Textbook Question
Chapter 13, Problem 8P
The professor from problem 6 is considering reducing the time for completion of the project. He can hire a teaching assistant (TA) to help with the new course, but this will cost additional money. The TA can help reduce the times only for activities A. D, and C. In each case the TA can reduce the time required by one day for $150 and two days for $300.
- a. Which activity should the TA perform to reduce the project completion time by one day?
- b. Can the network be crashed by two days in total? Explain why or why not?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
The client of a project has requested the project team to crash 8 hours of time. The table below provides the necessary information about the possible project crashing.
(a) What is the crash cost for 8 hours of time-savings?
(b) Assume the team calls the client and asks for a project extension, reducing the amount of time they need to crash. The project team has a $20 crash budget. Is the budget sufficient to crash 4 hours of time?
Activity
Normal
Duration (hours)
Normal
Cost ($)
Crash
Duration (hours)
Crash
Cost (S)
Immediate
Predecessors
A
2
10
2
0
None
B
3
15
2
23
A
C
5
25
4
30
B
D
3
20
1
24
C
E
6
30
4
45
C
F
1
5
1
0
E
G
7
35
6
50
F
H
10
50
7
80
D, G
Hoosier Burger Juan Rodriquez has assigned you the task of requirements determination for the Hoosier Burger project. You are looking forward to this opportunity because it will allow you to meet and interact with Hoosier Burger employees. Besides interviewing Bob and Thelma Mellankamp, you decide to collect information from Hoosier Burger’s waiters, cooks, and customers. Mr. Rodriquez suggests that you formally interview Bob and Thelma Mellankamp and perhaps observe them performing their daily management tasks. You decide that the best way to collect requirements from the waiters and cooks is to interview and observe them. You realize that discussing the order-taking process with Hoosier Burger employees and then observing them in action will provide you with a better idea of where potential system improvements can be made. You also decide to prepare a questionnaire to distribute to Hoosier Burger customers. Because Hoosier Burger has a large customer base, it would be impossible to…
What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days?
Normal
Cost
$800
$200
$600
$750
$1,200
Normal
Crash
Activity Time (days) Time (days)
4
3
8
6
The total cost of crashing the project by 4 days is $
ABCDE
487
355
(Enter your response as a whole number.)
Total Cost
with Crashing Immediate Predecessor(s)
$1,500
$1,650
By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.)
Each Activity Should be
Reduced BY
(days)
Activity
A
B
C
D
E
$1,100
$600
$650
A
C
Chapter 13 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 13 - How, precisely, does project scheduling differ...Ch. 13 - How would you, after the fact, audit a project to...Ch. 13 - Prob. 3DQCh. 13 - Contrast and compare CPM and PERT as...Ch. 13 - Define the terms critical path, ES, and LF.Ch. 13 - What is the management significance of finding the...Ch. 13 - Prob. 7DQCh. 13 - What is meant by the need to make trade-offs...Ch. 13 - Why are a forward pass and a backward pass needed...Ch. 13 - What is the definition of the earliest and latest...
Ch. 13 - A public accounting firm requires the following...Ch. 13 - The following activities are required in starting...Ch. 13 - A construction project has the following network...Ch. 13 - A plant start-up is based on the following...Ch. 13 - An entrepreneur is starting a new business. The...Ch. 13 - Prob. 6PCh. 13 - Construction of a building is based on the...Ch. 13 - The professor from problem 6 is considering...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- You are in charge of a project at the local community center. The center needs to remodel one of the rooms in time for the start of a new program. Delays in the project mean that the center must rent other space at a nearby church at additional cost. Time and cost data for your project are contained in 7.10. Your interest is in minimizing the cost of theproject to the community center.a. Using the normal times for each activity, what is the earliest date you can complete the project?b. Suppose the variable overhead costs are $50 per day for your project. Also, suppose that the center must pay $40 per day for a temporary room on day 15 or beyond. Find the minimum-cost project schedule.arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $8,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity Immediate Predecessor(s) A B с D E F G || D, E Normal Time Crash Time Normal Cost (weeks) ($) 3 7,000 2 3,000 3 12,000 4 12,000 1 8,000 6 5,000 3 9,000 (weeks) 1 2 1 3 1 4 2 D Crash Cost ($) 14,000 3,000 40,000 22,000 8,000 13,000 16,000arrow_forwardWhat is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Crash Activity Time (days) Time (days) A B C The total cost of crashing the project by 4 days is $. (Enter your response as a whole number.) E 5 8 6 5 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) 4 6 5 3 Activity A B C D E Normal Cost $800 $200 $600 $750 $1,200 Total Cost with Crashing Immediate Predecessor(s) $1,100 $400 $650 $1,500 $1,650 Each Activity Should be Reduced BY (days) ACarrow_forward
- The table below contains data for the installation of new equipment in a manufacturing process at Excello Corporation. Your company is responsible for the installation project. Indirect costs are $12,000 per week, and a penalty cost of $6,000 per week will be incurred by your company for every week the project is delayed beyond week 12. Activity A B с D E F G Immediate Predecessor(s) AB Activity A B с D A C D, E E Normal Time Crash Time (weeks) (weeks) 3 1 2 2 1 3 4 1 6 3 Time according to schedule (weeks) 1 a. What is the shortest time duration for this project regardless of cost? The shortest project duration regardless of cost is 9 weeks. (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? The minimum total cost to complete the project in 12 weeks is $ 203500. (Enter your response as a whole number.) c. What is the total time of the minimum-cost schedule? (Enter your responses as whole numbers.) The total…arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process a Excello Corporation. Your company is responsible for the installation project. Indirect costs are $10,000 per week, and a penalty cost of $9,000 per week will be incurred by your company for every week the project is delayed beyond week12. Activity Immediate Predecessor(s) ABCDEFG long dash- long dash- ABCDEFG A B C D, E E Normal Time Crash Time Normal Cost Crash Cost (weeks) (weeks) ($) ($) 1 14,000 2 3,000 1 40,000 3 22,000 1 8,000 4 13,000 2 16,000 3234 1 6 63 7,000 3,000 12,000 12,000 8,000 5,000 9,000 a. What is the shortest time duration for this project regardless of cost? (Enter your response as a whole number.) b. What is the minimum total cost associated with completing the project in 12 weeks? C. What is the total time of the minimum cost schedule? (enter your response as whole numbers). The total project's duration according to minimum cost schedule is? The minimum cost schedule…arrow_forwardA large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. ID Description A Survey B Soils report с Traffic design D Lot layout E Approve design F G Drainage H Landscape I Signage J Illumination Bid proposal The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 9 22 25 6 76 20 24 24 25 9 days. day(s).arrow_forward
- Three activities are candidates for crashing on a project network for a large computer installation (all are, of course, critical) Activity details are in the following table: a) Activity that should be orashed first to reduce the project duration by 1 day is b) Activity that should be crashed next to reduce the project duration by one additional day is c) Total cost of crashing the project by 2 days = S (Enter your response as an integer) Normal Activity Time (days) A B C 7 4 11 Crash Normal Time (days) Cost $8,000 $1,200 $4,200 6 2 9 Total Cost with Crashing Immediate Predecessor(s) $6,500 $3,000 $6.200 A Barrow_forwardYou are the project manager of the software installationproject in Table 7.12. You would like to find the minimum-costschedule for your project. There is a $1,000-per-week penaltyfor each week the project is delayed beyond week 25. In addi-tion, your project team determined that indirect project costsare $2,500 per week.a. What would be your target completion week?b. How much would you save in total project costs with yourschedule?arrow_forwardA project with total budget cost of 30 cr. is scheduled to be completed in 80 weeks. A periodic review was carried out at end of 60 weeks and results are as given: Budgeted cost of work performed = 17 cr. Actual Cost of work performed = 19 cr. Budgeted cost of work scheduled = 21 cr. What is the cost performance index? A.0.895 B.0.81 C.0.90 D.1.12arrow_forward
- A large Southeast city is requesting federal funding for a park-and-ride project. One of the requirements in the request application is a network plan for the design phase of the project. Sophie Kim, the chief engineer, wants you to develop a project network plan to meet this requirement. She has gathered the activity time estimates and their dependencies shown here. Description Survey Soils report C Traffic design D Lot layout E Approve design Illumination G Drainage H Landscape I Signage J Bid proposal ID A B The project is expected to take The critical path is: Early start for Activity E is: Late finish for Activity F is: Slack for Activity C is: Predecessor None A A A B, C, D E E E E F, G, H, I Time (days) 13 22 21 a 9 74 20 20 22 17 15 12 days. day(s).arrow_forwardYou are an electronic engineer who is working on the design, production and implementation of Digital electronic circuits for customers of an electronic company. You manager has given you two digital electronic circuits to analyze and explain their operations. You need to write a report for the manager so he can pass this on to the customers who will be using these circuits. The report should include a section for each circuit. Task 1 You manager has asked you to write a report to a customer who will be using the following digital circuits that implement combinational circuits in their operation: 1.. A one bit, 3 input majority counter (voter)Within your report, you need to explain and analyze the construction and operation of the circuit making sure the customer knows how it works in simple steps. You need to include in your report the truth table of the circuit and also need to use the Boolean Algebra/Karnaugh Map to minimize the number of gates used in the design and…arrow_forwardThe table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY