Concept explainers
Interpretation:
Requirement of number of FTE staff in May through August.
Concept Introduction:
FTE is (Full time equivalent) is the number of hours a full time employee works in a stipulated time period. It shows an average hours for work.
Explanation of Solution
Variables used to calculate FTE staff are:
- Month
- Number of days in a month
- Average
forecast of a month - Percentage in product mix
Formula to be used are:
.
For the four-month time horizon, the mix percentages will remain the same as given.
Month | May | |||
Working days | 22 | |||
Total forecast | 750 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 165.00 | 3.60 | 594.00 |
2 | 17 | 127.50 | 2.00 | 255.00 |
3 | 13 | 97.50 | 1.70 | 165.75 |
4 | 12 | 90.00 | 5.50 | 495.00 |
5 | 10 | 75.00 | 4.00 | 300.00 |
6 | 9 | 67.50 | 3.00 | 202.50 |
7 | 7 | 52.50 | 2.00 | 105.00 |
8 | 5 | 37.50 | 2.00 | 75.00 |
9 | 3 | 22.50 | 1.50 | 33.75 |
10 | 2 | 15.00 | 4.00 | 60.00 |
Total | 100 | 750 | 2286 | |
Required # of workers | 15 |
Month | June | |||
Working days | 20 | |||
Total forecast | 825 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 181.50 | 3.60 | 653.40 |
2 | 17 | 140.25 | 2.00 | 280.50 |
3 | 13 | 107.25 | 1.70 | 182.33 |
4 | 12 | 99.00 | 5.50 | 544.50 |
5 | 10 | 82.50 | 4.00 | 330.00 |
6 | 9 | 74.25 | 3.00 | 222.75 |
7 | 7 | 57.75 | 2.00 | 115.50 |
8 | 5 | 41.25 | 2.00 | 82.50 |
9 | 3 | 24.75 | 1.50 | 37.13 |
10 | 2 | 16.50 | 4.00 | 66.00 |
Total | 100 | 825 | 2514.6 | |
Required # of workers | 18 |
Month | July | |||
Working days | 22 | |||
Total forecast | 900 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 198.00 | 3.60 | 712.80 |
2 | 17 | 153.00 | 2.00 | 306.00 |
3 | 13 | 117.00 | 1.70 | 198.90 |
4 | 12 | 108.00 | 5.50 | 594.00 |
5 | 10 | 90.00 | 4.00 | 360.00 |
6 | 9 | 81.00 | 3.00 | 243.00 |
7 | 7 | 63.00 | 2.00 | 126.00 |
8 | 5 | 45.00 | 2.00 | 90.00 |
9 | 3 | 27.00 | 1.50 | 40.50 |
10 | 2 | 18.00 | 4.00 | 72.00 |
Total | 100 | 900 | 2743.2 | |
Required # of workers | 18 |
Month | July | |||
Working days | 22 | |||
Total forecast | 775 | |||
Products | Product Mix (%) | No. of files | Hours per file | Hours |
1 | 22 | 170.50 | 3.60 | 613.80 |
2 | 17 | 131.75 | 2.00 | 263.50 |
3 | 13 | 100.75 | 1.70 | 171.28 |
4 | 12 | 93.00 | 5.50 | 511.50 |
5 | 10 | 77.50 | 4.00 | 310.00 |
6 | 9 | 69.75 | 3.00 | 209.25 |
7 | 7 | 54.25 | 2.00 | 108.50 |
8 | 5 | 38.75 | 2.00 | 77.50 |
9 | 3 | 23.25 | 1.50 | 34.88 |
10 | 2 | 15.50 | 4.00 | 62.00 |
Total | 100 | 775 | 2362.2 | |
Required # of workers | 16 |
In summary, the FTEs required can be written in the following table:
Month | FTE |
May | 15 |
Jun | 18 |
Jul | 18 |
Aug | 16 |
Want to see more full solutions like this?
- The forecasted requirements for an electric hand drill for the next 6 weeks are 15, 40, 10, 20, 50, and 30 units. The marketing department has booked orders totaling 20, 25, 10, and 20 units for delivery in the first (current), second, third, and fourth weeks. Currently, 30 hand drills are in stock. The policy is to order in lots of 60 units. Lead time is one week.a. Develop the MPS record for the hand drills.b. A distributor of the hand drills places an order for 15 units. What is the appropriate shipping date for the entire order?arrow_forwardDescribe what is the purpose of the Gantt chart as a scheduling tool and when do they use a Gantt chart instead of network based method?arrow_forwardWSS company makes weatherproof surveillance systems for parking lots. Demand estimates for the next four quarters are 25, 9, 13, and 17 units. Prepare an aggregate plan that uses inventory, regular time and overtime and back orders. Subcontracting is not allowed. Regular time capacity is 15 units for quarters 1 and 2, 18 units for quarters 3 and 4. Overtime capacity is 3 units per quarter. Regular time cost is $2000 per unit, while overtime cost is $3000 per unit. Back order cost is $300 per unit per quarter; inventory holding cost is $100 per unit per quarter. Beginning inventory is zero. Questions At the end of quarter 3, what is the ending inventory of finished systems? Answer: No ending Inventory =0 What is the total cost? 15*2000 + 6*2300 +4*2600 + 9*2000 + 13*2000 + 17*2000 =$132, 200 What is the average cost per unit? Answer 132200 / 64 = $2,066.arrow_forward
- :Explain each of the following terminologies in the context of SCM with an example: Logistic systemization, Schedule-sales point association.arrow_forwardDescribe the differences between capacity planning and materials planning.arrow_forwardDeb Bishop Health and Beauty Products has developed a new shampoo and you need to develop its aggregate schedule. The cost accounting department has supplied you the cost relevant to the aggregate plan and the marketing department has provided a four-quarter forecast. the four-quarter forecast. Quarter Forecast 1 1,400 2 1,100 3 1,700 4 1,300 aggregate plan. Costs Previous quarter's output 1,600 units Beginning inventory 0 units Stockout cost for backorders $55 per unit Inventory holding cost $11 per unit for every unit held at the end of the quarter Hiring workers $50 per unit Layoff workers $75 per unit Unit cost $35 per unit Overtime $20 extra per unit Subcontracting Not available Your job is to develop an aggregate plan for the next four quarters. Part 2 a) Try hiring and layoffs (to meet the forecast) as necessary (enter your responses as whole…arrow_forward
- describe what is the purpose of the Gantt chart as a scheduling tool and when do they using a Gantt chart instead of a network based method?arrow_forwardDescribe the process of capacity planning in IT resource management and the importance of scaling resources to meet demand.arrow_forwardExplain what is the purpose of the Gantt chart as a scheduling tool and when they use a Gantt chart instead of a network based method?arrow_forward
- How do the concepts of master production scheduling and material requirements planning translate to a service organization? Provide an example.arrow_forwardWhat precisely is the key distinction between planning for the long term and planning for the short term when it comes to process scheduling?arrow_forwardThe opening backlog is 800 units. Forecast demand is as shown here. Calculate theweekly production for level production if the backlog is to be reduced to 100 units.arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.