Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
expand_more
expand_more
format_list_bulleted
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
Knowledge Booster
Similar questions
- Problem 4 Draw the network diagram from the following information. Create a data sheet for ES, EF, LS, LF, TF, FF, INTF and Independent Float. Find the critical path and critical activities. CIV 417/CPM THE NETWORK DIAGRAM Activity Duration (days) Activity Description 1-2 Relocation of Boundaries-Cleaning 1 2-3 2 Construction of Field Office 2-4 5 Delivery of Materials 2-5 2 Staking and batter boards 3-5 Digging/excavation 4-5 10 Cutting and assembling of steel reinforcement 4-7 Dummy 3-6 12 Making of forms and door jambs 5-6 Positioning Steel Reinforcement 5-7 Forms and Scaffoldings 5-8 8 Electrical, plumbing and water pipe connections 6-8 Dummy 6-9 Pouring of footings and columns 2 7-8 1 Removal of forms CIV 417/CPM 95arrow_forwardPlz provide correct Answer for it previous one was wrongarrow_forwardTIME (WEEKS) COST (P) CRASH COST CRITICAL ACTIVITY NORMAL CRASH NORMAL CRASH PER WEEK (P) РАTH? A 2 1 22,000 23,000 1,000 Yes В 3 1 30,000 34,000 2,000 No 1 26,000 27,000 1,000 Yes 48,000 49,000 58,000 D 4 3 1,000 No E 4 2 56,000 1,000 Yes F 3 2 30,000 30,500 500 No G 5 80,000 86,000 2,000 Yes H 2 16,000 19,000 3,000 Yes Table 1. above shows the normal and crash data for General Foundry, Inc. a) Determine the project completion time (if no delays occur). b) Determine the crash cost if the project is crashed to 12 weeks.arrow_forward
- Which one is NOT one of the three time estimates used with PERT?a) Optimistic timeb) Most cost-effective timec) Pessimistic timed) Most likely timearrow_forwardA company must perform a maintenance project consisting of seven activities. The activities, their predecessors, and their respective time estimates are presented below: Activity Break down both machines Clean machine 1 Clean machine 2 Re-set machine 1 Re-set machine 2 Re-calibrate both machines. Final test Designation A B с Using CPM, which activities have slack in this project? D E F G Immediate Predecessor None A A B с D and E F Time in Days 3 3 3 4 2 1 1arrow_forward.arrow_forward
- Example 2.39 Table 2.119 provides normal and crash times as well as normal and crash costs for the activities of a project. Table 2.119 Project activity details Activity Normal Time (Weeks) Normal Cost (Lakhs) Crash Time (Weeks) 1-2 3 5 2-3 4 8 2-4 3 4 2-5 8 S 3-6 4 3 4-6 6 2 5-7 5 10 6-7 3 7 1 3 2 7 2 4 4 1 Crash Cost (Lakhs) 9 14 6 6 5 3 14 10 Project Network Analysis-1 | 141 (a) Draw the network and find the critical path. (b) Using the above information, crash or shorten the activities step by step until the shortest duration is reached. MMM, VI Sem, Mumbai Univ, 2006arrow_forwardThe following table details the tasks required for Indiana-based Frank Pianki Industries to manufacture a fully portable industrial vacuum cleaner. The times in the table are in minutes. Demand forecasts indicate a need to operate with a cycle time of 11 minutes. Fig. 1 Activity Activity Description rerormance Predecessors Time (mins) A Attach wheels to tub 5.0 B Attach motor to lid 1.6 Attach battery pack Attach safety cutoff 3.0 D 3.6 Attach filters 3.0 Fig. 2 F Attach lid to tub 2.0 A, E G Assemble 3.0 attachments H. Function test 3.7 D, F, G Final inspection Packing 2.0 J 2.0 a-b) One of the possible assignment of tasks to workstations is shown correctly in Fig. 2. The efficiency of the assembly line with 3 workstations = 99.31 % (enter your response rounded to two decimal Fig. 3 places). c) The goal is to have 100% efficiency. Is this possible? No BI d) The theoretical minimum number of workstations = (round your response up to the next whole number).arrow_forwardActivity Normal_time Crash_time Normal_cost Crash_cost Slack A 31 17 4800 6200 В 14 14 5500 5500 C 34 18 5100 6600 21 17 4500 6800 E 15 15 5300 5300 F 17 17 5300 5300 The table shows normal time, crash time, normal cost, crash cost and slack time of activities in a project. According to this table which activity must be crashed first? Assume there is only one critical path. (Only type the name of the activity, Example: A. @orsdemir. Copyrighted content. Cannot be posted.) 0ㅇ11 2 0arrow_forward
- Q6:write briefly but relevant answer a) PERT and CPM b) Risk Management and its types.arrow_forwardtime (hours) pH 7.00 7.30 6.99 7.00 Assignment 1 2 7.12 7.25 7.12 7.20 3 720 7.16 720 7.16 4 6.98 7.00 6.94 7.00 5 6.99 6.99 6.99 6.98 6 7.00 6.93 7.02 6.93 7 6.92 7.00 6.92 7.02 Construct the X-Bar charts and R- charts 6.88 6.82 6.94 6.99 7.10 7.00 7.00 7.00 for reporting your results 10 721 7.02 721 7.04 11 7.01 6.86 7.01 6.90 12 6.86 6.98 6.90 6.98 13 6.90 7.00 6.87 7.00 14 7.01 7.04 7.01 7.05 15 7.00 6.95 7.00 6.99 16 7.09 7.20 7.03 7.20 17 6.89 7.14 6.87 7.15 18 6.98 6.80 6.98 6.89 19 7.00 6.90 7.00 6.90 20 7.20 7.00 723 7.00 21 7.04 7.03 7.08 7.00 22 6.90 6.92 6.98 6.92 23 7.00 7.00 7.00 7.00 24 7.00 6.97 7.01 6.98arrow_forward4,4 The late start time for activity c is: 04 b, s None of the above 14 7 O11 0.3 d5 f. 2 h, Iarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.