Why is it recommended that the estimator begin a takeoff of concrete work by measuring the quantity of concrete in an item rather than the amount of formwork?
The reason recommended for the estimator to begin a takeoff of concrete work by measuring the quantity of concrete in an item rather than the formwork amount.
Explanation of Solution
Taking off concrete work must start with the estimator measuring the concrete as the actual concrete descriptions are usually given on the drawings, whereas the details of the formwork are not given. The estimator can then review the needs for the formwork by measuring and estimating the volume of concrete needed followed by the requirements of finishing.
Since only the area of forms in contact with the concrete is measured, at the time of the takeoff, the estimator does not have to review the descriptions of the forms design.
Want to see more full solutions like this?
Chapter 5 Solutions
Fundamentals Of Construction Estimating
- Why is it also preferable to measure the concrete and all other work associated with an item before going on to measure the concrete in another item?arrow_forwardHow is unit weight of concrete affected by its aggregates?arrow_forward1. Concrete in cubic yards? 2. No. 4 rebar in tons? 3. No. 6 rebar in tons? 4. Formwork in square footage?arrow_forward
- Hello! can you please help me with this? I'm stuck because we need to provide explanation and I don't know how to explain. Thank you in advance! Q: What is your process for testing the workability of concrete?arrow_forwardWhat is the maximum diameter of aggregate in cm?arrow_forwardWhat is the w/cm ratio of concrete produced using 225 kilograms of portland cement, 75 kilograms of Fly Ash, and 120 kilograms of water?arrow_forward
- Q1. What do we mean by curing concrete? What will happen if concrete is not cured?arrow_forwardEstimate the total amount of cost for concrete works (class “B”) based from the following given: 10-pcs of F1 (1.2m x 1.2m x 0.3 m) 10-pcs of C1 (0.3 m x 0.3 m x 4.1 m) Floor area of 100mm thk slab-on-grade = 53 sq.m The cost of cement (40kg per bag) = 210 per bag. The cost of sand is 710 per cubic meter. The cost of gravel is 1900 per cubic meter.arrow_forwardHow useful are concrete hollow blocks in construction and why is it important?arrow_forward
- How to do quantity surviying of concretesarrow_forwardHow is concrete consolidated?arrow_forwardPlease give me both a and b answers a. If a concrete with 28 day compressive strength of 4500 psi is being poured, then it how much strength would you expect after 7 days(assuming good curing conditions)? Explain how you obtain the 7 day strength? b. Briefly explain the effect of water to cement ratio on concrete strength?arrow_forward
- Fundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,Construction Materials, Methods and Techniques (M...Civil EngineeringISBN:9781305086272Author:William P. Spence, Eva KultermannPublisher:Cengage Learning