Question
Chapter 13, Problem 15PA
Summary Introduction
Interpretation:
MRP explosions to make garden tools.
Concept Introduction:
Bill of material is the detailed description of all components required to produce final product.
Material Requirement Planning (MRP) is the detailed planning of all components required and its quantity for the end product. It is usually prepared for a week and keeps on changing according to the product. It consist of gross requirement,
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Tots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information:
component
plastic
time
space
cost to manufacture
cost to purchase
front
2
11
2
7
11
seat/frame
3
7
2
6
10
rear
0.5
2.5
0.2
2
5
available
60000
180000
35000
Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost.
Use Excel's Solver to obtain the optimal solution. How many of each component should be manufactured vs. purchased? What is the overall cost? What are the binding constraints?
Upload a screenshot of the spreadsheet that you used…
The bill of materials (BOM) for product A is shown in the figure below. The lotsizing rule and other
information for each item can be found in the table. The demand for product A is 400 units in week 5,
600 units in week 6, and 500 units in week 7. Production lead time for product A is 1 weeks. Develop
the material requirements plan for the components B, C, and D.
C(1)
D(1)
BI2)
D(2)
D(2)
Table
B
D
EOQ=2000 or
multiples of 2000
POQ: P=2
1 week
Lotsizing rule
LAL
Lead time
2 weeks
1 week
4000 (week 1)
100
Scheduled receipts
none
Beginning inventory
200
Tots Toys makes a plastic tricycle that is composed of three major components: a handlebar-front wheel-pedal assembly, a seat and frame unit, and rear wheels. Please note that each tricycle requires two rear wheels, the front wheel is included in the front wheel-pedal assembly. The company has orders for 15,000 of these tricycles. Current schedules yield the following information:
component
plastic
time
space
cost to manufacture
cost to purchase
front
2
11
2
7
11
seat/frame
3
7
2
6
10
rear
0.5
2.5
0.2
2
5
available
60000
180000
35000
The company obviously does not have the resources available to manufacture everything needed for the completion of 15,000 tricycles so has gathered purchase information for each component.
Develop a linear programming model to tell the company how many of each component should be manufactured and how many should be purchased in order to provide 15,000 fully completed tricycles at the minimum cost. (state the objective function, decision…
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Brown and Brown Electronics manufactures a line of digital audiotape (DAT) players. The bill of materials, showing the number of each item required is shown below follows: F(2) C(1) I(2) F(2) H(1) I(2) Data for A: Gross requirement is 100 units on 9th week, Lead time is 2 weeks, Lot for lot A G(2) D(2) Data for C: Lead time is 1 weeks, Lot for lot Data for D: Lead time is 2 weeks, schedule receipt is 30 on 1st week, lot size 170 units Data for F: Lead time is 1 weeks, scheduled receipt is 60 on 1st week, on hand inventory is 15, lot for lot Data for G: Lead time is 1 weeks, scheduled receipt is 100 on 1st week, on hand inventory is 50, lot for lot Data for H: Lead time is 1 weeks, scheduled receipt is 50 on 1st week, lot size is 200 Data for I: Lead time is 1 weeks, scheduled receipt is 60 on 1st week, on hand inventory is 15, lot for lot Prepare an MRP schedule to satisfy the demand.arrow_forwardProduct PI is made of one unit of sub assembly A and four units of sub assembly B. Sub assembly A is made of 4 units of component X while sub assembly B is made of 2 units of X. one unit of Y and 3 units of Z. The manufacturing lead times PI, A, B, X, Y and Z are 1, 1, 1, 4, 6 and 1 (week) respectively. The lead time for delivery of PI in weeks isarrow_forwardDevelop a material requirements plan for component H. Lead times for the end item and each component except B are one week. The lead time for B is three weeks. Sixty units of A are needed at the startof week 8. There are currently 15 units of B on hand and 130 of E on hand, and 50 units of H are inproduction and will be completed by the start of week 2. Lot-for-lot ordering will be used for all items.arrow_forward
- Analyze the challenges and best practices associated with requirement analysis for complex, large-scale projects.arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 5,500 kits in week 2 Start assembling 11,000 kits in weeks 3, 4, and 5 Start assembling 9,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 19,000 Week 1 2 3 4 Gross requirements 5,500 11,000…arrow_forwardYour boss at Xiangling Hu Products, Inc., has just provided you with the schedule and lead times for the bracket. The unit is to be prepared in week 10. The lead times for the components a re bracket (I week), base (1 week), spring ( I week), clamp (I week), housing (2 weeks), handle (I week), casting (3 weeks), bearing (I week), and shaft (1 week).a) Prepare the time-phased product structure for the bracket.b) In what week do you need to start the castings?arrow_forward
- Given the following data, can an order for 20 for delivery in week 4 be accepted?Calculate the ATP using the following table. On hand = 50 units.arrow_forwardDiscuss the concept of traceability in requirement analysis and management. Why is it essential, and how is it typically achieved in a project?arrow_forwardThe three tables above show the master production schedule and the bill of materials of part A, and the inventory records of all the parts. There are no scheduled receipts. Given this information, what is the net requirement of part A in Week 4?arrow_forward
- What are some common techniques and methodologies for prioritizing requirements in complex projects? How can the MoSCoW method and the Kano model be applied in this context?arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: Production plans for complete kits are as follows: Start assembling 10,500 kits in week 2 Start assembling 20,000 kits in weeks 3, 4, and 5 Start assembling 15,500 kits in week 6 The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time 1 week: Minimum order quantity=10,500 Week 1 Gross requirements Scheduled receipts Projected…arrow_forwardThe product structure for product X is illustrated below. Level 0 Level 1 4 Level 2 Level 3 Part H B C D H K M N X Z с K B Lead Time (in weeks) 1 1 3 2 3 2 3 3 4 M D N The lead time for manufacturing any number units for an item and the required number of units for the lower level part in the product structure are reported in the following table. For example, each unit of Part X requires 1 units of Part C and, in turn, each unit of Part C requires 2 units of Part H and 2 units of Part K. 2 1 4 2 2 2 4 1 2 Required number of units X Z H K 100 units of product X are to shipped at the end of week 25. There is no inventory on hand. How many units of part N are required for production? 3200 Specify only the number.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Inventory Management | Concepts, Examples and Solved Problems; Author: Dr. Bharatendra Rai;https://www.youtube.com/watch?v=2n9NLZTIlz8;License: Standard YouTube License, CC-BY