The Dubuque Cement Company packs 80-pound bags of concrete mix. Time-study data for the filling activity are shown in the following table. Because of the high physical demands of the job, the company's policy is a
20%
allowance for workers. (Round all intermediate calculations to two decimal places before proceeding with further calculations.)
|
Performance
|
Observation (seconds)
|
||||||||||
Element
|
Rating
|
1
|
|
2
|
|
3
|
|
4
|
|
5
|
|
|
Grasp and place bag
|
105
|
%
|
8
|
|
10
|
|
9
|
|
12
|
|
6
|
|
Fill bag
|
85
|
%
|
36
|
|
40
|
|
39
|
|
36
|
|
114
|
*
|
Seal bag
|
105
|
%
|
14
|
|
17
|
|
13
|
|
19
|
|
17
|
|
Place bag on conveyor
|
85
|
%
|
7
|
|
6
|
|
9
|
|
30
|
^
|
34
|
^
|
* Bag breaks open; included as delay in the allowance factor
^ Conveyor jams; included as delay in the allowance factor
Part 2
a) The standard time for this process =
enter your response here
seconds (round your response to two decimal places).Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- give two unethical behaviours related to process selection and the ethical principles they violetarrow_forwardThe Money Pit Mortgage Company is interested in monitoring the performance of the mortgage process. Fifteen samples of five completed mortgage transactions each were taken during a period when the process was believed to be in control. The times to complete the transactions were measured. The means and ranges of the mortgage process transaction times, measured in days, are as follows: Sample Mean Range ew an example 1 2 16 12 7 12 Get more help. 3 6 5 4 5 6 7 8 9 15 10 10 13 14 11 9 10 16 13 16 11 Subsequently, samples of size 5 were taken from the process every week for the next 10 weeks. The times were measured and the following results obtained: D Sample Mean Range 16 9 8 17 12 12 18 19 13 7 7 5 20 15 13 MacBook Pro Click the icon to view the table of factors for calculating three-sigma limits for the x-chart and R-chart. a. Construct the control charts for the mean and the range, using the original 15 samples. Set up the R-chart by specifying the center line and three-sigma control…arrow_forward00 R D Question 32 The control of projects involves close monitoring of which of the following? O quality O budgets costs resources O All of the answer choices are correct. Previous Not saved MacBook Air 08 2$ DD F7 3. % F8 Yarrow_forward
- Name four process controls and their importance.arrow_forwardWhat would be the implications of quality initiatives on cost, schedule, and features. What might be the tradeoffs.arrow_forwardThe Dubuque Cement Company packs 80-pound bags of concrete mix. Time-study data for the filling activity are shown in the following table. Because of the high physical demands of the job, the company's policy is a 20% allowance for workers. (Round all intermediate calculations to two decimal places before proceeding with further calculations.) Performance Observation (seconds) Element Rating 1 2 3 4 5 Grasp and place bag 105 % 8 10 9 12 6 Fill bag 85 % 36 40 39 36 114 * Seal bag 105 % 14 17 13 19 17 Place bag on conveyor 85 % 7 6 9 30 ^ 34 ^ * Bag breaks open; included as delay in the allowance factor ^ Conveyor…arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.