Station 1 Machine A 20 min/unit Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 3 8 min/unit A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. The process time of each machine/station is indicated in the flowchart. What is the capacity rate of this system measured in units/min?
Q: The best way to explain the steps involved in project management is through an example, but is it…
A: Yes, it is possible to explain the steps involved in project management through an example. Here is…
Q: 21. Using Northwest Corner Rule, how many must be supplied from Visayas to Taguig? (a) 170 (b) 180…
A: As per Bartleby guidelines, we can only solve the first three subparts of one question at a…
Q: Compute correctly the 3day forecast report, show the computation and solutions
A: %occ = Total rooms occupied/total rooms x 100
Q: What are the steps you need to take to ensure that your opening day will not bomb? (If you were to…
A: Opening a new shop in an area can be an exciting but also challenging experience, particularly if…
Q: Sales of Volkswagen's popular Beetle have grown steadily at auto dealerships in Nevada during the…
A: The above-given question is to calculate the sales forecasting, MAD and MSE. sales regression…
Q: What are the various types of groups often found in work situations? Why do people join groups?…
A: The above-given questions are regarding work groups and teams. Workgroup design can be described in…
Q: The following diagram represents a process where two components are made at stations A1 and A2 (one…
A: The average hourly output of the process determines the number of units that can be or are being…
Q: has recently added a new product to their offerings. Manufacturing reports that production is going…
A: Given- Time to manufacture first unit (T1) = 500 hoursTime to manufacture second unit (T2) = 375…
Q: Consider a firm like Zara that has developed production capabilities with very short replenishment…
A: A short lead time will mean that less cash is attached to the safety stock, regardless of whether…
Q: Alinear programming computer package is needed. Western Family Steakhouse offers a variety of…
A:
Q: Provide an explanation for the operation of predictive analytics and a scenario in which it might be…
A: Predictive analytics is the utilization of data, statistical algorithms, and machine learning…
Q: More Info Clamp (1) The product structure. Base (1) Bracket Spring (2) Housing (1) Handle (1)…
A: Product diagram-
Q: The activity variance along the critical path is [ ? ]
A: Here, for each activity, I would determine the expected activity time, standard deviation and…
Q: Q2 . write about managment planning and explined it probably about 250 words
A: Planning in Management or Management Planning - It is the fundamental aspect of management that…
Q: John is operating a business in the Caribbean in the manufacturing sector. Over the years the…
A: 6. If John decides to expand to South Korea, Canada, Taiwan, Thailand, or Japan, a PESTEL analysis…
Q: The demand (in units) for a product in the past 4 months are: 371, 398, 384, 367 What is the value…
A: Naive method predicate that next time period value will be the current period value.
Q: True or False 1. Given three corner points A, B, and C of a linear programming problem, if A is…
A: Linear programming is a mathematical optimization technique used to find the best solution to a…
Q: A patient takes vitamin pills. Each day he must have at least 360 IU of vitamin A, 4 mg of vitamin…
A:
Q: b. What is the critical path? O A-C-D-E-G O A-B-E-G OA-C-D-F-G O A-B-D-F-G c. How many weeks will it…
A: A network diagram shows the sequence of the task that is done to complete a project. It usually…
Q: Labor unions were created to protect its members from subjective and unpredictable treatment by…
A: An association of various people protecting their interests and rights concerning their employment…
Q: Among all of the stakeholders in an office project, which is NOT a reason to do a market study?…
A: A market study is an analysis process that mainly focuses on identifying the demand and supply…
Q: 1. Describe some of the factors that make up a culture. Also, indicate where these factors come…
A: Culture, in straightforward terms, is alluded to as the shared qualities of a specific gathering,…
Q: true or false Building scenarios is a tool to help with concept generation.
A: Scenario planning is a strategic management tool that involves envisioning and developing multiple…
Q: Charles Lackey operates a bakery in Victoria, BC. Because of its excellent product and excellent…
A: Output = 1500 Pay rate = $8 Number of hour = 160 Utility cost = 700 Labor hour = $8 Cost of…
Q: Learn the differences between functional, matrix, and project structures. Specify the effects of…
A: The organization of a company's workforce, resources, and work procedures is called its…
Q: Pinpoint the influences on commercial activity and the potential difficulties facing American…
A: The influences on commercial activity in the United States include factors such as macroeconomic…
Q: Explain how SAP ERP distinguishes between a person, a job, and a task.
A: SAP ERP (Enterprise Resource Planning) is a software system that is widely used by organizations for…
Q: Lack of Intellectual Property (IP) protection hurts International Firms in form of lost sales, less…
A: Intellectual property rights (IPR) is a significant aspect to businesses and specially for those who…
Q: Station 1 6 min/unit Machine A 15 min/unit 6 minutes 20 minutes 91 minutes 226 minutes Station 2…
A: Ans) Cycle Time is defined as the time taken by one unit from Start to End position. Station 1 time…
Q: Explain how the Spiral Model and the V Model work in managing the completion of projects.
A: From planning to testing and deployment, software development models offer a systematic method of…
Q: When you are connected to a representative, it will be, with equal probability, somebody from the…
A: The above-given question is to calculate the expected waiting time. Expected Wait Time (EWT) is the…
Q: How can Total Quality Management be adapted to fit the needs of different industries or…
A: Concept Introduction :- Total Quality Management is described as a constant endeavour by a specific…
Q: Explain the categories of justice and fairness from a deontological perspective and consider ways in…
A: From a deontological perspective, justice and fairness are categories that are grounded in moral…
Q: A store generates Monday through Thursday sales of $150, $125, $75, and $180. What sales on Friday…
A: Here, we could see the sales data for each day from Monday through Thursday, the weekday average…
Q: You Make the Call 6-49. What is the primary decision facing Starbucks? 6-50. What factors are…
A: 6-49. The primary decision facing Starbucks is how to increase sales in the afternoon to address…
Q: why might the problem of rapid urbanization be a more significant population issues then curtailing…
A: Urbanization is the country's growing proportion of city dwellers to the country's overall…
Q: Research about Angkas. A public transportation provider in Metro Manila. Explain what Angkas app is…
A: Angkas is a popular ride-hailing app in Metro Manila, Philippines that offers motorcycle…
Q: Which one would be t best example of a final service? 2: a consumer visits a doctor to get a…
A: Finished product is a product that has gone through all the production stages and packed in the…
Q: Go to the Jersey Mike's website Franchise Investment - Sub Sandwich Opportunity - Jersey Mike's Subs…
A: 1. Costs associated with opening a Jersey Mike's franchise location: Opening a Jersey Mike's…
Q: Explanation of the Spiral Model and the V Model for Project Management and How They Work.
A: Two well-liked project management approaches that are frequently applied in the software development…
Q: (a) A fruit grower has 150 acres of land available to raise two crops, A and B. It takes one day to…
A: To find: The number of acres of each fruit should be planted to maximize profit. Given: The amount…
Q: Use Prim's algorithm to find the minimum weighted spanning tree for the graph in figure K. Fill in…
A: Minimum spanning tree: Graph/route containing all the vertices (nodes) with minimum number of edges…
Q: What are some of the challenges that a corporation would have to overcome in order to accomplish the…
A: Corporations may encounter complex and challenging task when combining a defined brand strategy…
Q: Lazer Technologies Inc. (LTI) has produced a total of 20 high-power laser systems that could be used…
A: Formulae used: The learning percentage can be estimated by calculating the average of the ratio of…
Q: mig for a Project One in une City is network plan for the design phase of the project. Sophie Kim,…
A: The critical path method refers to a method that is used to determine the activities that need to be…
Q: What are the 6 Strategic HR Issues in Global Assignments?
A: There are following six Strategic HR Issues in Global Assignments
Q: Buckley Enterprise sells a product that cost $450 per unit and has a monthly demand of 5,000 units.…
A: Given the data, Monthly demand is 5000 Hence, the annual demand is 5000×12 Hence, the annual…
Q: On page 32, Alex and his team learn some things about robot efficiencies. Rogo notes, "To give the…
A: Given data: Capacity per hour=25 parts Cost per hour=$20
Q: Why are pipelines unknown to many individuals? Do you think the pipelines should advertise to change…
A: there could be several reasons why pipelines are not known to many individuals: Lack of awarness = A…
Q: Explain how the Spiral Model and the V Model work in managing the completion of projects.
A: Introduction- The spiral model can be defined as a model for risk analysis which implies the overall…
Notes: please have answer as decimal, not fraction. Also - round final answer to two decimal places.
Step by step
Solved in 2 steps
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) Q 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is minutes (enter your response as a whole number).Station 1 Machine A 20 min/unit Station 1 Machine B 20 min/unit Station 2 12 min/unit Station 3 8 min/unit A three station work cell is illustrated in the image above. A unit needs to be processed at either Machine A or Machine B for Station 1 (parallel lines, both lines doing the exact same thing). The unit is then processed at Stations 2 and 3 before leaving the work cell. The process time of each machine/station is indicated in the flowchart. What is the process time of this system measured in minutes/unit?A production line at V. J. Sugumaran’s machine shop has three stations. The first station can process a unit in 10 min-utes. The second station has two identical machines, each of which can process a unit in 12 minutes. (Each unit only needs to be pro-cessed on one of the two machines.) The third station can process a unit in 8 minutes. Which station is the bottleneck station?
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is minutes per unit (enter your response as a whole number). Q MThe Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is minutes (enter your response as a whole number). QA production line at V. J. Sugumaran's machine shophas three stations. The first station can process a unit in I 0 minutes.The second station has two identical machines, each of whichcan process a unit in 12 minutes. (Each unit only needs to be processedon one of the two machines.) The third station can processa unit in 8 minutes. Which station is the bottleneck station?
- The Pullman Mfg., Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 12 min/unit Station 1 Machine A Station 1 Machine B 12 min/unit Station 2 12 min/unit Station 3 2 min/unit The manager, Ms. Hartley, has asked you to evaluate the system if she adds a parallel machine at station 2. a) The throughput time of the new work cell is 26 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 6 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 2 is whole number). units (enter your response as aDreamInflate is a balloon manufacturing company. Balloon manufacturing consists of seven work stations, each performing a single step as indicated in the table below. There are five workers manned for the seven work stations as shown. Assume the workers are paid $15 per Worker Task Sequence Processing Time (secs/balloon) Task Dye production Electrocharging Dipping (Cold and Hot) Mortar Dipping Balloon inflation and delaltexing Vulcanization Inspection/Testing 1 30 w1 20 3 35 W2 25 W3 30 W4 6. 45 W5 7 40 hour. Each balloon pack is sold for $6 and has a variable cost of $1. The company has fixed costs of $200 per hour. There is more demand than the overall production system can provide. Based on the information provided, answer the following questions: • What is the cost of direct labor for balloons? • How much profit does DreamInflate make every hour? (note that the cost of direct labor is also a variable cost). What would the profit of DreamInflate be if the variable costs were 10…The Pullman Mig, Inc. three-station work cell illustrated in the figure below has two machines at station 1 in parallel. (The product needs to go through only one of the two machines before proceeding to station 2.) 20 minunit Station 1 Machine A Station 1 Machine B 20 min/unit Station 2 6 min/unit Station 3 12 minunit The manager, Seimone Hartley, has asked you to evaluate the system if she adds a parallel machine at station 3. a) The throughput time of the new work cell is 38 minutes (enter your response as a whole number). b) The bottleneck time of the new work cell is 10 minutes per unit (enter your response as a whole number). c) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell with the second machine at workstation 3 is 360 units (enter your response as a whole number). d) If the firm operates 10 hours per day, 6 days per week, the weekly capacity of the work cell without the second machine at workstation 3 is units (enter your response…
- A work cell at Chris Ellis Commercial Laundryhas a workstation with two machines, and each unit producedat the station needs to be processed by both of the machines.(The same unit cannot be worked on by both machines simultaneously.) Each machine has a production capacity of 4units per hour. What is the throughput time of the work cell?A manufacturing company has a small production line dedicated to the production of a particular product. The line has four stations in serial. Inputs arrive at station 1 and the output from station 1 becomes the input to station 2. The output from station 2 is the input to station 3 and so on. The output from station 4 is the i nished product. Station 1 can process 2,700 units per month, station 2 can process 2,500/month, station 3 can process 2,300/month, and station 4 can process 2,100/month. What station sets the maximum possible output from this system? What is that maximum output number?In the welding operations of a bicycle manufacturer, a bike frame has a flow time of about 14.35 hours. The time in the welding operation is spent as follows: 3 hours waiting in front of the cutting machine for the batch to start, 2 hours waiting for the setup of the machine, 1 hour waiting for the other pieces of the batch to go through cutting, 2 minute at the cutting machine, and 3 hours waiting for the transfer to the welding machine. Then, at the welding machine, the unit spends 1 hour waiting in front of the welding machine for the batch to start, 2 hour waiting for the setup of the welding machine, 0.35 hour waiting for the other pieces of the batch to go through welding, 0.25 minute at the welding machine, and 2 hour waiting for the transfer to the next department. (Round your percentage answer to 4 decimal places.) Determine the exact flow time. What is the value-added percentage of the flow time? percent