Chubbs Inc.'s manufacturing
Actual variable costs were indirect materials $13,500. indirect labor $9,500, utilities $8,700, and maintenance $5,000. Actual fixed costs equaled budgeted costs except for property taxes and insurance, which were $8,300. The actual activity level equaled the budgeted level.
All costs are considered controllable by the production department manager except for
Instructions
(a) Prepare a manufacturing overhead flexible budget report for the first quarter.
(b) Prepare a responsibility report for the first quarter.
Want to see the full answer?
Check out a sample textbook solutionChapter 10 Solutions
Managerial Accounting: Tools for Business Decision Making
Additional Business Textbook Solutions
Financial Accounting
Horngren's Financial & Managerial Accounting, The Financial Chapters (6th Edition)
Managerial Accounting (4th Edition)
Horngren's Financial & Managerial Accounting, The Managerial Chapters (6th Edition)
Financial Accounting: Tools for Business Decision Making, 8th Edition
Financial Accounting (11th Edition)
- In the Assembly Department of Cobb Company, budgeted and actual manufacturing overhead costs for the month of April 2010 were as follows. Budget Actual Indirect materials $15,000 $14,300 Indirect labor 20,000 20,600 Utilities 10,000 10,750 Supervision 5,000 5,000 All costs are controllable by the department manager. Prepare a responsibility report for April for the cost center.arrow_forwardCost and production data for Rob Manufacturing for the 2018 financial year was as follows: Budgeted variable factory overhead $120,000 Budgeted fixed factory overhead $180,000 Total $300,000 Budgeted production (direct labour hours) $15,000 Actual variable factory overhead $125,300 Actual fixed factory overhead $164,700 Total $290,000 Actual production (direct labour hours) 15,500 It is organisational policy and procedure that Factory overhead is applied to production using direct labour hours as the cost driver. Required: (a) Calculate the factory overhead application rate, and, (b) Under or over applied overhead.arrow_forwardIn the Assembly Department of Hannon Company, budgeted and actual manufacturing overhead costs for the month of April 2020 were as follows. Budget Actual Indirect materials $15,300 $14,700 Indirect labor 19,800 20,300 Utilities 10,100 10,900 Supervision 5,800 5,800 All costs are controllable by the department manager.Prepare a responsibility report for April for the cost center. HANNON COMPANYAssembly DepartmentManufacturing Overhead Cost Responsibility ReportFor the Month Ended April 30, 2020 Difference Controllable Cost Budget Actual FavorableUnfavorableNeither Favorablenor Unfavorable Select an opening responsibility report item Indirect MaterialsIndirect LaborSupervisionUtilities $Enter a dollar amount $Enter a dollar amount $Enter the difference Select an option…arrow_forward
- Champion Company manufacturing overhead budget for the first quarter of 2016 contained the following data: Variable Costs Indirect materials $40,000 Indirect labor 24,000 Utilities 20,000 Maintenance 12,000 Fixed Costs Supervisor’s salary $80,000 Depreciation 16,000 Property taxes 8,000 Actual variable costs for the first quarter were: Indirect materials $37,200 Indirect labor 26,400 Utilities 21,000 Maintenance 10,600 Actual fixed costs were as expected except for property taxes which were $9,000. All costs are considered controllable by the department manager except for the supervisor’s salary. Instructions Prepare a manufacturing overhead responsibility performance report for the first quarterarrow_forwardARKANSAS CORPORATION …… is a company that produces machinery to customer order. Its job costing system, using normal costing, has two direct cost categories, direct materials and direct labor, and one indirect cost pool, manufacturing overhead, allocated using a budgeted rate based on direct labor costs. Budgeted and actual information for 2016 are as follows: Budget Actual Direct Labor $420,000 $400,000 Manufacturing overhead $252,000 $186,840 At the end of 2016, the ending work in process consisted of: Ending Work In Process: Direct Materials $64,000 Direct Labor 50,000 Overhead 30,000 $144,000 There were no beginning work-in-process or finished-goods inventories. Ending Finished Goods showed a balance of $156,000, which included overhead costs of $25,200. Cost of goods sold was $1,600,000, of which $184,800 consisted of applied overhead.…arrow_forwardThe following information was taken from the annual manufacturing overhead cost budget of Tamarisk Company: Variable manufacturing overhead costs Fixed manufacturing overhead costs Normal production level in labour hours Normal production level in units Standard labour hours per unit (U) During the year, 4,000 units were produced, 16,300 hours were worked, and the actual manufacturing overhead was $55,600. Actual fixed manufacturing overhead costs equalled the budgeted fixed manufacturing overhead costs. Overhead is applied based on direct labour hours. Your answer is partially correct. Total overhead variance Calculate the total, budget, and volume overhead variances. Budget overhead variance $35,260 $18,860 16,400 JA Volume overhead variance $ e Texthook and Media 4,100 2340 115 2455 Unfavourable Unfavourable Unfavourablearrow_forward
- The manufacturing overhead budget for Pina Colada Company contains the following items. Variable costs (b) Indirect materials Indirect labor Maintenance expense Manufacturing supplies Total variable Variable costs Indirect materials Indirect labor Maintenance expense Manufacturing supplies Total variable $21,120 11,520 Total cost 9,600 $ 5,760 $48,000 Your answer is correct. The budget was based on an estimated 1,920 units being produced. During the past month, 1,440 units were produced, and the following costs incurred. $21,600 13,000 7,900 4,800 $47,300 Fixed costs Supervision Inspection costs Insurance expense 69,600 Depreciation Total fixed Fixed costs Supervision Inspection costs Insurance expense Depreciation $16,300 Total fixed 1,000 1,900 14.400 $33,600 $17,700 1,200 2,100 How much should have been spent during the month for the manufacture of the 1,440 units? 14,100 $35,100arrow_forwardThe measure of activity in the standard costing system used at Esta GmbH is machining hours. The company's flexible manufacturing overhead budget and then data regarding the most recent period's operations are given below: Flexible Budget: Budgeted Level of Activity: 6,600 machining hours Overhead costs at the Budgeted activity level: Variable Overhead Cost: $17,226 Fixed Overhead Cost: $13,992 Most Recent period's operations: Actual level of activity: 7,200 machining hours Standard level of activity for output: 7,140 machining hours Actual total variable overhead cost: $17,856 Actual total fixed overhead cost: $14,256 PART A What is the variable overhead rate variance? (936 favorable, 481 unfavorable, 630 unfavorable, 779 favorable, OR 2,267 favorable) PART B What is the variable overhead efficiency variance? (157 unfavorable, 1409 unfavorable, 1566 unfavorable, 1488 unfavorable, OR 149 unfavorable) PART C What is the fixed overhead budget variance? (264 unfavorable, 1272…arrow_forwardSinbad Company applies factory overhead of the basis of direct labor hours. Budget and actual data for direct labor and overhead for the year are as follows: Budget Actual Direct labor hours 1,200,000 1,300,000 Manufacturing overhead costs 1,440,000 1,520,000 The manufacturing overhead for Sinbad for the current year isarrow_forward
- Privack Corporation has a standard cost system in which it applies overhead to products based on the standard direct labor-hours allowed for the actual output of the period. Data concerning the most recent year appear below: Budgeted variable overhead cost per direct labor-hour $ 4.00 Total budgeted fixed overhead cost per year $ 528,180 Budgeted direct labor-hours (denominator level of activity) 75,455 Actual direct labor-hours 84,000 Standard direct labor-hours allowed for the actual output 81,000 Required: 1. Compute the predetermined overhead rate for the year. Be sure to include the total budgeted fixed overhead and the total budgeted variable overhead in the numerator of your rate. (Round your intermediate calculations and final answer to the nearest whole dollar amount.) 2. Compute the amount of overhead that would be applied to the output of the period. (Round your intermediate calculations and final answer to the nearest whole dollar amount.)arrow_forwardFire King manufactures safes- mobile safes, and walk-in stationary bank safes. As part of its annual budgeting process, Custer is analyzing the profitability of its two products. Part of this analysis involves estimating the amount of overhead to be allocated to each product line. The following information relates to overhead. (a) The total estimated manufacturing overhead was $235,000. Under traditional costing (which assigns overhead on the basis of direct-labor hours), what amount of manufacturing overhead costs are assigned to One mobile safe? The total estimated manufacturing overhead of $235,000 was comprised of $150,000 for material-handling costs and $85,000 for purchasing activity costs. Under activity-based costing (ABC): (b) What amount of material handling costs are assigned to One mobile safe? (c) What amount of purchasing activity costs are assigned to One mobile safe?arrow_forwardThe following information was taken from the annual manufacturing overhead cost budget of Fergie Manufacturing. Variable manufacturing overhead costs $46,200 Fixed manufacturing overhead costs $27,720 Normal production level in labor hours 23,100 Normal production level in units 5,775 Standard labor hours per unit 4 During the year, 5,600 units were produced, 18,340 hours were worked, and the actual manufacturing overhead was $75,600. Actual fixed manufacturing overhead costs equaled budgeted fixed manufacturing overhead costs. Overhead is applied on the basis of direct labor hours. Fergie's total overhead rate is Group of answer choices $1.20. $2.00. $3.27. $3.20.arrow_forward
- Cornerstones of Cost Management (Cornerstones Ser...AccountingISBN:9781305970663Author:Don R. Hansen, Maryanne M. MowenPublisher:Cengage Learning