(a)
Interpretation:
The time period required on an average to finish the job.
Concept Introduction:
(a)
Explanation of Solution
Given information:
The owner of an in HM Catering Company has four jobs to deliver today, shown in the order in which they are received:
Job | Processing Time (hrs) | Due (hrs) |
Schedule the jobs based on the first come first served:
Hours | ||||||||||
Job |
From the table, it is observed that the flow time of the job
The flow time of the job
The flow time of the job
In order of the job
The flow time of the job
In order of the job
Thus, calculate the average flow time that is required to finish the each job:
Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;
(b)
Interpretation:
The job that will be late and the average job tardiness.
Concept Introduction:
Schedule the job on the basis of the
(b)
Explanation of Solution
Given information:
The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:
Job | Processing Time (hrs) | Due (hrs) |
Schedule the jobs based on the
Hours | ||||||||||
Job |
From the table, it can be observed that
Thus, calculate the average flow time that is required to finish the each job:
Now, calculating the average tardiness, adding the delay time of the order and divide it by the number of the orders;
(c)
Interpretation:
The job that will be late and the average job tardiness.
Concept Introduction:
Schedule the job on the basis of the
(c)
Explanation of Solution
Given information:
The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:
Job | Processing Time (hrs) | Due (hrs) |
Schedule the jobs based on the
Hours | ||||||||||
Job |
From the table, it can be observed that
Now, calculating the tardiness, adding the delay time of the order and divide it by the number of the orders;
Thus, calculate the average flow time that is required to finish the each job:
(d)
Interpretation:
The most efficient sequence from the
Concept Introduction:
The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.
(d)
Explanation of Solution
Given information:
The owner of an in home meal catering company has four jobs to deliver today, shown in the order in which they are received:
Job | Processing Time (hrs) | Due (hrs) |
The efficiency can be measured as the average tardiness or the number of jobs delayed and the average flow time.
Average flow time:
By comparing the average flow time, it is observed that
Average tardiness:
By comparing the average tardiness, it is observed that
Number of jobs delayed:
Both
Therefore, it depends on the owner which gives the priority to the most efficient method will vary.
Want to see more full solutions like this?
Chapter 14 Solutions
Practical Operations Management
- The first five columns of the following table contain information about a set of four jobs that just arrived (end of Hour 0 or beginning of Hour 1) at an engine lathe. They are the only ones now waiting to be processed. Several operations, including the one at the engine lathe, remain to be done on each job. Determine the schedule by using (a) the CR rule and (b) the S/RO rule. Compare these schedules to those generated by FCFS, SPT, and EDD. Job ProcessingTime at EngineLathe (hours) TimeRemainingUntil Due Date(days) Number ofOperationsRemaining Shop TimeRemaining(days) CR S/RO 1 2 3 4 2.3 10.5 6.2 15.6 15 10 20 8 10 2 12 5 6.1 7.8 14.5 10.2 2.46 1.28 1.38 0.78 0.89 1.10 0.46 -0.44arrow_forwardSix jobs are to be processed through a two-step operation. The first operation involves sanding, and the second involves painting. Processing times are as follows: Determine a sequence that will minimize the total completiontime for these jobs. Illustrate graphically.arrow_forwardA defense contractor in Dallas has six jobs awaiting processing. Processing time and due dates are given in the table. Assume that jobs arrive in the order shown. Compare the average completion time, utilization, average jobs in the system and average job lateness of the following scheduling rules. Start date is day 1. a) SPT: shortest processing time and b) EDD: earliest due datearrow_forward
- For a single machine scheduling problem, what priority rule guarantees that the average (mean) flow time is minimized?arrow_forwardSix ships are docked in a harbor awaiting unloading. The times required to unload the ships are random variables with respective means of 0.6, 1.2, 2.5, 3.5, 0.4, and 1.8 hours. The ships are given a priority weighting based on tonnage. The respective tonnages are 12, 18, 9, 14, 4, and 10. In what sequence should the ships be unloaded in order to minimize the expected weighted time?arrow_forwardThe following jobs are waiting to be processed at Rick Solano’s machine center. Solano’s machine center has a relatively long backlog and sets a fresh schedule every 2 weeks, which does not disturb earlier schedules. Below are the jobs received during the previous 2 weeks. They are ready to be scheduled today, which is day 241 (day 241 is a workday). Job names refer to names of clients and contract numbers. Job Date job received Productiondays needed Date job due BR-02 228 15 300 CX-01 225 25 270 DE-06 230 35 320 RG-05 235 40 360 SY-11 231 30 310 a. Complete the following table. (Show your supporting calculations.) b.Which dispatching rule has the best score for flow time? c. Which dispatching rule would you select? Support your decision.arrow_forward
- Analyze scheduling problems using priority rules and more specialized techniques.arrow_forwardwhere the consulting company has five jobs in its backlog. Create a schedule usingthe EDD rule, calculating the average days past due and flow time. In this case, does EDD outperformthe FCFS rule?arrow_forwardGiven the data below, using the SPT heuristic sequencing rule, determine the completion date and tardiness for each job as well as the average completion time and average tardiness for all four jobs. Which of the following statements is true? Job Processing time (days) Due date (in days) A 10 10 B 5 8 C 15 25 D 8 15 a.Jobs B and D will have no tardiness b.The tardiness for Job A is 12 days c.The average tardiness is 19.75 d.The average completion time is 6.5arrow_forward
- The operations manager of a body and paint shop has five cars to schedule for repair. The estimates of the times required to do the body and paint work on each are as follows: Using Johnson's Rule to minimize total duration, the correct sequence of these five jobs is; a. DCAEB b. DBECA c. BEACD d. ACEBD Car Body Work (Hours) Paint (Hours) A 8 7 B 9 4 C 7 9 D 3 4 E 12 5arrow_forwardIn her last semester at SPC, Polly Hedron needs to take Statistics, Composition 2, Ethics, and Physics. Because Polly is registering early, she has 14 choices for her section of Statistics, 19 choices for her section of Composition, 17 choices for her section of Ethics, and 18 choices for her section of Physics. From how many possible schedules can Polly choose? (You may presume that none of these sections interfere with each other) Your Answer:arrow_forwardSix patients are waiting in a hospital emergency room to receive care for various complaints, ranging from a sprained ankle to a gunshot wound. The patients are numbered in the sequence that they arrived and are given a priority weighting based on the severity of the problem. There is only one doctor available.Consider the situation of the emergency room mentioned. Determine the sequence in which patients should be treated in order to minimize the weighted value of the mean flow time.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.