P, Q, R, and S are four work centres in a series that belong to a manufacturing company. The figure below shows each center's individual capacity in units per day. Input P Q R (260) (300) (350) (A) Determine the bottle neck centre. (B) Determine the system capacity. (C) Determine the system efficiency. S (320) Actual Output (250)

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter4: Linear Programming Models
Section4.8: Data Envelopment Analysis (dea)
Problem 42P
icon
Related questions
Question
100%
P, Q, R, and S are four work centres in a series that
belong to a manufacturing company. The figure below
shows each center's individual capacity in units per day.
Input
Q
(300)
P
(280)
(350)
(A) Determine the bottle neck centre.
(B) Determine the system capacity.
(C) Determine the system efficiency.
RS
(320)
Actual
Output
(250)
Transcribed Image Text:P, Q, R, and S are four work centres in a series that belong to a manufacturing company. The figure below shows each center's individual capacity in units per day. Input Q (300) P (280) (350) (A) Determine the bottle neck centre. (B) Determine the system capacity. (C) Determine the system efficiency. RS (320) Actual Output (250)
Expert Solution
steps

Step by step

Solved in 2 steps

Blurred answer
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,