture of additional units. An 80 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: Required: 1. Set up a table with columns for cumulative number of units, cumulative average time per unit in hours, and the cumulative total time in hours. Complete the table for 1, 2, 4, 8, 16, and 32 units. (Round hours to one significant digit.) 2. What are the total variable costs of producing 1, 2, 4, 8, 16, and 32 units? What is the variable cost per unit for 1, 2, 4, 8, 16, and 32 units?arrow_forwardPart A: Note: You must complete part A before completing parts B and C. Genuine Spice Inc. began operations on January 1 of the current year. The company produces 8-ounce bottles of hand and body lotion called Eternal Beauty. The lotion is sold wholesale in 12-bottle cases for $100 per case. There is a selling commission of $20 per case. The January direct materials, direct labor, and factory overhead costs are as follows: DIRECT MATERIALS CostBehavior Unitsper Case Costper Unit Direct MaterialsCost per Case Cream base Variable 100 ozs. $0.02 $2.00 Natural oils Variable 30 ozs. 0.30 9.00 Bottle (8-oz.) Variable 12 bottles 0.50 6.00 $17.00 DIRECT LABOR Department CostBehavior Timeper Case Labor Rateper Hour Direct LaborCost per Case Mixing Variable 20 min $18.00 $6.00 Filling Variable 5 14.40 1.20 25min $7.20 FACTORY OVERHEAD Cost Behavior Total Cost Utilities Mixed $600 Facility lease…arrow_forward
- Sample Exercise opens EA2. Rene is working with the operations manager to determine what the standard labor cost is for a spice chest. He has watched the process from start to finish and taken detailed notes on what each employee does. The first employee selects and mills the wood, so it is smooth on all four sides. This takes the employee 1 hour for each chest. The next employee takes the wood and cuts it to the proper size. This takes 30 minutes. The next employee assembles and sands the chest. Assembly takes 2 hours. The chest then goes to the finishing department. It takes 1.5 hours to finish the chest. All employees are cross-trained so they are all paid the same amount per hour, $17.50. A. What are the standard hours per chest? B. What is the standard cost per chest for labor?arrow_forwardUse the following information to answer the next 2 questions: Henry Incorporated manufactures a high volume of identical flashlights called the Illumin-8. The company reported the following for the month of August: Physical Units Beginning work in process, August 1 18,000 Started during the August 90,000 Ending work in process, August 31 24,000 Materials are added at the beginning of the process. The beginning inventory was 60% complete with respect to conversion, and ending inventory was 90% complete with respect to conversion. 4. What is Henry's equivalent units for materials in August using the weighted average method? a. 84, 000. b. 90,000. c. 108, 000. d. 66,000. 5. What is Henry's equivalent units for conversion in August using the FIFO method? a. 98, 400. b. 94,800. c. 108, 000. d . 105,600.arrow_forwardThe following scenario relates to 5 questions. Bear Co has developed a new model of television. The estimated labour time for the first unit is 12 hours but a learning curve of 75% is expected to apply for the first eight units produced Note: The learning index for a 75% learning curve is-0-415. Overhead production costs must be estimated based on a previous model, the Leonardo, that was made by Bear Co. Production quantities and total overhead costs for the last four months of production of the Leonardo were as follows: Month Output Total overhead cost (units) $ September 1,800 278,200 October 2,000 310,000 November 1,700 252,900 December 1,000 200,000 The first phase of production has now been completed for the new television. The first unit actually took 12-5 hours to make and the total time for the first eight units was 34-3 hours, at which point the learning effect came to an end. What is the actual learning rate, and did the labour force learn more quickly or less quickly than…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Essentials of Business Analytics (MindTap Course ...StatisticsISBN:9781305627734Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. AndersonPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningManagerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub