Preparing a schedule of cost of goods manufactured and an income statement for a manufacturing company
Learning Objective 3
COGM: $182,000
Certain item descriptions and amounts are missing from the monthly schedule of cost of goods manufactured and income statement of Elly Manufacturing Company Fill in the blanks with the missing words, and replace the Xs with the correct amounts.
ELLY MANUFACTURING COMPANY | |||||
_________________________________ | |||||
_________June 30, 2018 | |||||
Beginning ____________ | $27,000 | ||||
Direct _________: | |||||
Beginning Direct Materials | $X | ||||
Purchases of Direct Materials | 56,000 | ||||
____________________ | 84,000 | ||||
Ending Direct Materials | (20,000) | ||||
Direct___________ | $X | ||||
Direct __________ | X | ||||
Manufacturing |
44,000 | ||||
Total ______ Costs _____ | 180,000 | ||||
Total ______ Costs _____ | X | ||||
Ending _________________ | (25,000) | ||||
________________________ | $X |
ELLY MANUFACTURING COMPANY | ||||||
________________________________________ | ||||||
_________June 30, 2018 | ||||||
Net Sales revenue | $X | |||||
Cost of Goods Sold: | ||||||
Beginning ________________________________ | $110,000 | |||||
Cost of Goods _______________________________ | X | |||||
Ending ______________________________ | X | |||||
Cost of Goods Sold | X | 232,000 | ||||
Gross Profit | 258,000 | |||||
______________________ Expenses: | ||||||
Selling Expenses | 98,000 | |||||
Administrative Expenses | X | |||||
Total________________ | 160,000 | |||||
____________ Income | $X |
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
4:40 W W
n
s16-9
Learning Objective 3
Direct Materials Used
Use the following inventory data for Caddy Golf Company to compute the cost
of goods manufactured for the year:
Manufacturing Overhead
Work-in-Process Inventory:
Beginning Balance
Ending Balance
Direct Labor
Finished Goods Inventory:
Beginning Balance
Ending Balance
со
888/1480
G
Q5G all 75%
Word
Bit
QAA
$ 12,000
21,000
1,000
5,000
9,000
18,000
4,000
||| 0 <
:
X
S17-8 Completing and selling products
Learning Objective 4
Lincoln Company completed jobs that cost $38,000 to produce. In the same
period, the company sold jobs for $88,000 that cost $42,000 to produce. Prepare
the journal entries for the completion and sales of the jobs. All sales are on
account.
https://elearn.squ.edu.om/mod/quiz/attempt.php?attempt3D1764
EMIC)
E-LEARNING SERVICES -
SQU LIBRARIES
SQU PORTAL ATTEND
Time left 1:56:15
O c. Finished Goods to be understated by OMR 12,000
the year.
O d. Cost of Goods Manufactured to be overstated by OMR 12,000 for
the year.
Work in Process to be understated by OMR 12,000 at year end.
A Company uses job order costing and has chosen direct labor hours to
allocate its manufacturing overhead. The company estimates that total
direct labor hours to be operated next year are 300,000 hours. The
estimated variable overhead is $10 per hour and the estimated fixed
overhead costs are $500,000. The predetermined overhead rate is:
O a. None of the answers given
O b. S16.67
Oc. $11.67
O d. $7
O e. $1.67
OUS PAGE
NEXT PAGE
Chapter 18 Solutions
Horngren's Accounting (12th Edition)
Ch. 18 - Prob. 1QCCh. 18 - Prob. 2QCCh. 18 - Dunaway Company reports the following costs for...Ch. 18 - Which of the following is a direct cost of...Ch. 18 - Which of the following is not part of...Ch. 18 - Which of the following accounts does a...Ch. 18 - Questions 7 and 8 use the data that follow....Ch. 18 - Questions 7 and 8 use the data that follow....Ch. 18 - World-class businesses use which of these systems...Ch. 18 - Prob. 10QC
Ch. 18 - What is the primary purpose of managerial...Ch. 18 - List six differences between financial accounting...Ch. 18 - Explain the difference between line positions and...Ch. 18 - Explain the differences between planning,...Ch. 18 - Prob. 5RQCh. 18 - Describe a service company, and give an example.Ch. 18 - Describe a merchandising company, and give an...Ch. 18 - How do manufacturing companies differ from...Ch. 18 - List the three inventory accounts used by...Ch. 18 - Explain the difference between a direct cost and...Ch. 18 - What are the three manufacturing costs for a...Ch. 18 - Give five examples of manufacturing overhead.Ch. 18 - What are prime costs? Conversion costs?Ch. 18 - What are product costs?Ch. 18 - How do period costs differ from product costs?Ch. 18 - How is cost of goods manufactured calculated?Ch. 18 - How does a manufacturing company calculate cost of...Ch. 18 - How does a manufacturing company calculate unit...Ch. 18 - How does a service company calculate unit cost per...Ch. 18 - How does a merchandising company calculate unit...Ch. 18 - Prob. S18.1SECh. 18 - Prob. S18.2SECh. 18 - Distinguishing between direct and indirect costs...Ch. 18 - Computing manufacturing overhead Learning...Ch. 18 - Identifying product costs and period costs...Ch. 18 - Computing cost of goods sold, merchandising...Ch. 18 - Computing cost of goods sold and operating income,...Ch. 18 - Prob. S18.8SECh. 18 - Prob. S18.9SECh. 18 - Prob. S18.10SECh. 18 - S18-11 Matching business trends...Ch. 18 - Prob. S18.12SECh. 18 - Prob. E18.13ECh. 18 - Prob. E18.14ECh. 18 - Prob. E18.15ECh. 18 - Prob. E18.16ECh. 18 - Identifying differences between service,...Ch. 18 - Prob. E18.18ECh. 18 - Computing cost of goods manufactured Learning...Ch. 18 - Prob. E18.20ECh. 18 - Prob. E18.21ECh. 18 - Prob. E18.22ECh. 18 - Prob. E18.23ECh. 18 - Prob. E18.24ECh. 18 - Prob. P18.25APGACh. 18 - Classifying period costs and product costs...Ch. 18 - Calculating cost of goods sold for merchandising...Ch. 18 - Prob. P18.28APGACh. 18 - Preparing a schedule of cost of goods manufactured...Ch. 18 - Prob. P18.30APGACh. 18 - Prob. P18.31APGACh. 18 - Prob. P18.32APGACh. 18 - Prob. P18.33BPGBCh. 18 - Prob. P18.34BPGBCh. 18 - Prob. P18.35BPGBCh. 18 - Prob. P18.36BPGBCh. 18 - Prob. P18.37BPGBCh. 18 - Prob. P18.38BPGBCh. 18 - Prob. P18.39BPGBCh. 18 - Prob. P18.40BPGBCh. 18 - Prob. P18.41CTCh. 18 - Prob. P18.42CPCh. 18 - Prob. 18.1TIATCCh. 18 - Prob. 18.1DCCh. 18 - Prob. 18.1EI
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- 116 chapter 17 Learning Objectives 2, 3, 4, 5 4. COGM $46,750 5. NI $19,150 P17-38B Preparing comprehensive accounting for manufacturing transactions Teacher Stars produces stars for elementary teachers to reward their students. Teacher Stars' trial balance on June 1 follows: Account Title Cash Accounts Receivable Inventories: Raw Materials Work-in-Process Finished Goods Plant Assets TEACHER STARS Trial Balance June 1, 2016 Accumulated Depreciation Accounts Payable Wages Payable Common Stock Retained Earnings Sales Revenue Cost of Goods Sold Manufacturing Overhead Selling and Administrative Expenses Balance June transactions are summarized as follows: a. Collections on account, $153,000. Debit $ 14,000 150,000 5,600 42.500 20,700 240,000 Job 120: Paper, $ 800 Job 121: Paper, $7,900 Indirect materials, $1,600 June 1 balances in the subsidiary ledgers were as follows: • Raw Materials Inventory subsidiary ledger: Paper, $4,300; indirect materials, $1,300 • Work-in-Process Inventory…arrow_forwardE3-25A Analyze manufacturing overhead (Learning Objectives 3 & 5) Smith Foundry in Columbus, Ohio, uses a predetermined manufacturing overhead rate to allocate overhead to individual jobs based on the machine hours required. At the begin- ning of the year, the company expected to incur the following: Manufacturing overhead costs Direct labor cost Machine hours $ 630,000 $1,650,000 90,000 ********e** At the end of the year, the company had actually incurred the following: Direct labor cost Depreciation on manufacturing plant and equipment Property taxes on plant Sales salaries ... $1,230,000 $ 480,000 $ 19,500 $ 26,500 Delivery drivers' wages Plant janitors' wages 17,000 %24 8,500 Machine hours 56,500 hours Requirements 1. Compute Smith's predetermined manufacturing overhead rate. 2. How much manufacturing overhead was allocated to jobs during the year? 3. How much manufacturing overhead was incurred during the year? Is manufacturing overhead underallocated or overallocated at the end…arrow_forwardLearning Objectives 2, 3, 4 1. Total cost per EUP $2.26 3. WIP Balance $1,836 Open with P18-38B Preparing a production cost report, two materials added at different points, no beginning WIP or costs transferred in; journal entries Bryan's Exteriors produces exterior siding for homes. The Preparation Department begins with wood, which is chopped into small bits. At the end of the process, an adhesive is added. Then the wood/adhesive mixture goes on to the Compression Department, where the wood is compressed into sheets. Conversion costs are added evenly throughout the preparation process. January data for the Preparation Department are as follows: UNITS Beginning Work-in-Process Inventory Started in production Completed and transferred out to Compression in January Ending Work-in-Process inventory (35% of the way through the preparation process) COSTS Beginning Work-in-Process Inventory Costs added during January: Wood Adhesives Direct labor Manufacturing overhead allocated Total costs…arrow_forward
- Problem: Module 6 Textbook Problem 6 Learning Objective: 6-3 Make appropriate outsourcing decisions Benson Electronics currently produces the shipping containers it uses to deliver the electronics products it sells. The monthly cost of producing 9,400 containers follows. Unit-level materials Unit-level labor Unit-level overhead Product-level costs* Allocated facility-level costs $ 6,600 6,300 4,000 9,900 26,400 *One-third of these costs can be avoided by purchasing the containers. Russo Container Company has offered to sell comparable containers to Benson for $2.80 each. Required a. Calculate the total relevant cost. Should Benson continue to make the containers? b. Benson could lease the space it currently uses in the manufacturing process. If leasing would produce $12,400 per month, calculate the total avoidable costs. Should Benson continue to make the containers? a. Total relevant cost Should Benson continue to make the containers? b. Total avoidable cost Should Benson continue to…arrow_forwardFA-22A Using ABC to bill clients at a service firm (Learning Objective 2) Kushner & Company is an architectural firm specializing in home remodeling for private clients and new office buildings for corporate clients. Kushner charges customers at a billing rate equal to 130% of the client's total job cost. A client's total job cost is a combination of (1) professional time spent on the client ($63 per hour cost of employing each professional) and (2) operating overhead allocated to the client's job. Kushner allocates operating overhead to jobs based on professional hours spent on the job. Kushner estimates its five professionals will incur a total of 10,000 professional hours working on client jobs during the year. All operating costs other than professional salaries (travel reimbursements, copy costs, secretarial salaries, office lease, and so forth) can be assigned to the three activities. Total activity costs, cost drivers, and total usage of those cost drivers are estimated as…arrow_forwardProblem: Module 6 Textbook Problem 6 Learning Objective: 6-3 Make appropriate outsourcing decisions Perez Electronics currently produces the shipping containers it uses to deliver the electronics products it sells. The monthly cost of producing 9.200 containers follows. Unit-level materials Unit-level labor Unit-level overhead Product-level costs Allocated facility-level costs $5,400 6,800 4,100 9,600 27,900 "One-third of these costs can be avoided by purchasing the containers. Russo Container Company has offered to sell comparable containers to Perez for $2.80 each.. Required a. Calculate the total relevant cost. Should Perez continue to make the containers? b. Perez could lease the space it currently uses in the manufacturing process. If leasing would produce $11,700 per month, calculate the total avoidable costs. Should Perez continue to make the containers? a Total relevant cost Should Perez continue to make the containers? b. Total avoidable cost Should Perez continue to make the…arrow_forward
- LEARNING UNIT 1 REVISION EXERCISE 2 Rainbow Ltd produces two products known as Bubbles and Candy. Bubbles is manufactured in department one and Candy is manufactured in department two. The following information is available for August 2019: STANDARD MATERIAL COSTS Material A R3 per kg Material B R4 per kg Direct Labour R5 per hour STANDARD MATERIAL AND LABOUR USAGE BUBBLES CANDY Material A Material B Direct Labour 5 kg 8 kg 10 hours 7 kg 9 kg 15 hours FINISHED GOODS BUBBLES CANDY Forecast sales units Selling price per unit Required closing inventory (units) Opening inventory (units) 8 000 R160 1 500 500 3 000 R220 200 100 DIRECT MATERIALS MATERIAL A MATERIAL B Opening inventory (kg) Required closing inventory (kg) 8 700 9 000 1 700 1 800 Prepare the following budgets for August 2019: Sales…arrow_forwardCalculate a job cost using ABC (Learning Objective 2)Oliver Industries, a small, family-run manufacturer, has adopted an ABC system . The fol- lowing manufacturing activities, indirect manufacturing costs, and usage of cost drivers have been estimated for the year :54-7Direct materials ................................................................................ ? Direct labor ...................................................................................... ? Manufacturing overhead ...... .......... .......... ............. ................. .......... ? Total job cost .................................................................................... $?Classifying costs within the cost hierarchy (Learning Objective 2) Classify each of the following costs as either unit-level, batch-level, product-level, orfacility-level.a. Engineering costs for new productb. Order processingc. Depreciation on factoryd. Direct labore. Shipment of an order to a customerf. Product line manager…arrow_forwardLearning Objectives 2, 3, 4 1. Total EUP for CC 2,850 3. WIP Balance $1,145 P18-31A Preparing a production cost report, two materials added at different points, no beginning WIP or costs transferred in; journal entries Smith's Exteriors produces exterior siding for homes. The Preparation Department begins with wood, which is chopped into small bits. At the end of the process, an adhesive is added. Then the wood/adhesive mixture goes on to the Compression Department, where the wood is compressed into sheets. Conversion costs are added evenly throughout the preparation process. January data for the Preparation Department are as follows: UNITS Beginning Work-in-Process Inventory Started in production Completed and transferred out to Compression in January Ending Work-in-Process inventory (30% of the way through the preparation process) COSTS Beginning Work-in-Process Inventory Costs added during January Wood Adhesives Direct labor Manufacturing overhead allocated Total costs Requirements…arrow_forward
- eleam.squ.euu.om/mod/qu12/attempt.p learning System (Academic) stion 3 Company XYZ uses machine hours to allocate its manufacturing overhead. The company estimates that total machine hours to be operated next year are 190,000 hours. The estimated variable overhead is $9 per hour and the estimated fixed overhead costs are $152,000. Calculate wer saved ked out of 2 the predetermined overhead rate. lag question Select one: O a. $9.80 O b. $0.80 O c. $10.80 O d. $0.10 O e. None of the answers given Clear my choicearrow_forwardE4-23A Use ABC to allocate manufacturing overhead (Learning Objective 2) Several years after reengineering its production process, Biltmore Corporation hired a new controller, Rachael Johnson. She developed an ABC system very similar to the one used by Biltmore’s chief rival, Westriver. Part of the reason Johnson developed the ABC system was because Biltmore’s profits had been declining even though the company had shifted its product mix toward the product that had appeared most profitable under the old system. Before adopting the new ABC system, Biltmore had used a plantwide overhead rate based on direct labor hours that was developed years ago. For the upcoming year, Biltmore’s budgeted ABC manufacturing overhead allocation rates are as follows: Activity Allocation Base Activity Cost Allocation Rate Materials handling # of parts $3.84 per part Machine setup # of setups $330.00 per setup Insertion of parts # of parts $30.00 per part Finishing Finishing DL hrs $54.00 per hour The…arrow_forwardCengageNOWv2 | Online teachin x 2 MindTap - Cengage Learning * + https://v2.cengagenow.com/ilmn/takeAssignment/takeAssignmentMain.do?invoker-assignments&takeAssignmentSession L... A Classwork eBook Cost of Materials Issuances Bravo Wire Enterprises is a manufacturer of electrical conductors. The following incomplete subsidiary ledger is for wire cable during July: a. Complete the materials issuances and balances for the wire cable subsidiary ledger. Assume a first-in, first-out cost flow. Received Receiving Report Number Received Quantity Received Unit Price Issued Materials Requisition Number Issued Quantity Issued Balance Amount Date Balance Quantity Balance Amount Balance Unit Price 309 200 $7.00 July 1 July 5 125 $750 $ 6.00 125 V 750 V 6.00 7401 240 July 10 422 400 $8.00 July 201 7639 325 July 26 b. Determine the balance of wire cable at the end of July, 1,280 c. Determine the total amount of materials transferred to Work in Process for July. 4.070 Check My Work Q Search 8 144 0 P…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education
Job Cost Sheet - Job Cost Accounting System; Author: Accounting Instruction, Help, & How To;https://www.youtube.com/watch?v=ElD8nKNXE1I;License: Standard Youtube License