Utah Technology has a weighted-average cost of capital of 8.85 percent and is evaluating project B. Project B involves an initial investment of $71,700.00 and an expected cash flow of $116,400.00 in 5 years. Project B is considered less risky than an average-risk project at Utah Technology, such that the appropriate discount rate for it is 1.70 percentage points different than the discount rate used for an average-risk project at Utah Technology. The internal rate of return for project B is 10.18 percent. What is the NPV of project B? -$0.00 (plus or minus $10) $4,474.71 (plus or minus $10) $10,712.31 (plus or minus $10) -$1,204.85 (plus or minus $10) None of the above is within $10 of the correct answer

Financial And Managerial Accounting
15th Edition
ISBN:9781337902663
Author:WARREN, Carl S.
Publisher:WARREN, Carl S.
Chapter26: Capital Investment Analysis
Section: Chapter Questions
Problem 2CMA: Staten Corporation is considering two mutually exclusive projects. Both require an initial outlay of...
Question
Utah Technology has a weighted-average cost of capital of 8.85 percent and is evaluating project B. Project B involves an initial investment of $71,700.00 and
an expected cash flow of $116,400.00 in 5 years. Project B is considered less risky than an average-risk project at Utah Technology, such that the appropriate
discount rate for it is 1.70 percentage points different than the discount rate used for an average-risk project at Utah Technology. The internal rate of return
for project B is 10.18 percent. What is the NPV of project B?
-$0.00 (plus or minus $10)
$4,474.71 (plus or minus $10)
$10,712.31 (plus or minus $10)
-$1,204.85 (plus or minus $10)
None of the above is within $10 of the correct answer
Transcribed Image Text:Utah Technology has a weighted-average cost of capital of 8.85 percent and is evaluating project B. Project B involves an initial investment of $71,700.00 and an expected cash flow of $116,400.00 in 5 years. Project B is considered less risky than an average-risk project at Utah Technology, such that the appropriate discount rate for it is 1.70 percentage points different than the discount rate used for an average-risk project at Utah Technology. The internal rate of return for project B is 10.18 percent. What is the NPV of project B? -$0.00 (plus or minus $10) $4,474.71 (plus or minus $10) $10,712.31 (plus or minus $10) -$1,204.85 (plus or minus $10) None of the above is within $10 of the correct answer
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Financial And Managerial Accounting
Financial And Managerial Accounting
Accounting
ISBN:
9781337902663
Author:
WARREN, Carl S.
Publisher:
Cengage Learning,
Managerial Accounting
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Intermediate Financial Management (MindTap Course…
Intermediate Financial Management (MindTap Course…
Finance
ISBN:
9781337395083
Author:
Eugene F. Brigham, Phillip R. Daves
Publisher:
Cengage Learning
EBK CONTEMPORARY FINANCIAL MANAGEMENT
EBK CONTEMPORARY FINANCIAL MANAGEMENT
Finance
ISBN:
9781337514835
Author:
MOYER
Publisher:
CENGAGE LEARNING - CONSIGNMENT