Question

Question 1
An assembly line must be designed to produce 40 containers per hour. The following data give
the necessary information

Please use table  in the image provided to answer the following questions

iv. Assign the tasks to workstation?
v. What is the efficiency of the line? 
vi. Calculate the idle time. 

TASK TIME (sec)
IMMEDIATE
PREDECESSOR
TASK
A
None
60
В
A
12
C
В
35
D
A
55
E
D
10
F
E
50
G
F, C
5
expand button
Transcribed Image Text:TASK TIME (sec) IMMEDIATE PREDECESSOR TASK A None 60 В A 12 C В 35 D A 55 E D 10 F E 50 G F, C 5
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Similar questions
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.