Chapter 19, Problem 19.24E

Waiting time. It’s a Dog’s World (IDW) makes toys for big breed puppies. IDW’s managers have recently learned that they can calculate the average waiting time for an order from the time an order is received till the time manufacturing starts. They have asked for your help and have provided the following information.

Expected number of orders for the product: 3,200

Manufacturing time per order: 5 hours

Annual machine capacity in hours: 18,000

  1. 1. Calculate the average waiting time per order.

Required

  1. 2. After learning about the average waiting time, IDW’s managers are confused. They do not understand why, if annual machine capacity is greater than the average number of orders for the product, there would be any waiting time at all. Write a memo to clarify the situation.
  2. 3. The managers have asked for your suggestions on what they can do to minimize or eliminate waiting time. How would you respond?
Blurred answer
Students have asked these similar questions
It’s a Dog’s World (IDW) makes toys for big breed puppies. IDW’s managers have recently learned that they can calculate the average waiting time for an order from the time an order is received till the time manufacturing starts. They have asked for your help and have provided the following information. Expected number of orders for the product: 3,200 Manufacturing time per order: 5 hours Annual machine capacity in hours: 18,000 Q. After learning about the average waiting time, IDW’s managers are confused. They do not understand why, if annual machine capacity is greater than the average number of orders for the product, there would be any waiting time at all. Write a memo to clarify the situation.
It’s a Dog’s World (IDW) makes toys for big breed puppies. IDW’s managers have recently learned that they can calculate the average waiting time for an order from the time an order is received till the time manufacturing starts. They have asked for your help and have provided the following information. Expected number of orders for the product: 3,200 Manufacturing time per order: 5 hours Annual machine capacity in hours: 18,000 Q. The managers have asked for your suggestions on what they can do to minimize or eliminate waiting time. How would you respond?
Nash Corporation manufactures and sells custom snowmobiles. From the time an order is placed till the time the snowmobile reaches the customer averages 50 days. This 50 days is spent as follows: Wait time: 10 days Move time: 5 days Process time: 15 days Queue time: 15 days Inspection time: 5 days What is Nash's manufacturing cycle efficiency (MCE) for its snowmobiles?

Chapter 19 Solutions

Horngren's Cost Accounting: A Managerial Emphasis (16th Edition)

Knowledge Booster
Background pattern image
Accounting
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Essentials of Business Analytics (MindTap Course ...
Statistics
ISBN:9781305627734
Author:Jeffrey D. Camm, James J. Cochran, Michael J. Fry, Jeffrey W. Ohlmann, David R. Anderson
Publisher:Cengage Learning
Text book image
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
How to Estimate Project Costs: A Method for Cost Estimation; Author: Online PM Courses - Mike Clayton;https://www.youtube.com/watch?v=YQ2Wi3Jh3X0;License: Standard Youtube License