Question 1
An assembly line must be designed to produce 40 containers per hour. The following data give
the necessary information
Please use table in the image provided to answer the following questions
iv. Assign the tasks to workstation?
v. What is the efficiency of the line?
vi. Calculate the idle time.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 4 steps with 3 images
Knowledge Booster
Similar questions
- system analysis and desingarrow_forward2 external references,of process, location and layout strategies with examples.arrow_forward(Layout Strategies) A steel workshop wants to improve its productivity by making small metal hooks by changing the layout of the workshop into a workstation. The workshop has made observations on the activities of its workers in the workshop and arranged these activities in the form of the table below. Activities Duration (in seconds) Predecessor A 17 None B 15 A C 18 B D 8 B E 12 B F 6 C,D,E G 14 F The workshop aims to produce 225 small metal hooks for 2 hours. Based on this information, please answer the questions below. Sketch a precedence diagram of the above activity Calculate cycle time and the minimum number of workstations to be made Make a grouping of the workstations Calculate the efficiency of the work with the workstationarrow_forward
- An assembly line made up of 10 operators currently operates with the following standard minute times at each workstation. What is the efficiency of the line? Workstation Standard Minutes to Perform Operation 1 1.20 2 1.23 3 1.42 4 1.18 5 1.20 6 1.36 7 1.41 8 1.06 9 1.11 10 1.40arrow_forwardWhich are the Tools of Shop-Floor Control?arrow_forwardI have uploaded 2 pictures of the question.arrow_forward
- Hi, I need help solving the remainder of this Operations Management problem. Thank you! *Notes: - The correct answer to part B is also known, "66.8" - "13.4" and "13.5" were both attempted for part C and are not the correct answersarrow_forwardPart D) I would like to double check my answerarrow_forwardNotes: please have answer as decimal, not fraction. Also - round final answer to two decimal places.arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.