Before answering the following questions, you must draw the arrow diagram, rectangles, network calculations, and the project diagram, the details of which are shown in the table below. Time (week) Activity Dependency Resource a m 2 1.5 2 2.5 3 3 2.5 1 2 А, В 1.5 2 2.5 0.5 1 1.5 2 F D 2 3 3 D, E C, F, G С, G 3 3.5 3 4 2 1.5 2 2.5 2 13 - The average value of the resources needed by the project is All options are incorrect 4.23 6.00 3.73 4.08 3.82 63 M75 EN ABCDEECHI
Q: 4. Schedules and activities of a project are shown below. Answer the questions. Activity…
A: A) The CPM chart is as follows: The critical path is: A-D-E-H-I-L
Q: __________2a) What steps comprise the “critical path”? __________2b) What is the minimum completion…
A: A project network is a graphical network that shows the duration of project activities and their…
Q: QI/B/ For the project data in Table below, answer the following questions: a) Draw an AOA network of…
A: Given data is
Q: Draw the network and identify the critical path. Also calculate the earliest-latest starting and…
A: The method used for scheduling a set of activities that form part of a project, is called critical…
Q: Below is the first set of activities (Phase I) in constructing a new house, the respective time…
A:
Q: Paul Silver, owner of Sculptures International, just initiated a new art project. The following data…
A: a. The network diagram for the project is:
Q: The Laurenster Corporation is getting into the construction business. A list of activities and their…
A: ES = maximum (EF of all immediate predecessor) EF = ES + duration Minimum project duration = largest…
Q: A) Draw the Gantt Chart B) Draw the Network Diagram C) Identify and draw the critical path using the…
A: A project schedule network diagram shows the sequence of the task that are performed to complete a…
Q: snip
A: Note: Since you have posted a question with multiple sub-parts, we will solve the first three…
Q: A project has been defined to contain the following activities, along with their time estimates for…
A: The Critical path diagram of the given activities as follows -
Q: The following information is available about a project to organize an event to honor the mayor of…
A: a.
Q: A local grocery store plans on holding a big sales event at the end of season. The activities that…
A: Given - Activity Duration (Weeks) Immediate Predecessor A 3 - B 1 A C 4 A D 2 B E 3 D,…
Q: activities, define the located activities on the critical path, define the total project duration,…
A: Find the Given details below: Activity Precedent Activity Time (Week) A - 7 B - 5 C B, E…
Q: For the following sitution draw a PERT network, and determine the following: Critical path…
A: The Program Evaluation and Review Technique (PERT) can be defined as a technique in which an…
Q: Norton Industries is installing a new computer system. The activities, the activity times, and the…
A: Crashing an activity is basically adding more assets toward an activity so it tends to be finished…
Q: 5) Draw the Network and do the analysis Using the information in Table 1, assuming that the project…
A: Note: - Since we can answer only up to 3 subparts, we will answer sub part i, ii, and iii for…
Q: (a) What is the critical path? (b) How long will it take to complete this project? (c) Can…
A: A network diagram related to the project shows the sequence of the task that is performed to…
Q: The detail of the direct cost for project XYZ are given in Table 1. Table 1 Details for Project XYZ…
A: Given data is
Q: Project Activity and Time (days) Data Activity Normal Time (days) Crash Time (days) Immediate…
A: Using the following format for the network diagram: Early Start(Es Duration Early Finish(EF)…
Q: Roger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A: a. The network diagram is as follows:
Q: Below is the network diagram from a project: B(2) D(5) A(2) F(3) C(5) E(3) What is the slack for…
A: A project network is the visual representation of the project activities and their respective…
Q: For the following sitution draw a PERT network, and determine the following: Critical path…
A: Since you have posted a question with multiple sub-parts, we will solve first three subparts for…
Q: Q1,Draw the network. Q2,what is the critical path Q3,how many weeks will it take to complete the…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: A project has the following activities, with specified precedents and expected durations (in days).…
A: The AON diagram with the given table:
Q: E G 5) 2. 4 days 9 days A-5/ days C-2 days F8 days H-7 days B-3 days D 3 4. 6. 5 days 6 days
A: What is Early Start & Late Finish? In any activity network diagram, there will be multiple…
Q: The Laurenster Corporation is getting into the construction business. A list of activities and their…
A: Expected time of each activity, Activity to tm tp te=to+4⋅tm+tp6 σ2=(tp-to)62 A…
Q: The table below shows the complete project plan and includes all the activities with its immediate…
A: A network diagram is a visual representation of a project which helps to calculate the project…
Q: oger Ginde is developing a program in supply chain management certification for managers. Ginde has…
A: The project network is the diagrammatic form in which project activities and their durations are…
Q: Draw the network diagram of the following activities. Activity Dependencies Duration A 2 В 2 4. D 8…
A: a. The minimum time required to complete the project is known as the project duration and that can…
Q: a) Calculate each activity duration using the last digit of your student number For example, if your…
A: Below is the solution:-
Q: A project has the following activities, with specified precedents and expected durations (in hours).…
A: A network diagram is a diagram that shows the visual form of the project activities and their…
Q: Consider the following data for a project to reorganize the office space at Platinum Financial…
A:
Q: Consider the following project.…
A: The critical path method (CPM), otherwise called critical path examination (CPA), is a booking…
Q: able Activities Name A E Predecessor A А, В D C, E Time (Days) 7 9 12 9.
A: As per Bartleby guidelines, we can only solve one question at a time...Kindly upload the other…
Q: 1. A new application development project at NeuProd, Inc. consists of the following activities:…
A: Project management is the management in which different types of knowledge and skills are needed to…
Q: Using the network diagram constructed in Problem 1,(a) Calculate the completion time for the…
A: The completion time of the project can be calculated as below:
Q: Reliable Garage is completing production of the J2000 kit car. The following data are available for…
A:
Q: Construction of a building is based on the followingCPM network:a. Draw the network for this project…
A: "Since you have posted a question with multiple sub-parts, we will solve first three sub-parts for…
Q: Task time estimates for the modificat ion of an assembly line at Jim Goodale's Carbondale, Illinois,…
A: Since you have posted a question with multiple sub-parts, we will solve the first three subparts for…
Q: For the small project with the relationships shown below. Activity IPA's Duration (Day) A В 7 C 4…
A: Given Information:
Q: Please help me answer parts 3. and 4. of this question if not all of them. Thank you
A: Forward Pass:Early Start = Maximum (or Highest) EF value from immediate Predecessor(s)Early Finish =…
Q: 11-23 Tom Schriber, the director of personnel of Manage- ment Resources, Inc., is in the process of…
A: In a network diagram, the activities with no predecessor activities are initial activities. When an…
Q: Before answering the following questions, you must draw the arrow diagram, rectangles, network…
A: Find the Given details: Activity Dependency Optimistic Time(To) a(Days) Pessimistic Time(Tp)…
Q: What is the slack time for activity A? 7 5 3 0
A: Formula:
Q: Roger Ginde is developing a program in supplychain management certification for managers. Ginde…
A: Hi, we are supposed to answer three subparts at a time. Since you have not mentioned which subpart…
Q: a) Calculate each activity duration using the last digit of your student number. For example, if…
A: THE ANSWER IS AS BELOW:
Q: The table below show a set of activities of an IS project,its expected completion time (ET) and…
A: 1. Activity Immediate Predecessors Duration A - 7 B A 9 C A , B 5 D C 17 E C 12 F C 7…
Q: Draw a project network given the information below. Time (Days) Predecessor Description First…
A: A network diagram is the pictorial representation of all the activities in the project in…
Q: For the activity times and network model below, What is the expected completion time? ________ What…
A: Here is the network diagram with activity & time duration :
Trending now
This is a popular solution!
Step by step
Solved in 2 steps with 3 images
- What is the minimum cost of crashing the following project that Roger Solano manages at Slippery Rock University by 4 days? Normal Cost $800 $200 $600 $750 $1,200 Normal Crash Activity Time (days) Time (days) 4 3 8 6 The total cost of crashing the project by 4 days is $ ABCDE 487 355 (Enter your response as a whole number.) Total Cost with Crashing Immediate Predecessor(s) $1,500 $1,650 By how many days should each activity be crashed to reduce the project completion time by 4 days? Fill in the table below. (Enter your responses as whole numbers.) Each Activity Should be Reduced BY (days) Activity A B C D E $1,100 $600 $650 A CImage of Diagram included Using the diagram, find: The critical path. How long it will take to complete the project? How does simulation determine the probabilities of various project completion times? What is "slack" and why is it important? Why is activity-on-arrow (AOA) or activity-on-node (AON) of significant value to the project manager? How is the uncertainty in project scheduling dealt with? Should the critical path activities be managed differently from noncritical path activities? Explain.Can i get help with the question below please and thank you 16) This could be a rover, probe/satellite, manned mission, telescope, etc. This mission must be accomplished using technology that is available today (no Warp or Epstein drives) and must be accomplished within your lifetime. Your mission will not be a copy of a real mission. Constraints: ▪ Answer using the underlined subheadings at each point below (Mission Objective, Target, Instrumentation), marks will be deducted for poorly organized answers. ▪ You target must be reachable by whatever you are sending within a human lifetime (~75 years), it would be nice to visit Gliese 581c, but it is 20 light years from Earth so for now it is unreachable. What this means is that you are constrained to our solar system except for telescopes that peer into the universe or a probe getting to interstellar space. ▪ If your mission includes sending humans, then we need to estimate a reasonable limit on how far we can send humans. For our…
- 2:30 PM ě 0.3KB/s 1ll 54 4G+ 00:15:12 Remaining Multiple Choice The primary difference between PERT and CPM is that CPM uses probabilities on the activity times and PERT does not. O. PERT considers activity costs and CPM does not. PERT can assign probabilities to activity times and CPM does not. CPM considers activity costs and PERT does not. 5 of 20 IIThe table below contains data for the installation of new equipment in a manufacturing process for a steel corporation. Your company is responsible for the installation project. Indirect costs are $6,000 per week, and a penalty cost of $10,000 per week will be incurred by your company for every week the project is delayed beyond week 15. Activity Immediate Predecessor(s) Normal Time (weeks) Crash Time (weeks) Normal Cost ($) Crash Cost ($) A None 2 1 7,000 10,000 B None 2 2 3,000 3,000 C A 3 1 12,000 40,000 D B 3 2 12,000 28,000 E C 1 1 8,000 8,000 F D, E 5 3 5,000 15,000 G E 3 2 9,000 18,000 H F, G 8 6 14,000 32,000 Construct a network diagram for the project. What are the project completion time and the total cost under normal conditions? What is the shortest time duration for this project regardless of cost? What is the resulting total cost? What is the…Problem Statement: Project Control and Monitoring You are working on a manufacturing project having a budget of PKR 3,600,000 and expected time of its completion is one year. There is an ideal condition that your budget and work are evenly spread across the duration of the project that is twelve month. At the end of forth month, the senior management has called a meeting and invited all the stakeholders to brief about the status of the project. You being the PM of this project is giving the presentation to all the attendees and informed that project is on schedule and PKR 1,800,000 have already been spent on the project. Required: Calculate Cost and Schedule Variance What is SPI and CPI of the project? Estimate at completion and Estimated time to complete?
- Given the data for a project in table Q3, using the following assumptions: 1. 8 hours as working day 2. The company will work all days. 3. Maximum number of workers available per day is 6 4. Activities cannot be break down 5. Budget will distributed equally per day, except for activities (B, H and L), the payment will be after two days of working: means that the first payment will be at the end of day2, then day four and so on. 6. They estimate that the work will starts on the first of November 2017 Develop a report containing the followings: Date of finish BAD O GYEK 1. 2. Early start and Slack time for each activity 3. Resource histogram 4. Cumulative Budget baseline curve 5. Interpret the final report co Table Q3 Duration (Hrs) No of Workers Budget Activity predecessor A None 48 12000 64 32000 C 16 10000 32 4. 12000 B,C 32 8000 B,C 16 6000 G B,C 16 4 10000 H. 64 16000 3. 16 4000 32 1 12000 K 32 3 16000 H. 48 1 12000 Total Budget of RM150000B/U pe Activity A B D 11. A project has the activity duration and cost information indicated in the table where all times are in weeks. There is a penalty of $4,000 per week for every week the project exceeds 37 weeks. What is the lowest total cost for completing this project? Predecessor Time 18 11 A A B C E D Normal A H 12 15 3 19 Asbe de ABC' AMBBC RACE AB 7 8 12 6 Normal Cost Crash Time Crash Cost $22,000 $32,000 $62,000 $18,000 $35,000 $8,000 $23,000 $32,000 $56,000 $12,000 5 $18,000 19 $22,000 $9,000 $15,000 $5,000 $13,000 $20,000 $45,000 2 5 4PERT/CPM HOMEWORK (MOD 10) In the table below, you will see activities and times associated with each activity. Review the PowerPoint slides in Module 10 , before you start this assignment. Task Preceding Tasks to (optimistic) tm (most likely) tp (pessimistic) A NONE 2 3 10 B NONE 2 3 4 C A 1 2 3 D A 4 6 14 E B 4 5 12 F C 3 4 5 G D,E 1 1 7 1.) Draw the network using the table above. Make sure all 4 values (ES, EF, LS, LF) are listed on the network. 2.) What is the slack for each activity? What is the critical path? Show ALL of your work! 3.) Find the expected project completion time. What is the project variance? 4.) What is the probability that it would be in more than 14 days? Show ALL of your work. *The circle diagram picture is just an example of how it should look it is not apart of the problem in the chart
- 1 Cara's clients, Emily and Dave, have just had a baby and she would like to do something nice for them. She signs them up for a baby registry that sends them a small gift. Emily and Dave will be sent information and service lists that are geared toward helping new parents. She provided their names, address and phone numbers so that they will not miss any of the activities provided in the package. Has Cara dealt with her clients appropriately? NUYLOTNQhObm1bEVKUTO90 a0 Cara did not protect her clients' privacy when she shared their personal information with the baby registry. O Cara should not make this a regular practice. Her clients will begin to expect gifts and she will not be able to sustain this. CO Cara should have set up an appointment to re-evaluate her clients' needs now that they have had a baby. 40 Cara's gift is very thoughtful and will help to build a relationship with her clients. NUTYks10TNRUQ2h0bmkbEVKUTO90Normal Time Problem 1 You are the manager of a project to improve a billing process at your firm. The following table contains the data you will need to conduct crashing of the project duration. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12. Activity Immediate Predecessor(s) Crash Time (weeks) Normal (Direct) Cost Crash Cost (weeks) ($) ($) A 4 1 5,000 8,000 B 5 2 8,000 11,000 C A 1 1 4,000 4,000 Ꭰ B 6 3 6,000 12,000 E B, C 7 6 4,000 7,000 F Ꭰ 7 6 4,000 7,000 What is the optimum choice for project duration?What is the minimum cost of crashing the following project at Sawaya Robotics by 4 days? NORMAL TIME (DAYS) CRASH TIME (DAYS) 5 4 ACTIVITY Design (A) Wiring (8) Chip install (C) 7 5 3 4 7 2 2 4 NORMAL COST 300 900 500 CRASH COST 1,100 1,200 350 975 575 Software (D) Testing (E) The minimum cost of crashing the following project at Sawaya Robotics by 4 days is $1,875 (enter your response as a whole number). IMMEDIATE PREDECESSOR(S) 1,300 1,650 A, B с