Question
Which of the following activities has the highest crash cost per week?
G
F
В
If you wanted to shorten the overall duration of the project, which activity should you crash first?
C
A
E
What is the total cost of crashing the project from its current duration down to 11 weeks?
Number
What is the total cost of crashing the project from its original duration to 9 weeks?
Number
expand button
Transcribed Image Text:Which of the following activities has the highest crash cost per week? G F В If you wanted to shorten the overall duration of the project, which activity should you crash first? C A E What is the total cost of crashing the project from its current duration down to 11 weeks? Number What is the total cost of crashing the project from its original duration to 9 weeks? Number
PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After
gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities:
Activity
Normal Time (weeks)
Crashed Time (weeks)
Normal Cost
Crashed Cost
Predecessor(s)
А
3
$1,000
$3,300
В
1
$2,160
$2,460
3
2
$1,300
$3,000
D
7
3
$2,000
$2,500
A
E
3
$1,650
$2,100
B
F
4
3
$4,100
$5,260
G
4
2
$1,650
$2,100
D, E
What is the overall duration of the project?
Number
Which of the following activities has the lowest crash cost per week?
O A
O E
expand button
Transcribed Image Text:PM.66 Real estate developer Russell Call was working with a few contractors to make a number of improvements to one of his rental properties. After gathering information from these contractors he determined the following durations, predecessors, and costs of all the required activities: Activity Normal Time (weeks) Crashed Time (weeks) Normal Cost Crashed Cost Predecessor(s) А 3 $1,000 $3,300 В 1 $2,160 $2,460 3 2 $1,300 $3,000 D 7 3 $2,000 $2,500 A E 3 $1,650 $2,100 B F 4 3 $4,100 $5,260 G 4 2 $1,650 $2,100 D, E What is the overall duration of the project? Number Which of the following activities has the lowest crash cost per week? O A O E
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.