QUESTION 6.
The activities involved in the construction of a new shopping mall are given in Table Q6. One
resource type will be used during the contract. Determine minimum level of the resource
required to complete the project.
Table Q6
Activity
Duration
Predecessors
Resource (units/week)
(Weeks)
A
B
2
2
2
1
2
3
1
5
3
1
E
2
6.
2
F
G
3
H
6.
4
4
4
5, 6
6, 7
2, 8
2, 8, 9
10, 11, 12, 13
4
2
K
2
L.
2.
A contractor who does not meet the deadline on the construction of a building is fined P8,000.00 per day for each of the first ten days of extra time, and for each additional day thereafter the fine is increased by P1,600.00 each day. If the contractor is fined P201,600.00, by how much extra days was the construction time delayed?
Kindly show the detailed solution.
The following eight activities constitute an overall bar chart portrayal of a 4-month project.
After 1.5 months, activities A, B, D are completed and E is 50% complete, for a cost of $80,000.
For this project, using earned value concepts, determine the schedule and cost variance. Is the
project ahead or behind schedule? Over or under budget?
Activity
A
B
с
D
E
F
G
H
Cost
$2,000
$1,000
$6,000
$2,000
$7,000
$9,000
$3,000
$10,000
Month 1
Month 2
Month 3
Month 4
Chapter 11 Solutions
Traffic and Highway Engineering
Ch. 11 - Prob. 1PCh. 11 - Prob. 2PCh. 11 - Prob. 3PCh. 11 - Prob. 4PCh. 11 - Prob. 5PCh. 11 - Prob. 6PCh. 11 - Prob. 7PCh. 11 - Prob. 8PCh. 11 - Prob. 9PCh. 11 - Prob. 10P
Ch. 11 - Prob. 11PCh. 11 - Prob. 12PCh. 11 - Prob. 13PCh. 11 - Prob. 14PCh. 11 - Prob. 15PCh. 11 - Prob. 16PCh. 11 - Prob. 17PCh. 11 - Prob. 18PCh. 11 - Prob. 19PCh. 11 - Prob. 20PCh. 11 - Prob. 21PCh. 11 - Prob. 22PCh. 11 - Prob. 23PCh. 11 - Prob. 24PCh. 11 - Prob. 25PCh. 11 - Prob. 26PCh. 11 - Prob. 27P
Knowledge Booster
Similar questions
- The following bar chart shows the activities to complete a project in 6 months (each column represents 1 month). The total project cost is $1,480. After 3 months, Activities A, B, C, E, and half of F are completed, for a cost of $490. What is the status of the project in terms of the budget (over or under) and the schedule (ahead or behind)? (Give each answer in terms of a percent variance.)arrow_forwardThe initial construction cost of a project is $200000 which should be paid at the beginning of the construction period (time =0). Extra expenditures planning to be paid during operation period, which are ($5000) at the end of the first year, $3000 at the end of the second year, $1000 at the end of the third year, $1000 at the end of the fifth year and $ 1000 at the end of the sixth year. If the project life is 10 years and the interest rate is %10, draw the cash flow diagram and find a) the present worth of the project, b) the future worth at the end of the project life, c) the annual payment worth.arrow_forwardQ3: The construction plan for a house is shown in figure and table below, gives the manhoures required and team size for each Activity. Prepare a line of balance schedule for a contract of 15 houses using rate of build of 3 house/ week and each team working at their natural rate. Assume 5 day working week, 8 hours per day, and a minimum buffer time 5 days. A В E D Activity Manhours per activity(M) Men per activity(Q) A B F G 180 320 200 60 38 120 80 40 4 4 2 2 3 2 3arrow_forward
- 1. A project your firm is considering for implementation has these estimated costs and revenues: an investment cost of $50,000; maintenance costs that start at $5,000 at the end of year (EOY) 1 and increase by $1,000 for each of the next 4 years, and then remain constant for the following 5 years; savings of $20,000 per year (EOY 1-10); and finally a resale value of $35,000 at the EOY 10. If the project has a 10-year life and the firm's MARR is 10% per year, what is the present worth of the project? Is it a sound investment opportunity? 2. A toll bridge across the Mississippi River is being considered as a replacement for the current 1-40 bridge linking Tennessee to Arkansas. Because this bridge, if approved, will become a part of the U.S. Interstate Highway system, the B-C ratio method must be applied in the evaluation. Investment costs of the structure are estimated to be $17,500,000 and $325,000 per year in operating and maintenance costs are anticipated. In addition, the bridge…arrow_forwardProblem 4 A construction company is planning their projects for the year 2023. The company is considering the construction of 18 buildings, each is 2,900 m². In 2018, they have built similar buildings but with smaller areas, and the material costs associated with those buildings are shown in the following table: 16 OL O ^ 6 7 17 i ♫+ The materials cost index values are as shown in the following table: Cost index 321 332 348 368 379 398 406 & ( Building # 1 2 7 3 4 a V 5 6 7 8 18 144 f8 TY! U * Year 2017 2018 Area (m²) 1,430 1,475 2019 2020 2021 2022 2023 fg 00 1,655 1,790 1,961 2,015 2,375 2,533 THE UNIVERSITY OF 8 ▷II A myhp NO ( + Cost ($) 311,812 313,744 331,893 339,479 f10 DPI 356,153 359,265 383,146 385,265 9 A fm H ¡1 O X ***** O B f12 P 慢 XI ins prt sc = S C ← de bacarrow_forward6 The third question: For a part of a construction project whose activities are shown in Table No. 3, the project was visited on the eighth day after the start of work on it, and it was found that the two actions A and B were fully accomplished. event c a quarter of which was accomplished, activity G was five completed, activity F was completed The completion of a third of It, other activities have not started yet, but it is expected after the end of the event and the existence of a comprehensive ban for a period of 3 days. Therefore, it was decided to postpone the work of Event E for a period of three days (days of ban). In light of the information above, find the time period required to complete the project and the critical path before and after the update Table3 Act. Dur.(week) Preceded by A A D 5 G 10 A,D 5 C,G F 12 A,D H 6 Farrow_forward
- The following eight activities constitute an overall bar chart portrayal of a 4-month project. After 1.5 months, Activities A, B, D, and half of E were completed, for a cost of $8,000. For this project, using earned value concepts, determine the schedule variance and the cost variance. State if the project is over or under budget and if it is ahead or behind schedule.arrow_forward3- The maintenance costs for a bridge with an expected 50 years life are estimated to be ($10,000,000) each year for the first 5 years, followed by ($50,000,000) other costs at year 15, and ($75,000,000) at the year 30, if ( i = 10%), what is the annual uniform cost over the entire 50 years? %3Darrow_forwardQ2. Explain the demand, income, cross-price and supply elasticity for five (5) types of building [5] materials used in normal construction.arrow_forward
- Q6: A construction project will have a Base cost of $3,250,000. There is a 5 percent chance that the costs will increase by $250,000. There is a 20 percent chance that the project will finish ahead of schedule and win incentive reward of $40,000. There is a 10 percent chance that an accident will add $105,000 to the cost. Calculate the following: a) calculate the contingency reserve b) What is the expected value of the project? c) What is the best case scenario and its value? d) What is the worst case scenario and its value?arrow_forwardA contractor is planning the acquisition of construction equipment, including bulldozers, needed for a new project in a remote area. Suppose that from his prior experience with similar bulldozers, he estimated that there is a 65% chance that each bulldozer can remain operational for at least 6 months. 1.) If he purchased four bulldozers for the new project, what is the probability that there will be at least two bulldozers left operational after six months into the project? .arrow_forwardShow complete solution You are faced with making a decision on a large capital investment proposal. The capital investment amount is $640,000. Estimated annual revenue at the end of each year in the eight year study period is $180,000. The estimated annual year-end expenses are $42,000 starting in year one. These expenses begin decreasing by $4,000 per year at the end of year four and continue decreasing through the end of year eight. Assuming a $20,000 market value at the end of year eight and a MARR = € =12% per year, answer the following questions. Using FW, AW and PW, determine whether this proposal is acceptable.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Traffic and Highway EngineeringCivil EngineeringISBN:9781305156241Author:Garber, Nicholas J.Publisher:Cengage LearningFundamentals Of Construction EstimatingCivil EngineeringISBN:9781337399395Author:Pratt, David J.Publisher:Cengage,
Traffic and Highway Engineering
Civil Engineering
ISBN:9781305156241
Author:Garber, Nicholas J.
Publisher:Cengage Learning
Fundamentals Of Construction Estimating
Civil Engineering
ISBN:9781337399395
Author:Pratt, David J.
Publisher:Cengage,