a)
To determine: The circumstances in which developing one aggregate plan is enough rather than two.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 periods.
b) and c)
To determine: The circumstances in which developing one aggregate plan is enough rather than two.
Introduction: The aggregate plan is the output of sales and operations planning. The major concern of aggregate planning is the production time and quantity for the intermediate future. Aggregate planning would encompass a time prospect of approximately 3 to 18 periods.
Trending nowThis is a popular solution!
Chapter 11 Solutions
OPERATIONS MANAGEMENT(LL)-W/CONNECT+
- Find the planned order for all items.arrow_forward1. Describe the various functions of purchase orders. Describes the steps to register a purchase order in the Sage 50 (Peachtree) program.arrow_forward1. Determine how much is the balance in the 11th period. Prod A. 1 2 7 8 9. 10 11 12 Requirement 1700 2500 1000 Receipt Balance 800 Production LT=1 LS=300 SS=400 2. Determine how much is the requirement in the 9th period of material D. Material C 1 2 3 4 5 6 7 8 10 11 12 1500 700 800 Requirement Receipt Balance 450 Order LT=1 EOQ= 400 SS=300 (3) 田 Material D 1 2 4 8 6. 10 11 12 ? Requirement 3.arrow_forward
- How do you do this step by step?arrow_forwardFigure shows a partially completed MPS record for 2 inch pneumatic control valves. Suppose that you receive the following orders at right for the valves (shown in the order of their arrival). As they arrive, you must decide whether to accept or reject them. Which orders would you accept for shipment?Order Amount (Units) Week Requested1 15 22 30 53 25 34 75 7arrow_forward|Product D is stocked only at the AMC Chemical Company's Dallas warehouse and at the company's plant warehouse in Akron. The sales director has forecast product sales from the Dallas warehouse to be 40 units per week for the next 8 weeks. Product D is manufactured at the firm's Akron plant using 2 units of ingredient X per unit of product D. Information: Ingredient X Projected available balance: 4 Units Schedule receipt in week 1: 320 units Safety stock quantity: 2 Product D in Dallas Product D in Plant Warehouse Warehouse Projected available balance: 85 Units Safety stock quantity: 5 units Lead time: 2 weeks Lot for lot size quantity Projected available balance: 2 Units Schedule receipt in week 1: 46 units Safety stock quantity: 8 units units Lead time: 1 week Lead time: 4 weeks Lot for lot size quantity Lot size quantity: 320 units Prepare the DRP records for product D at the Dallas warehouse and the plant warehouse as well as the MRP record for ingredient X (Assume ingredient X is…arrow_forward
- What to Do Ab 41. What are the contracts with asymmetric information? Capacity Reservation Contracts and Advance Purchase Contracts Pay-Back Contracts and Cost Sharing Contracts Long Term Contracts and Flexible or Option Contracts All of the Above 42. Warehouse Costs are: 111 annual flowarrow_forwardWhat do you understand by Materials requirements planning (MRP)?arrow_forwardEach Triam Deluxe gamer computer system consists of two speakers, a monitor, a system unit, a keyboard, and an installation kit. These pieces are packed together and shipped as a complete kit. In MRP terms, all of these items are level 1 items that make the level 0 kits. Complete the MRP records, using the following information: • Production plans for complete kits are as follows: Start assembling 4,500 kits in week 2 Start assembling 1,000 kits in weeks 3, 4, and 5 Start assembling 8,000 kits in week 6 • The gross requirements for the system unit have already been given to you. For the remaining items, you will need to figure out the gross requirements. • All scheduled receipts, lead times, and beginning inventory levels are shown. Click the icon to view the MRP records. Construct the material requirements plan for item System unit (enter your responses as whole numbers). System unit: Lead Time = 1 week; Minimum order quantity = 3,500 Week 1 2 3 Gross requirements 4,500 1,000…arrow_forward
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.