Managerial Accounting
3rd Edition
ISBN: 9780077826482
Author: Stacey M Whitecotton Associate Professor, Robert Libby, Fred Phillips Associate Professor
Publisher: McGraw-Hill Education
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Chapter 11, Problem 11ME
To determine
Concept introduction:
It is the method to evaluate the project feasibility. This method calculates the PV (present value) of cash inflows and outflows, and then calculates the net present value of the investment. A project should be accepted if it has a positive NPV. The formula to calculate the NPV is as follows:
To choose:
The better project using the NPV technique.
Expert Solution & Answer
Want to see the full answer?
Check out a sample textbook solutionStudents have asked these similar questions
Project S requires an initial outlay at t=0 of $12,000, and its expected cash flows would be $4,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t =
0 of $38,500, and its expected cash flows would be $9,200 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend?
Select the correct answer.
Oa. Both Projects S and L, because both projects have NPV's > 0.
Ob. Project S, because the NPVs > NPVL
Oc. Both Projects S and L, because both projects have IRR's > 0.
Od. Neither Project S nor L, because each project's NPV NPVs.
Project S requires an initial outlay at t= 0 of $16,000, and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t= 0 of $27,500, and its expected cash flows would be $10,150 per year for 5 years. If
both projects have a WACC of 14%, which project would you recommend?
Select the correct answer.
Ca. Project S, because the NPVs > NPVL.
Ob. Both Projects S and L, because both projects have IRR's > 0.
Oc. Both Projects S and L, because both projects have NPV's > 0.
Od. Project I because the NPVL > NPVs.
Oe. Neither Project S nor L, because each project's NPV < 0.
Project Q requires an initial outlay at t = 0 of $20,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,000, and its expected cash flows would be $13,600 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend?
Select the correct answer.
a. Neither Project S nor L, since each project's NPV < 0.
b. Project S, since the NPVS > NPVL.
c. Project L, since the NPVL > NPVS.
d. Both Projects S and L, since both projects have IRR's > 0.
e. Both Projects S and L, since both projects have NPV's > 0.
Chapter 11 Solutions
Managerial Accounting
Ch. 11 - Prob. 1QCh. 11 - Prob. 2QCh. 11 - Prob. 3QCh. 11 - Which capital budgeting methods incorporate the...Ch. 11 - What is a company’s hurdle rate? How is it...Ch. 11 - How do cash flow and net income differ? Explain...Ch. 11 - In everyday terms, explain what information the...Ch. 11 - What do a positive NPV and a negative NPV indicate...Ch. 11 - Prob. 9QCh. 11 - Prob. 10Q
Ch. 11 - Why is the net present value method generally...Ch. 11 - Briefly explain how the profitability mdcx is...Ch. 11 - Prob. 13QCh. 11 - Prob. 14QCh. 11 - Prob. 15QCh. 11 - When would you use the PV of annuity table instead...Ch. 11 - Prob. 17QCh. 11 - Which of the following requires managers to...Ch. 11 - Prob. 2MCCh. 11 - Prob. 3MCCh. 11 - Prob. 4MCCh. 11 - Prob. 5MCCh. 11 - Prob. 6MCCh. 11 - Prob. 7MCCh. 11 - Prob. 8MCCh. 11 - Prob. 9MCCh. 11 - Prob. 10MCCh. 11 - Matching Key Terms and Concepts to DefinitionsCh. 11 - Prob. 2MECh. 11 - Prob. 3MECh. 11 - Prob. 4MECh. 11 - Prob. 5MECh. 11 - Prob. 6MECh. 11 - Prob. 7MECh. 11 - Prob. 8MECh. 11 - Computing Present Value of Complex Contract As a...Ch. 11 - Prob. 11MECh. 11 - Prob. 12MECh. 11 - Prob. 1ECh. 11 - Prob. 2ECh. 11 - Prob. 3ECh. 11 - Prob. 4ECh. 11 - Prob. 5ECh. 11 - Prob. 6ECh. 11 - Prob. 8ECh. 11 - Prob. 9ECh. 11 - Using NPV to Evaluate Mutually Exclusive Projects...Ch. 11 - Prob. 12ECh. 11 - Prob. 13ECh. 11 - Prob. 1.1GAPCh. 11 - Prob. 1.2GAPCh. 11 - Prob. 1.3GAPCh. 11 - Prob. 1.4GAPCh. 11 - Prob. 1.5GAPCh. 11 - Prob. 2.1GAPCh. 11 - Prob. 2.2GAPCh. 11 - Prob. 2.3GAPCh. 11 - Prob. 2.4GAPCh. 11 - Prob. 2.5GAPCh. 11 - Making Automation Decision Beacon Company is...Ch. 11 - Prob. 3.1GAPCh. 11 - Prob. 3.2GAPCh. 11 - Prob. 3.3GAPCh. 11 - Prob. 3.4GAPCh. 11 - Prob. 4.1GAPCh. 11 - Prob. 4.2GAPCh. 11 - Prob. 4.3GAPCh. 11 - Prob. 4.4GAPCh. 11 - Prob. 4.5GAPCh. 11 - Prob. 5.1GAPCh. 11 - Prob. 5.2GAPCh. 11 - Prob. 6.1GAPCh. 11 - Evaluating Sustainability Projects Citco Company...Ch. 11 - Evaluating Sustainability Projects Citco Company...Ch. 11 - Evaluating Sustainability Projects Citco Company...Ch. 11 - Prob. 1.1GBPCh. 11 - Prob. 1.2GBPCh. 11 - Prob. 1.3GBPCh. 11 - Prob. 1.4GBPCh. 11 - Prob. 1.5GBPCh. 11 - Prob. 2.1GBPCh. 11 - Prob. 2.2GBPCh. 11 - Prob. 2.3GBPCh. 11 - Prob. 2.4GBPCh. 11 - Prob. 2.5GBPCh. 11 - Prob. 2.6GBPCh. 11 - Prob. 3.1GBPCh. 11 - Comparing, Prioritizing Multiple Projects Harmony...Ch. 11 - Prob. 3.3GBPCh. 11 - Prob. 3.4GBPCh. 11 - Prob. 4.1GBPCh. 11 - Prob. 4.2GBPCh. 11 - Prob. 4.3GBPCh. 11 - Prob. 4.4GBPCh. 11 - Prob. 4.5GBPCh. 11 - Prob. 5.1GBPCh. 11 - Prob. 5.2GBPCh. 11 - Prob. 6.1GBPCh. 11 - Prob. 6.2GBPCh. 11 - Prob. 6.3GBPCh. 11 - Prob. 6.4GBP
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Staten Corporation is considering two mutually exclusive projects. Both require an initial outlay of 150,000 and will operate for five years. The cash flows associated with these projects are as follows: Statens required rate of return is 10%. Using the net present value method and the present value table provided in Appendix A, which of the following actions would you recommend to Staten? a. Accept Project X and reject Project Y. b. Accept Project Y and reject Project X. c. Accept Projects X and Y. d. Reject Projects X and Y.arrow_forwardThe Pinkerton Publishing Company is considering two mutually exclusive expansion plans. Plan A calls for the expenditure of 50 million on a large-scale, integrated plant that will provide an expected cash flow stream of 8 million per year for 20 years. Plan B calls for the expenditure of 15 million to build a somewhat less efficient, more labor-intensive plant that has an expected cash flow stream of 3.4 million per year for 20 years. The firms cost of capital is 10%. a. Calculate each projects NPV and IRR. b. Set up a Project by showing the cash flows that will exist if the firm goes with the large plant rather than the smaller plant. What are the NPV and the IRR for this Project ? c. Graph the NPV profiles for Plan A, Plan B, and Project .arrow_forwardProject S requires an initial outlay at t = 0 of $19,000, and its expected cash flows would be $5,500 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $37,000, and its expected cash flows would be $10,800 per year for 5 years. If both projects have a WACC of 13%, which project would you recommend? Select the correct answer. a. Project L, because the NPVL > NPVS. b. Neither Project S nor L, because each project's NPV < 0. c. Both Projects S and L, because both projects have NPV's > 0. d. Both Projects S and L, because both projects have IRR's > 0. e. Project S, because the NPVS > NPVL.arrow_forward
- Project S requires an initial outlay at t = 0 of $14,000, and its expected cash flows would be $6,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $26,500, and its expected cash flows would be $7,600 per year for 5 years. If both projects have a WACC of 14%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, because each project's NPV < 0. b. Both Projects S and L, because both projects have NPV's > 0. c. Project S, because the NPVS > NPVL. d. Both Projects S and L, because both projects have IRR's > 0. e. Project L, because the NPVL > NPVS.arrow_forwardeBook Project S costs $14,000 and its expected cash flows would be $6,500 per year for 5 years. Mutually exclusive Project L costs $30,000 and its expected cash flows would be $10,150 per year for 5 years. If both projects have a WACC of 16%, which project would you recommend? Select the correct answer. Oa. Project L, since the NPVL > NPVS. Ob. Both Projects S and L, since both projects have NPV's > 0. Oc. Project S, since the NPVS > NPVL. Od. Both Projects S and L, since both projects have IRR's > 0. Oe. Neither Project S nor L, since each project's NPV < 0.arrow_forwardGive typing answer with explanation and conclusion Project S requires an initial outlay at t = 0 of $13,000, and its expected cash flows would be $5,000 per year for 5 years. Mutually exclusive Project L requires an initial outlay at t = 0 of $28,000, and its expected cash flows would be $13,850 per year for 5 years. If both projects have a WACC of 15%, which project would you recommend? Select the correct answer. a. Neither Project S nor L, because each project's NPV < 0. b. Both Projects S and L, because both projects have NPV's > 0. c. Project S, because the NPVS > NPVL. d. Both Projects S and L, because both projects have IRR's > 0. e. Project L, because the NPVL > NPVS.arrow_forward
- Central Energy is considering two mutually exclusive projects, Project Red and Project The projects have the following cash flows: Year Project Red Cash Flows Project White Cash Flows 0 -$1,000 -$1,000 1 100 700 2 200 400 3 600 200 4 800 100 Assume that both projects have a 10 percent WACC. At what weighted average cost of capital would the two projects have the same net present value?arrow_forwardNet present values for three alternative Investment projects follow. (a) If the company accepts all positive net present value Investments, which of these projects will it accept? (b) If the company can choose only one project, which will it choose? Potential Projects Net present value Project A $1,400 Project B $(12,100) Project C $15,000 (a) If the company accepts all positive net present value investments, which of these projects will it accept? (b) If the company can choose only one project, which will it choose?arrow_forwardLewis Services is evaluating six investment opportunities (projects). The following table reflects each project's net present value NPV and the respective initial investments required. All of these projects are independent. Project NPV Investment 2,500 2,500 II 4,000 20,000 II 7,500 30,000 IV 8,000 40,000 2,000 10,000 VI 2,500 5,000 Lewis has an investment constraint of P50,000. Which combination of projects would represent the optimal investment that should be recommended to Lewis Services' management? O I. II, and VI O I, II, V, and VI O , II, II, IV, V, and VI OI, II, III, V, and VIarrow_forward
- Lopez Industries has identified the following two mutually exclusive capital investment projects: Year Project A Project B 0 -16000 -15500 1 400 12500 2 800 8000 3 13000 800 4 14000 800 If the required return is 11%, what is the NPV for each of these projects? Which project should the firm accept if they apply the NPV rule?arrow_forwardThe net present value of four projects is given below: Project W: $24,000 Project X: $ 11,000 Project Y: $20,000 Project Z: $14,000 The four projects given above require the same amount of investment. How would you rank them using net present value (NPV) method? Group of answer choices X, Z, Y, W W, X, Y, Z W, Y, Z, XX, Y, Z, Warrow_forwardProject S has a cost of $10,000 and is expected to produce benefits (cash flows) of $3,000 per year for 5 years. Project L costs $25,000 and is expected to produce cash flows of $7,400 per year for 5 years. Calculate the two projects’ NPVs, IRRs, assuming a cost of capital of 12%. Which project would be selected, assuming they are mutually exclusive, using each ranking method? Which should actually be selected?arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- EBK CONTEMPORARY FINANCIAL MANAGEMENTFinanceISBN:9781337514835Author:MOYERPublisher:CENGAGE LEARNING - CONSIGNMENTIntermediate Financial Management (MindTap Course...FinanceISBN:9781337395083Author:Eugene F. Brigham, Phillip R. DavesPublisher:Cengage LearningFinancial And Managerial AccountingAccountingISBN:9781337902663Author:WARREN, Carl S.Publisher:Cengage Learning,
- Managerial AccountingAccountingISBN:9781337912020Author:Carl Warren, Ph.d. Cma William B. TaylerPublisher:South-Western College Pub
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:9781337514835
Author:MOYER
Publisher:CENGAGE LEARNING - CONSIGNMENT
Intermediate Financial Management (MindTap Course...
Finance
ISBN:9781337395083
Author:Eugene F. Brigham, Phillip R. Daves
Publisher:Cengage Learning
Financial And Managerial Accounting
Accounting
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:Cengage Learning,
Managerial Accounting
Accounting
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:South-Western College Pub
Capital Budgeting Introduction & Calculations Step-by-Step -PV, FV, NPV, IRR, Payback, Simple R of R; Author: Accounting Step by Step;https://www.youtube.com/watch?v=hyBw-NnAkHY;License: Standard Youtube License