Problem 7-71 (Algo) Incomplete Data: Job Costing (LO 7-2, 3, 4) Plainview Paving Contractors (PPC) is a rapidly growing, recently established company that has not been profitable despite increases in sales. It has hired you as a consultant to find ways to improve profitability. You belleve that the problem results from poor cost control and inaccurate cost estimation on jobs. The company has essentially no accounting system from which to collect data. You are able, however, to piece together the following information for April: Production 1. Completed Job 33. 2. Started and completed Job 41 3. Started Job 42. Inventory Values Work-in-process inventory (excluding applied overhead): March 31: Job 33 Direct materials $8,100 Labor (1,000 hours $36) 36,000 April 30: Job 42 Direct materials Labor (1,078 hours $36) $ 7,300 38,520 - Job 33 was exactly 60 percent complete as to labor on March 31. Job 42 was exactly 40 percent complete as to labor on April 30. All direct materials necessary to do the entire job were charged to each job as soon as it was started. There were no direct materials inventories or finished goods Inventories at either March 31 or April 30, Actual overhead was $125,800. Cost of goods sold (before adjustment for over- or underapplied overhead): Job 33 Materials Labor Overhead 5 8,100 7 Total Job 41 $122,100 Materials Labor Overhead Total Overhead was applied to jobs using a predetermined rate per labor dollar that has been used since the company began operations. All direct materials were purchased for cash and charged directly to Work-in-Process Inventory when purchased. Direct materials purchased in April amounted to $18,360. Direct labor costs charged to jobs in April were $130,200. All labor costs were the same per hour for all laborers for April. Required: Calculate the following: a. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over- or underapplied overhead for each job sold. b. The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. c. Over- or underapplied overhead for April
Problem 7-71 (Algo) Incomplete Data: Job Costing (LO 7-2, 3, 4) Plainview Paving Contractors (PPC) is a rapidly growing, recently established company that has not been profitable despite increases in sales. It has hired you as a consultant to find ways to improve profitability. You belleve that the problem results from poor cost control and inaccurate cost estimation on jobs. The company has essentially no accounting system from which to collect data. You are able, however, to piece together the following information for April: Production 1. Completed Job 33. 2. Started and completed Job 41 3. Started Job 42. Inventory Values Work-in-process inventory (excluding applied overhead): March 31: Job 33 Direct materials $8,100 Labor (1,000 hours $36) 36,000 April 30: Job 42 Direct materials Labor (1,078 hours $36) $ 7,300 38,520 - Job 33 was exactly 60 percent complete as to labor on March 31. Job 42 was exactly 40 percent complete as to labor on April 30. All direct materials necessary to do the entire job were charged to each job as soon as it was started. There were no direct materials inventories or finished goods Inventories at either March 31 or April 30, Actual overhead was $125,800. Cost of goods sold (before adjustment for over- or underapplied overhead): Job 33 Materials Labor Overhead 5 8,100 7 Total Job 41 $122,100 Materials Labor Overhead Total Overhead was applied to jobs using a predetermined rate per labor dollar that has been used since the company began operations. All direct materials were purchased for cash and charged directly to Work-in-Process Inventory when purchased. Direct materials purchased in April amounted to $18,360. Direct labor costs charged to jobs in April were $130,200. All labor costs were the same per hour for all laborers for April. Required: Calculate the following: a. The cost elements (materials, labor, and overhead) of cost of goods sold before adjustment for over- or underapplied overhead for each job sold. b. The value of each cost element (materials, labor, and overhead) for each job in work-in-process inventory at April 30. c. Over- or underapplied overhead for April
Managerial Accounting
15th Edition
ISBN:9781337912020
Author:Carl Warren, Ph.d. Cma William B. Tayler
Publisher:Carl Warren, Ph.d. Cma William B. Tayler
Chapter13: Lean Manufacturing And Activity Analysis
Section: Chapter Questions
Problem 11E
Related questions
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by step
Solved in 2 steps
Recommended textbooks for you
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College
Managerial Accounting
Accounting
ISBN:
9781337912020
Author:
Carl Warren, Ph.d. Cma William B. Tayler
Publisher:
South-Western College Pub
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning
Principles of Accounting Volume 2
Accounting
ISBN:
9781947172609
Author:
OpenStax
Publisher:
OpenStax College