Table above shows the task time and precedence relationships for a pizza assembly. The product time per day is 8 hours and the production schedule requires 300 pizzas per day by the assembly time. 1. Draw the precedence diagram of the operation. 2. Determine the cycle time of the line. 3. Calculate the minimum number of workstations for this operation.
Table above shows the task time and precedence relationships for a pizza assembly. The product time per day is 8 hours and the production schedule requires 300 pizzas per day by the assembly time. 1. Draw the precedence diagram of the operation. 2. Determine the cycle time of the line. 3. Calculate the minimum number of workstations for this operation.
Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
Related questions
Question
![Table : Task time pizza assembly
Task
Description
Roll Dough
Add pizza source
Sprinkle cheese
A
B
с
D
E
F
G
H
Task time (sec) Preceding task
60
30
35
25
Add sausage
Add Pepperoni
35
Add Mushrooms 22
Shrink-wrap pizza 15
Add label
23
A
B
с
с
с
D,E,F
G
Total time
245 sec
Table above shows the task time and precedence relationships for a pizza assembly. The product time per day is
8 hours and the production schedule requires 300 pizzas per day by the assembly time.
1. Draw the precedence diagram of the operation.
2. Determine the cycle time of the line.
3. Calculate the minimum number of workstations for this operation.
4. Construct the line layout of the operations following by rules below:
5. Longest task time rule.
6. Number of following rules.
7. Compute the resulting efficiency and balance of delay percentages.
8. If a worker is paid RM35 per day, compute the cost of idleness per week (assuming a work 6-day week).](/v2/_next/image?url=https%3A%2F%2Fcontent.bartleby.com%2Fqna-images%2Fquestion%2Fdea2fd47-b722-4ff7-ae78-d6b86a278330%2Fe1b68f30-bb79-4ade-a35d-d0aa8a127db2%2F3mbstx_processed.jpeg&w=3840&q=75)
Transcribed Image Text:Table : Task time pizza assembly
Task
Description
Roll Dough
Add pizza source
Sprinkle cheese
A
B
с
D
E
F
G
H
Task time (sec) Preceding task
60
30
35
25
Add sausage
Add Pepperoni
35
Add Mushrooms 22
Shrink-wrap pizza 15
Add label
23
A
B
с
с
с
D,E,F
G
Total time
245 sec
Table above shows the task time and precedence relationships for a pizza assembly. The product time per day is
8 hours and the production schedule requires 300 pizzas per day by the assembly time.
1. Draw the precedence diagram of the operation.
2. Determine the cycle time of the line.
3. Calculate the minimum number of workstations for this operation.
4. Construct the line layout of the operations following by rules below:
5. Longest task time rule.
6. Number of following rules.
7. Compute the resulting efficiency and balance of delay percentages.
8. If a worker is paid RM35 per day, compute the cost of idleness per week (assuming a work 6-day week).
Expert Solution
![](/static/compass_v2/shared-icons/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 3 steps with 3 images
![Blurred answer](/static/compass_v2/solution-images/blurred-answer.jpg)
Recommended textbooks for you
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Practical Management Science](https://www.bartleby.com/isbn_cover_images/9781337406659/9781337406659_smallCoverImage.gif)
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
![Operations Management](https://www.bartleby.com/isbn_cover_images/9781259667473/9781259667473_smallCoverImage.gif)
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
![Operations and Supply Chain Management (Mcgraw-hi…](https://www.bartleby.com/isbn_cover_images/9781259666100/9781259666100_smallCoverImage.gif)
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
![Business in Action](https://www.bartleby.com/isbn_cover_images/9780135198100/9780135198100_smallCoverImage.gif)
![Purchasing and Supply Chain Management](https://www.bartleby.com/isbn_cover_images/9781285869681/9781285869681_smallCoverImage.gif)
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
![Production and Operations Analysis, Seventh Editi…](https://www.bartleby.com/isbn_cover_images/9781478623069/9781478623069_smallCoverImage.gif)
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.