storey residential project, make a logical arrangement of activities by filling out the column for Predecessor Activities. 2. Construct a Network Diagram. 3. What is the project duration if no delays will occur? 4. What are the activities in the Critical Path? 5. What is the Early Start and Early Finish of each activity? 5. What is the Late Start and late Finish of each activity?

Structural Analysis
6th Edition
ISBN:9781337630931
Author:KASSIMALI, Aslam.
Publisher:KASSIMALI, Aslam.
Chapter2: Loads On Structures
Section: Chapter Questions
Problem 1P
icon
Related questions
Question
1. Given below is the list of activities with respective durations of a single-
storey residential project, make a logical arrangement of activities by
filling out the column for Predecessor Activities.
2. Construct a Network Diagram.
3. What is the project duration if no delays will occur?
4. What are the activities in the Critical Path?
5. What is the Early Start and Early Finish of each activity?
6. What is the Late Start and late Finish of each activity?
Activities
Duration
Predecessors
1. Clearing and Grabbing
3 DAYS
2. Excavation
9 DAYS
3. Soil Poisoning
3 DAYS
4. Rebar Works
30 DAYS
24 DAYS
5. Concreting
6. Backfilling
7. Forms and Scaffolding
9 DAYS
36 DAYS
8. CHB laying
24 DAYS
9. Carpentry
10. Roofing
24 DAYS
12 DAYS
11. Tiles Installation
| 6 DAYS
12. Hardwares
3 DAYS
13. Plumbing
14. Electrical
24 DAYS
27 DAYS
15. Painting
6 DAYS
Transcribed Image Text:1. Given below is the list of activities with respective durations of a single- storey residential project, make a logical arrangement of activities by filling out the column for Predecessor Activities. 2. Construct a Network Diagram. 3. What is the project duration if no delays will occur? 4. What are the activities in the Critical Path? 5. What is the Early Start and Early Finish of each activity? 6. What is the Late Start and late Finish of each activity? Activities Duration Predecessors 1. Clearing and Grabbing 3 DAYS 2. Excavation 9 DAYS 3. Soil Poisoning 3 DAYS 4. Rebar Works 30 DAYS 24 DAYS 5. Concreting 6. Backfilling 7. Forms and Scaffolding 9 DAYS 36 DAYS 8. CHB laying 24 DAYS 9. Carpentry 10. Roofing 24 DAYS 12 DAYS 11. Tiles Installation | 6 DAYS 12. Hardwares 3 DAYS 13. Plumbing 14. Electrical 24 DAYS 27 DAYS 15. Painting 6 DAYS
Expert Solution
steps

Step by step

Solved in 2 steps with 1 images

Blurred answer
Knowledge Booster
Estimating construction costs
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, civil-engineering and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Structural Analysis
Structural Analysis
Civil Engineering
ISBN:
9781337630931
Author:
KASSIMALI, Aslam.
Publisher:
Cengage,
Structural Analysis (10th Edition)
Structural Analysis (10th Edition)
Civil Engineering
ISBN:
9780134610672
Author:
Russell C. Hibbeler
Publisher:
PEARSON
Principles of Foundation Engineering (MindTap Cou…
Principles of Foundation Engineering (MindTap Cou…
Civil Engineering
ISBN:
9781337705028
Author:
Braja M. Das, Nagaratnam Sivakugan
Publisher:
Cengage Learning
Fundamentals of Structural Analysis
Fundamentals of Structural Analysis
Civil Engineering
ISBN:
9780073398006
Author:
Kenneth M. Leet Emeritus, Chia-Ming Uang, Joel Lanning
Publisher:
McGraw-Hill Education
Sustainable Energy
Sustainable Energy
Civil Engineering
ISBN:
9781337551663
Author:
DUNLAP, Richard A.
Publisher:
Cengage,
Traffic and Highway Engineering
Traffic and Highway Engineering
Civil Engineering
ISBN:
9781305156241
Author:
Garber, Nicholas J.
Publisher:
Cengage Learning