To control the project, the project team should collect
Group of answer choices
data on the actual performance and information about any changes to the project scope, schedule, and budget.
anecdotal information from the project team members.
reports on the amount of money spent because that is the amount of work completed.
the names and descriptions of the resources used on the project.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps
Knowledge Booster
Similar questions
- This refers to the identification of what generates the project itself. As we said, it may be an opportunity, a need, a shortcoming or a failure. The fact is to define it as well as possible and evaluate its execution. a.Planning b.Evaluation c.Problem Statement d.Designarrow_forwardAll of the following represent the purpose of the project schedule BEFORE the project starts, EXCEPT: (multiple answers can be picked) To create 'what-if' scenarios to analyze alternatives To force detailed thinking To identify the critical path To identify the needed resources To identify who needs to do what and when To keep track of the budget for the project To show the project status To establish the timeframe and organize activities 0000000arrow_forwardYou are a project manager for a project in the execution phase that is on schedule and on budget. Your sponsor asks you for a project status update. What information about your project would you want to include in an update and explain why you picked each.arrow_forward
- Why a well thought out project plan and schedule is important for a successful project? a. It will form the basis for measurement as the project proceeds b. It provides the basis of documentation going forward c. All of them d. It provides the bench mark to monitor progress going forwardarrow_forwardIf hand written ...i'll rate....plz solve it fast... Hand written plzarrow_forwardIssues in project management include a. level of effort. b. period of performance. c. budget. d. all of the above. e. a and c only.arrow_forward
- Which of the following happens during the starting phase of project management? Revise budget Assign tasks. Determine completion Solve problems. Establish team rules.arrow_forwardWhich of the following are major characteristics of projects? Choose all that apply. Has a defined life span with a beginning and an end Requires all project activities to be completed by the same team Has specific performance, time, and cost requirements Has an established objectivearrow_forwardHaving a solid understanding of the project's map will be beneficial. taking into account the effects of the product.arrow_forward
- Hello I am having trouble with these two study questions for my software class. Please let me know if you can help me out. Thanks. Programmer's are overly optimistic when they estimate how long activities will take. True False Recording lessons learned from past projects is not a good source of information for estimating current projects because all projects are different. True Falsearrow_forwardYou’re managing a project with a schedule performance index (SPI) of 1.07and a cost performance index (CPI) of 0.94. How would you BEST describethis project?A. The project is ahead of schedule and within its budgetB. The project is behind schedule and within its budgetC. The project is ahead of its schedule and over its budgetD. The project is behind schedule and over its budget Which of the following is the BEST example of a reward system?A. Everyone will get a bonus of $500 if the project meets its quality goals, $500 if itmeets its budget goals, and $600 if it comes in on time.B. The team member who works the hardest will receive $1000C. The five team members who put in the most hours will get a trip to DisneylandD. The team will only get a bonus if the project comes in 50% under budget, scheduleand quality metric goals. Even though the team leads know this goal is unrealistic,they agree that it will motivate the team to work harder”arrow_forwardWhich one of the following is not a project management technique? A. Project definition B. Scope of work C. Task analysis D. Stakeholder managementarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON
Understanding Business
Management
ISBN:9781259929434
Author:William Nickels
Publisher:McGraw-Hill Education
Management (14th Edition)
Management
ISBN:9780134527604
Author:Stephen P. Robbins, Mary A. Coulter
Publisher:PEARSON
Spreadsheet Modeling & Decision Analysis: A Pract...
Management
ISBN:9781305947412
Author:Cliff Ragsdale
Publisher:Cengage Learning
Management Information Systems: Managing The Digi...
Management
ISBN:9780135191798
Author:Kenneth C. Laudon, Jane P. Laudon
Publisher:PEARSON
Business Essentials (12th Edition) (What's New in...
Management
ISBN:9780134728391
Author:Ronald J. Ebert, Ricky W. Griffin
Publisher:PEARSON
Fundamentals of Management (10th Edition)
Management
ISBN:9780134237473
Author:Stephen P. Robbins, Mary A. Coulter, David A. De Cenzo
Publisher:PEARSON