Textbook Question
Chapter 13, Problem 1P
A public accounting firm requires the following activities for an audit:
Activity | Immediate Predecessor | Activity Time |
A | – | 3 |
B | A | 2 |
C | – | 5 |
D | B, C | 2 |
E | A | 4 |
F | B, C | 6 |
G | E, D | 5 |
- a. Draw a network for this project.
- b. Make a forward pass and a backward pass to determine ES, LS, EF, and LF.
- c. What are the critical path and the project completion time?
- d. If the project completion must be reduced by two days, which activities might be affected?
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Using a suitable example each, describe what the following project planning process activities involve:
a. Establish project objective;
b. Define scope;
c. Create a Work Breakdown Structure (WBS);
d. Estimate activity durations; e. Sequencing activities.
By using Bar chart planning method, find the following:
- Total duration for the project activities shown below
- The project completion date (assume the start date is
1/3/2012
Activity
A
CDEFGHI
J
Duration
85 2846 7 45 6
(days)
Following
Activity
C,D EFGHIJJ
* If the project shown above had a delay of (4 days after
(13working days), what would its new delivery date be?
B
B
The following table shows estimates of activity times (in weeks) for a project:
b. What is the probability that the project will be completed within 33 weeks?
c. What is the probability that the project will be completed in more than 34 weeks?
Activity
d. What is the probability that the project will be completed in 35 weeks?
ABCDEFG
А
G
Optimistic Most Probable
Time
Time
5
6
3.5
4
3
6
7
5
9
4
6.5
Suppose that the critical path is A-C-E-F-G. Use Appendix A to answer the questions. Do not round intermediate calculations. Round your answers to three decimal places.
a. What is the probability that the project will be completed within 36 weeks?
6
10.5
Pessimistic
Time
7
4.5
5
10
9
7
15
Chapter 13 Solutions
OPERATIONS MANAGEMENT IN THE SUPPLY CHAIN: DECISIONS & CASES (Mcgraw-hill Series Operations and Decision Sciences)
Ch. 13 - How, precisely, does project scheduling differ...Ch. 13 - How would you, after the fact, audit a project to...Ch. 13 - Prob. 3DQCh. 13 - Contrast and compare CPM and PERT as...Ch. 13 - Define the terms critical path, ES, and LF.Ch. 13 - What is the management significance of finding the...Ch. 13 - Prob. 7DQCh. 13 - What is meant by the need to make trade-offs...Ch. 13 - Why are a forward pass and a backward pass needed...Ch. 13 - What is the definition of the earliest and latest...
Ch. 13 - A public accounting firm requires the following...Ch. 13 - The following activities are required in starting...Ch. 13 - A construction project has the following network...Ch. 13 - A plant start-up is based on the following...Ch. 13 - An entrepreneur is starting a new business. The...Ch. 13 - Prob. 6PCh. 13 - Construction of a building is based on the...Ch. 13 - The professor from problem 6 is considering...
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- You are the manager of a project to improve a billing processat your firm. Table 7.7 contains the data you will need toconduct a cost analysis of the project. Indirect costs are $1,600per week, and penalty costs are $1,200 per week after week 12.a. What is the minimum-cost schedule for this project?b. What is the difference in total project costs between the ear-liest completion time of the project using “normal” timesand the minimum-cost schedule you derived in part (a)?arrow_forwardJustify the use of earned value management (EVM) to control expenses and monitor the effectiveness of a project, and speculate as to why it is not used more often. How can one determine if a cost variation, a schedule variance, a cost performance index, or a schedule performance index is favorable or unfavorable? What are some general criteria to follow?arrow_forwardB/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4arrow_forward
- The following represents a project that should be scheduled using CPM: ACTIVITY A B C D E F G H IMMEDIATE PREDECESSORS A A B C, D D, E F,G b. What is the critical path? ⒸA-D-G-H OB-E-G-H ⒸA-C-F-H A-D-F-H Probability TIMES (DAYS) b Project completion time a 1 1 2 1 1 3 1 2 m 2 2 2 8 2 4 3 3 6 9 11 9 3 c. What is the expected project completion time? Note: Do not round intermediate calculations. Round your answer to 3 decimal places. 11 11 11 X Answer is not complete. days d. What is the probability of completing this project within 19 days? Note: Use Excel's NORM.S.DIST function to find the correct probability for your computed Z value. Do not round intermediate calculations. Round Z value to 2 decimal places and final answer to 4 decimal places.arrow_forwardProject Scope Management Khan, (2006) (see below) states that, "Managing the scope of a project is the most important function of a project manager ... Effective scope management of a project also ensures the success of key completion areas, including time, cost, and quality. Project scope management can be further subdivided into its components which include: project initiation, scope planning, scope definition, scope verification, and scope change control." Based on your Integrated Project: Select two of the subdivisions above and discuss the primary issues that could arise from the process. Your response should begin with a definition of the selected subdivision before detailing the selected processarrow_forwardSelect the best answer for the following questions: 1) An ongoing process that evaluates and implements functions that drive a business is: a) Mission impossible b) Continuous improvement c) Quality control d) Cost effectiveness 2) Project Schedules are meant to provide a path forward to guide the project planning process, but not all activities are on the 'critical' path. Those activities not on the Critical Path are distinguished by including: a) Cost of activity b) Total Float c) Long Lead time d) Negative Lag 3) At what point in an engineering project is the Engineer involved? a) Conceptual Development b) Providing specifications c) Design Development d) Financial pro-forma 4) Engineers are characteristically good at all of the following but: a) Analyzing critical data b) Providing alternate solutions to process development c) Delegating tasks for a project d) Provide Quality control during design.arrow_forward
- Project Duration= Planning on spending per month Project Budget (BAC) Percent complete per month Performance Analysis % Complete Planned Value (PV) Actual Cost (AC) Earned Value (EV) Schedule Variance (SV) Schedule Performance Index (SPI) Cost Variance (CV) Cost Performance Index (CPI) Estimate at Completion (EAC) Estimate to Complete (ETC) Variance at Completion (VAC) 5 months $300,000.00 $1,500,000.00 Month 1 20% 20% of work completed 15% of work completed Spent additional $110,000 Month 2 Instructions: Utilizing the EVM cheat sheet provided by the instructor, complete the calculations i formulas and functions to attain your answers. Please do not simply plug in numbers. This exerci ability to use Excel. Finally, answer the questions below to explain your answers. Question 1: What do your SV numbers tell you about the project schedule and how? Answer 1: Question 2: What do your SPI numbers tell you about the project schedule and how? Answer 2:arrow_forward[Project Management] Because a housing project is running late, the developer will need to complete and deliver the houses as quickly as possible. You and your management team are responsible for mitigating the situation by including a time-cost trade-off analysis into the project. You will need to include the following: Normal crash Activity Prior Days cost, RM Days cost, RM A 7,000 7,000 B A 8,000 9 8,000 B 14 6,000 12 11,000 D B 18 5,000 11 8,500 E C,D 12 8,000 12 8,000 E 20 6,000 16 12,000 E 7,000 7,000 E 11 11,000 7 15,000 G, H 10 15,000 21,000 7 I, F 6 9,000 6 9,000 Construct a network diagram (PDM), including activity early start, late start, early finish, late finish and float.arrow_forwardon in OMGT 1013 x (1) Facebook - usl-tuguegarao.neolms.com/student take_quiz_assignment/display/23380965?part=14&r ODE 606 ÖMGT 1013 Item 14 of 78 Refer to the given information below for a particular project. Activity Immediate Predecessors Time (weeks) A None 2 BD 4. 3 E F Compute the slack time for activity D A. LLarrow_forward
- Given the following activity duration and field report, calculate the ACWP, BCWP, BCWS, CPI, CV, SPI, and SV. Also, project the estimated budget at completion and the estimated project duration. Feel free to use the Excel spreadsheet example and plug the new numbers in. Activity Predecessor Duration Cost/Day Total Cost A B U D E F Activity A B с D E A F B D D Actual % Completion 100 100 50 50 2 0 3 4 4 3 2 Field Report at the end of Day 5 Incurred Costs 400 1000 500 900 200 0 300 300 400 300 200 400 900 1200 1600 900 400arrow_forwardConsider the project described in the table below: Activity Duration A B C D E F G H 9 4 8 8 5 7 4 6 OEST-9 and LCT = 15 OEST=9 and LCT = 13 Immediate Predecessor What is the earliest start time (EST) and latest completion time (LCT) of activity B? OEST=9 and LCT = 20 OEST-9 and LCT-17 - A A A B B,C C,D E,F,Garrow_forwardThe prime objectives of project management are cost, time andA. ScheduleB. QualityC. Customer satisfactionD. Performance.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY