To define: The relationship between aggregate planning and master production schedule
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 months.
Master production
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
What is the relationship between the aggregate plan andthe master production schedule?
Explain the role of the master production schedule?
Table below provides the demand forecast and production day information for an aggregate plan. Assume that no back orders are allowed in this case.
Month
January
February
March
April
May
June
Demand Forecast
3,000
4,500
3,400
2,500
4,000
3,200
Production Days
22
18
21
21
22
20
The costing information that is used to evaluate the total cost of each plan is as follows:• Inventory carrying cost: $4 per unit per month• Subcontracting cost per unit: $15 per unit• Working hours: 8 hours per day• Average pay rate: $12 per hour ($96 per day per worker)• Labour-hours to produce a unit: 2 hours per unit• Cost of increasing daily production rate (hiring and training): $300 per unit• Cost of decreasing daily production rate (layoffs): $700 per unitUse these information to formulate an aggregate plan. The firm would like to use level strategy: constant workforce for the aggregate planning. The firm chooses the average demand of the…
Chapter 13 Solutions
Principles Of Operations Management
Ch. 13 - Make the case for, and then against, this pricing...Ch. 13 - Prob. 1DQCh. 13 - Why are SOP teams typically cross-functional?Ch. 13 - Prob. 3DQCh. 13 - Prob. 4DQCh. 13 - Prob. 5DQCh. 13 - Prob. 6DQCh. 13 - Prob. 7DQCh. 13 - Prob. 8DQCh. 13 - Prob. 9DQ
Ch. 13 - Prob. 10DQCh. 13 - Prob. 11DQCh. 13 - Prob. 12DQCh. 13 - Prob. 13DQCh. 13 - Prob. 14DQCh. 13 - Prob. 1PCh. 13 - Prob. 2PCh. 13 - The president of Hill Enterprises, Terri Hill,...Ch. 13 - Prob. 4PCh. 13 - Prob. 5PCh. 13 - Prob. 6PCh. 13 - Consuelo Chua, Inc., is a disk drive manufacturer...Ch. 13 - Prob. 8PCh. 13 - Prob. 9PCh. 13 - Prob. 10PCh. 13 - Prob. 11PCh. 13 - Southeast Soda Pop, Inc., has a new fruit drink...Ch. 13 - Ram Roys firm has developed the following supply,...Ch. 13 - Jerusalem Medical Ltd., an Israeli producer of...Ch. 13 - Prob. 15PCh. 13 - Prob. 16PCh. 13 - Prob. 17PCh. 13 - Prob. 18PCh. 13 - Dwayne Cole, owner of a Florida firm that...Ch. 13 - Prob. 20PCh. 13 - Prob. 21PCh. 13 - Prob. 22PCh. 13 - Prob. 23PCh. 13 - Prob. 24PCh. 13 - Prob. 25PCh. 13 - Prob. 26PCh. 13 - Evaluate the various configurations of operating...Ch. 13 - Prob. 2CSCh. 13 - After researching revenue (yield) management in...Ch. 13 - The Magic used its original pricing systems of...Ch. 13 - Prob. 1.3VC
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- In production plan 2, vary inventory if the ending inventory for March is -32, what will be the beginning inventory for the month of April?arrow_forwardDescribe in detail what are the aggregate planning goal's?arrow_forwardWhat is the BOM stock needed for the shoe department for April if the sales are planned at $64,000 and the stock to sales ratio is 18.3?arrow_forward
- What factors are important in choosing the length of the planning horizon for aggregate planning?arrow_forwardCreate a level plan with a zero ending inventory for the forecast shown in the table. There is no beginning inventory and regular production capacity is 300 units. Overtime costs K15 extra and is limited to 25 units per month and subcontracting is limited to 60 units per month and costs K10 per unit. Back orders cost KS0 per unit and there is a cost of KS per month to hold a unit in inventory. What is the total plan cost? |Month January February March Forecast 250 300 400 |April 350arrow_forwardIdentify the variables decision makers have to work with in aggregate planning.arrow_forward
- which one would be the optimal production plan for part b?arrow_forwardExplain the master production schedule?arrow_forwardLarge service organisations, such as banks and hospitals, used to be noted for their lack of standard costing systems, and their relatively unsophisticated budgeting and control systems compared with large manufacturing organisations. But this is changing and many large service organisations are now revising their use of management accounting techniques. Requirement: Explain the uses of activity-based costing in the service industries.arrow_forward