6 The third question: For a part of a construction project whose activities are shown in Table No. 3, the project was visited on the eighth day after the start of work on it, and it was found that the two actions A and B were fully accomplished, event ca quarter of which was accomplished, activity G was five completed, activity F was completed The completion of a third of it, other activities have not started yet, but it is expected after the end of the event and the existence of a comprehensive ban for a period of 3 days. Therefore, it was decided to postpone the work of Event E for a period of three days (days of ban). In light of the infamation above, find the time period required to complete the project and the critical path before and after the update Table3 Act. Dur.(week) Preceded by A 6. 8 A D G 10 A,D 5 C,G 12 A,D 6.

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
6 The third question: For a part of a construction project whose activities are
shown in Table No. 3, the project was visited on the eighth day after the start of
work on it, and it was found that the two actions A and B were fully accomplished.
event c a quarter of which was accomplished, activity G was five completed,
activity F was completed The completion of a third of It, other activities have not
started yet, but it is expected after the end of the event and the existence of a
comprehensive ban for a period of 3 days. Therefore, it was decided to postpone
the work of Event E for a period of three days (days of ban). In light of the
information above, find the time period required to complete the project and the
critical path before and after the update
Table3
Act.
Dur.(week)
Preceded by
A
A
D
5
G
10
A,D
5
C,G
F
12
A,D
H
6
F
Transcribed Image Text:6 The third question: For a part of a construction project whose activities are shown in Table No. 3, the project was visited on the eighth day after the start of work on it, and it was found that the two actions A and B were fully accomplished. event c a quarter of which was accomplished, activity G was five completed, activity F was completed The completion of a third of It, other activities have not started yet, but it is expected after the end of the event and the existence of a comprehensive ban for a period of 3 days. Therefore, it was decided to postpone the work of Event E for a period of three days (days of ban). In light of the information above, find the time period required to complete the project and the critical path before and after the update Table3 Act. Dur.(week) Preceded by A A D 5 G 10 A,D 5 C,G F 12 A,D H 6 F
Expert Solution
steps

Step by step

Solved in 2 steps with 2 images

Blurred answer
Knowledge Booster
Management levels
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning