The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek C Task A B C D E F Were you able to assign all the tasks to the theoretical minimum number of workstations? No ) The total idle time per cycle for the process = seconds (enter your response as a whole number). Performance Time (seconds) 24 28 15 14 10 28 This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train set = 30 seconds (round your response to one decimal place) Predecessors c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number). d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks) Task A B C D E F A A A B, C D, E Workstation # Station 1 Station 2 Station 3 Station 3 Station 4 Station 5

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section: Chapter Questions
Problem 111P
icon
Related questions
Question
The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek
Performance Time
(seconds)
24
28
15
14
10
28
Were you able to assign all the tasks to the theoretical minimum number of workstations? No
e) The total idle time per cycle for the process
Task
A
=
כם 4 ס ח ד
seconds (enter your response as a whole number).
B
C
D
This exercise only contains parts b, c, d, e, and f.
b) Given the demand, the cycle time for the production of the new train set = 30 seconds (round your response to one decimal place).
E
F
c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number).
d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.)
Task
Workstation #
Station 1
Station 2
Station 3
Predecessors
A B C D E F
A
A
A
B, C
D, E
Station 3
Station 4
Station 5
K
Transcribed Image Text:The Action Toy Company has decided to manufacture a new train set, the production of which is broken into six steps. The demand for the train is 4,800 units per 40-hour workweek Performance Time (seconds) 24 28 15 14 10 28 Were you able to assign all the tasks to the theoretical minimum number of workstations? No e) The total idle time per cycle for the process Task A = כם 4 ס ח ד seconds (enter your response as a whole number). B C D This exercise only contains parts b, c, d, e, and f. b) Given the demand, the cycle time for the production of the new train set = 30 seconds (round your response to one decimal place). E F c) The theoretical minimum number of workstations = 4 (round your response up to the next whole number). d) Using the longest operation time rule, the assignment of tasks to workstations should be: (Hint: Number workstations sequentially in terms of precedence relationships and combine any applicable tasks.) Task Workstation # Station 1 Station 2 Station 3 Predecessors A B C D E F A A A B, C D, E Station 3 Station 4 Station 5 K
Expert Solution
trending now

Trending now

This is a popular solution!

steps

Step by step

Solved in 5 steps with 6 images

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,