Question
Chapter 15, Problem 15.12AE
1.
To determine
To compute: The traditional plantwide manufacturing
2.
To determine
To compute: The cost of the job using activity-based costing.
3.
To determine
To identify: Which cost would be better for a manager to use while doing cost estimates.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
In Class Assignment 1
AlSaleh has assigned overhead on a plantwide basis to its two products (Tables and Chairs) using
direct labor hours which are estimated to be 200,000 for the current year. The company has decided
to experiment with activity-based costing and has created two activity cost pools and related
activity cost drivers. These two cost pools are Ordering and receiving (cost driver is Purchase
orders) and machine setup (cost driver is number of setups). Overhead allocated to the ordering
and receiving cost pool is $200,000, and $800,000 is allocated to the machine setup cost pool.
Additional information related to these pools is as follows:
Cost Drivers
Tables
Chairs
Purchase orders
30,000
10,000
number of setups
10,000
30,000
a. Determine the amount of overhead assigned to the table product line and the chairs product
line using activity-based costing.
b. What amount of overhead would be assigned to the tables and chairs product lines using
the traditional approach,…
I have the following information: direct materials $250 and total manufacturing cost $700. Overhead applied to jobs at a rate of 200% of direct labor cost. This is for Chapter 2 job costing in managerial accounting. I am supposed to figure out conversion cost, direct labor cost, and manufacturing overhead.
I know the formula for conversion cost= direct labor + manufacturing OH
Prime cost= direct labor + direct materials
How do I figure out direct labor cost with the given information? The learning objective states calcualte predetermined overhead rate, but I do not have estimated manufacturing cost and estimated labor. Can you please help?
Thanks,
Erica Gordon
Activity-Based Costing
Slack Corporation has the following predicted indirect costs and cost drivers for the year for the given activity cost pools:
Maintenance
Materials handling
Machine setups
Inspections
Machine hours
Material moves
Machine setups
Inspection hours
Fabrication Department Finishing Department Cost Driver
Machine hours
Material moves
Direct materials cost
Direct labor cost
Machine hours (Fabrication)
Machine hours (Finishing)
Materials moves
Machine setups
Inspection hours
$150,000
The following activity predictions were also made for the year:
Fabrication Department Finishing Department
Direct materials
Direct labor
$50,000
30,000
70,000
It is assumed that the cost per unit of activity for a given activity does not vary between departments. Slack's president, Charles Slack, is trying to
evaluate the company's product mix strategy regarding two of its five product models, ZX300 and SL500. The company has been using a company-
wide overhead rate based on machine hours…
Chapter 15 Solutions
Managerial Accounting (5th Edition)
Ch. 15 - (Learning Objective 1) Which of the following is...Ch. 15 - (Learning Objective 1) Which of the following...Ch. 15 - Prob. 3QCCh. 15 - Prob. 4QCCh. 15 - (Learning Objective 2) What is the current status...Ch. 15 - (Learning Objective 2) Which of the following...Ch. 15 - Prob. 7QCCh. 15 - Prob. 8QCCh. 15 - Prob. 9QCCh. 15 - Prob. 10QC
Ch. 15 - Prob. 15.1SECh. 15 - Identify aspects within each G4 category on a GRI...Ch. 15 - Identify aspects within each G4 Social subcategory...Ch. 15 - Prob. 15.4SECh. 15 - Prob. 15.5SECh. 15 - Prob. 15.6SECh. 15 - Define key sustainability terms (Learning...Ch. 15 - Prob. 15.8SECh. 15 - Prob. 15.9AECh. 15 - Prob. 15.10AECh. 15 - Prob. 15.11AECh. 15 - Prob. 15.12AECh. 15 - Prob. 15.13AECh. 15 - Sustainability and cost behavior (Learning...Ch. 15 - Prob. 15.15AECh. 15 - Prob. 15.16AECh. 15 - Sustainability and budgeting (Learning Objective...Ch. 15 - Prob. 15.18AECh. 15 - Prob. 15.19AECh. 15 - Sustainability and capital investments (Learning...Ch. 15 - Sustainability and the statement of cash flows...Ch. 15 - Prob. 15.22AECh. 15 - Prob. 15.23BECh. 15 - Prob. 15.24BECh. 15 - Prob. 15.25BECh. 15 - Prob. 15.26BECh. 15 - Sustainability and process costing (Learning...Ch. 15 - Prob. 15.28BECh. 15 - Sustainability and CVP concepts (Learning...Ch. 15 - Prob. 15.30BECh. 15 - Prob. 15.31BECh. 15 - Prob. 15.32BECh. 15 - Prob. 15.33BECh. 15 - Sustainability and capital investments (Learning...Ch. 15 - Prob. 15.35BECh. 15 - Prob. 15.36BECh. 15 - Prob. 15.37APCh. 15 - Prob. 15.38APCh. 15 - Prob. 15.39BPCh. 15 - Prob. 15.40BPCh. 15 - Each year for the past six years, Caesars...Ch. 15 - Discussion Questions 1. Pressure to become more...Ch. 15 - Corporate Sustainability Reports Note: In the...Ch. 15 - Sustainability and investment choices...Ch. 15 - Ethics of internal sustainability reporting...Ch. 15 - FirstEnergy and its sustainability report...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Harriman Industries manufactures engines for the aerospace industry. It has completed manufacturing the first unit of the new ZX-9 engine design. Management believes that the 1,000 labor hours required to complete this unit are reasonable and is prepared to go forward with the manufacture of additional units. An 80 percent cumulative average-time learning curve model for direct labor hours is assumed to be valid. Data on costs are as follows: Required: 1. Set up a table with columns for cumulative number of units, cumulative average time per unit in hours, and the cumulative total time in hours. Complete the table for 1, 2, 4, 8, 16, and 32 units. (Round hours to one significant digit.) 2. What are the total variable costs of producing 1, 2, 4, 8, 16, and 32 units? What is the variable cost per unit for 1, 2, 4, 8, 16, and 32 units?arrow_forwardBordner Company manufactures HVAC (heating, ventilation, and air conditioning) systems for commercial buildings. For each new design, Bordner faces a 90 percent learning rate. On average, the first unit of a new design takes 600 hours. Direct labor is paid 25 per hour. Required: 1. Set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, and cumulative total time in hours. Show results by row for total production of one unit, two units, four units, eight units, and sixteen units. (Round hour answers to two significant digits.) 2. What is the total labor cost if Bordner makes the following number of units: one, four, sixteen? What is the average cost per system for the following number of systems: one, four, or sixteen? (Round your answers to the nearest dollar.) 3. Using the logarithmic function, set up a table with columns showing: the cumulative number of units, cumulative average time per unit in hours, cumulative total time in hours, and the time for the last unit. Show results by row for each of units one through eight. (Round answers to two significant digits.)arrow_forwardChurchill Products is considering updating its cost system to an activity-based costing system and is interested in understanding the effects. The company’s cost accountant has identified three overhead cost pools along with appropriate cost drivers for each pool. Cost Pools Costs Activity Drivers Utilities $ 310,000 62,000 machine-hours Scheduling and setup $ 290,000 580 setups Material handling $ 795,000 1,590,000 pounds of material The company manufactures three models of water basins (Oval, Round, and Square). The plans for production for the next year and the budgeted direct costs and activity by product line are as follows. Products Oval Round Square Total direct costs (material and labor) $80,000 $80,000 $70,000 Total machine-hours 30,000 10,000 22,000 Total number of setups 60 300 220 Total pounds of material 490,000 290,000 810,000 Total direct labor-hours 3,500 2,000 4,500 Number of units produced 4,400 2,000 6,000 Required: (Do not…arrow_forward
- Churchill Products is considering updating its cost system to an activity-based costing system and is interested in understanding the effects. The company’s cost accountant has identified three overhead cost pools along with appropriate cost drivers for each pool. Cost Pools Costs Activity Drivers Utilities $ 290,000 58,000 machine-hours Scheduling and setup 310,000 620 setups Material handling 805,000 1,610,000 pounds of material The company manufactures three models of water basins (Oval, Round, and Square). The plans for production for the next year and the budgeted direct costs and activity by product line are as follows. Products Oval Round Square Total direct costs (material and labor) $ 80,000 $ 90,000 $ 70,000 Total machine-hours 30,000 10,000 18,000 Total number of setups 80 320 220 Total pounds of material 460,000 320,000 830,000 Total direct labor-hours 3,500 1,500 5,000…arrow_forwardOriole Stairs Co.designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2025 are as follows. Overhead Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Activity Cost Pools Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines. For the last 4 years, Oriole Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2025, 100,000 machine hours are budgeted. Inspecting Inventory control (raw materials and finished goods) Utilities Jeremy Nolan, owner-manager of Oriole Stairs Co., recently directed his accountant, Bill Seagren, to…arrow_forwardOriole Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2025 are as follows. Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Overhead Cost Pools Total budgeted overhead costs Activity Cost Pools Purchasing Handling materials. Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Machine hours For the last 4 years, Oriole Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2025, 100,000 machine hours are budgeted. Direct materials Direct labor Jeremy Nolan, owner-manager of Oriole Stairs Co., recently…arrow_forward
- Oriole Stairs Co. designs and builds factory-made premium wooden stairways for homes. The manufactured stairway components (spindles, risers, hangers, hand rails) permit installation of stairways of varying lengths and widths. All are of white oak wood. Budgeted manufacturing overhead costs for the year 2025 are as follows. Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Overhead Cost Pools Inspecting Inventory control (raw materials and finished goods) Utilities Total budgeted overhead costs Purchasing Handling materials Production (cutting, milling, finishing) Setting up machines Inspecting Inventory control (raw materials and finished goods) Utilities Activity Cost Pools Direct labor For the last 4 years, Oriole Stairs Co. has been charging overhead to products on the basis of machine hours. For the year 2025, 100,000 machine hours are budgeted. Jeremy Nolan, owner-manager of Oriole Stairs Co., recently directed his accountant, Bill…arrow_forwardOle Company manufactures two products, Product A and Product B. Currently, machine hours are used to allocate the overhead costs to the two products. Ole Company is considering adopting an activity-based costing system. If so, overhead costs will be traced to the following activities: Activities Machining Quality Control Material Moves Activity cost pools $300,000 $200,000 $400,000 Cost Drivers Machine Hours Number of inspections Number of moves Product A 30,000 400 2,000 Product B 20,000 600 6,000 (a) Calculate the total overhead cost assigned to Product A under the current system. (b) Calculate the total overhead cost for Product A if the company implements activity-based costing system. (c) Briefly explain which costing method gives a more accurate picture of the costs. (d) Suppose you are the management accountant in a university. List any three (3)activities commonly carried out in universities and identify an appropriate cost driver for each activity.arrow_forwardUsing the following information for question 8-10 Honeydew Company produces two products, a high-end laptop computer under the label Bunsen Laptops, and an inexpensive desktop computer under the label Beaker Computers. The two products use two overhead activities, with the following costs: Setting up equipment Machining $2,000 12,000 The controller has collected the expected annual prime costs for each product, the machine hours, the setup hours, and the expected production. Direct Labor Direct Materials Expected Production in Units Machine hours Setup hours 8. Calculate Beaker's consumption ratio for setup hours. a. 0.50 b. 0.45 c. 0.90 d. 0.25 Bunsen Beaker $20,000 $5,000 15,000 4,000 2,000 2,000 750 1,500 50 50arrow_forward
- Asteroid produces and sells mountain bikes and has four keys products. this year, for the first time,it is operating an activity based costing system in parallel with its long-standing traditional costing system (which absorbs overheads on a machine hour basis). the planned production activity-based cost pools and cost driver activity levels for all the output for the year are as follow: Activity Cost Pool Activity Level Purchasing materials 750.000 5000 purchase orders Storing materials 800.000 1600 issue notes Setting up machinery 600.000 600 set-ups Running machinery 990.000 10.000 machine hours Total production overheads 3140.000 An analysis of actual production output for its two star products shows the following figures: Activity Tour Giro Units produced 1500 800 Purchase orders 1500 500 Store issue notes 800 400 Set-ups 235 100 Machine Hours 4000 3000 furthermore, cost in euro for direct material and hour for these two models are as follow:…arrow_forwardFisher Fixtures manufactures three types of lighting fixtures, with model names of Silver, Gold, and Platinum. It applies all indirect costs according to an annual predetermined rate based on direct labor-hours. The plant controller has recommended that the company switch to an activity-based costing system. The controller's staff prepared the following cost estimates for next year (year 2) for the recommended cost drivers. Activity Recommended Cost Driver Estimated Cost Estimated Cost Driver Activity Purchasing material Number of purchase orders $ 121,200 240 purchase orders Receiving material Direct materials cost 225,600 $ 2,820,000 Setting up equipment Number of production runs 219,360 120 runs Machine depreciation and maintenance Machine-hours 75,540 15,108 hours Ensuring regulatory compliance Number of inspections 437,400 54 inspections Shipping Number of units shipped 1,058,400 588,000 units Total estimated cost $ 2,137,500 In addition, management…arrow_forwardThe following information is provided to you: Time taken to produce first 8 shock pads 640 hours Time taken to produce first 16 shock pads 1200 hours Calculate the learning curve The following information is provided to you: Direct labour needed to make first machine. 1000 hoursLearning curve. 80%Direct labour cost. R300 per hourDirect materials cost. R180000 per machine Fixed cost for machines at each cumulative production R800000 Calculate the total direct hours required to manufacture four (4) machines. ( Indicate both average time per unit as well as cumulative time per unit for all theunits) Calculate the total costs to manufacture 4 machinesarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Excel Applications for Accounting PrinciplesAccountingISBN:9781111581565Author:Gaylord N. SmithPublisher:Cengage LearningCornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage LearningPrinciples of Accounting Volume 2AccountingISBN:9781947172609Author:OpenStaxPublisher:OpenStax College
Excel Applications for Accounting Principles
Accounting
ISBN:9781111581565
Author:Gaylord N. Smith
Publisher:Cengage Learning
Cornerstones of Cost Management (Cornerstones Ser...
Accounting
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:9781947172609
Author:OpenStax
Publisher:OpenStax College
Inspection and Quality control in Manufacturing. What is quality inspection?; Author: Educationleaves;https://www.youtube.com/watch?v=Ey4MqC7Kp7g;License: Standard youtube license