Traffic and Highway Engineering
Traffic and Highway Engineering
5th Edition
ISBN: 9781305156241
Author: Garber, Nicholas J.
Publisher: Cengage Learning
Question
Book Icon
Chapter 11, Problem 13P
To determine

Estimated construction cost in 2014 (in$).

Blurred answer
Students have asked these similar questions
QUESTION 6. The activities involved in the construction of a new shopping mall are given in Table Q6. One resource type will be used during the contract. Determine minimum level of the resource required to complete the project. Table Q6 Activity Duration Predecessors Resource (units/week) (Weeks) A B 2 2 2 1 2 3 1 5 3 1 E 2 6. 2 F G 3 H 6. 4 4 4 5, 6 6, 7 2, 8 2, 8, 9 10, 11, 12, 13 4 2 K 2 L. 2.
A contractor who does not meet the deadline on the construction of a building is fined P8,000.00 per day for each of the first ten days of extra time, and for each additional day thereafter the fine is increased by P1,600.00 each day. If the contractor is fined P201,600.00, by how much extra days was the construction time delayed? Kindly show the detailed solution.
The following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, activities A, B, D are completed and E is 50% complete, for a cost of $80,000. For this project, using earned value concepts, determine the schedule and cost variance. Is the project ahead or behind schedule? Over or under budget? Activity A B с D E F G H Cost $2,000 $1,000 $6,000 $2,000 $7,000 $9,000 $3,000 $10,000 Month 1 Month 2 Month 3 Month 4
Knowledge Booster
Background pattern image
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Text book image
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,