Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity A B с D E F G H I J K L Predecessor A, B с E F E D D, G, I I H Duration in Weeks 5 3 8 3 4 10 8 18 20 7 5 10

Practical Management Science
6th Edition
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:WINSTON, Wayne L.
Chapter2: Introduction To Spreadsheet Modeling
Section: Chapter Questions
Problem 20P: Julie James is opening a lemonade stand. She believes the fixed cost per week of running the stand...
icon
Related questions
Question

can someone help me with this one

Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new
football stadium. He developed the activities, durations, and predecessor relationships in the
following table for delivering company valuations.
Activity
A
B
с
D
E
F
G
H
I
J
K
L
Predecessor
A, B
C
E
F
E
D
D, G, I
|
H
Duration in Weeks
5
3
8
3
4
10
8
18
20
7
5
10
Transcribed Image Text:Nikos Anastopoulos of EMPROSS Strategic IT Consultants, leads the development of a new football stadium. He developed the activities, durations, and predecessor relationships in the following table for delivering company valuations. Activity A B с D E F G H I J K L Predecessor A, B C E F E D D, G, I | H Duration in Weeks 5 3 8 3 4 10 8 18 20 7 5 10
6A. Draw the Network Diagram, and identify and discuss the project duration and the
critical path using the following activity notation
ES
SL
LS
ID
EF
ANSWER:
SL
Time LF
First: Draw the precedence diagram.
You can draw the diagram using any software tool and paste it on this area OR you can draw the diagram by
hand on a clean white paper and take a picture to paste it in this area.
Second: Using the notation given identify the duration of the project. THIS PART MUST BE TYPED
If typing is difficult then it can be drawn by hand using the instructions given in the First step above.
Third: identify the critical part and explain the critical path.
Fourth: Explain your answer. This can be done by describing the process and the observations done once the
answer has been found.
Transcribed Image Text:6A. Draw the Network Diagram, and identify and discuss the project duration and the critical path using the following activity notation ES SL LS ID EF ANSWER: SL Time LF First: Draw the precedence diagram. You can draw the diagram using any software tool and paste it on this area OR you can draw the diagram by hand on a clean white paper and take a picture to paste it in this area. Second: Using the notation given identify the duration of the project. THIS PART MUST BE TYPED If typing is difficult then it can be drawn by hand using the instructions given in the First step above. Third: identify the critical part and explain the critical path. Fourth: Explain your answer. This can be done by describing the process and the observations done once the answer has been found.
Expert Solution
steps

Step by step

Solved in 4 steps with 6 images

Blurred answer
Follow-up Questions
Read through expert solutions to related follow-up questions below.
Follow-up Question

one thing i dont understand is when i asked the first question the precedence graph looks very different to the one for the third time i asked question satrting with 6C.

in the picture it shows the difference between the two the answer is both the same 41 weeks.

please chack the the  first time i asked the question and then the third time i asked the graphs look different

Start
#
0
H 22
18 22
2) The critical path is A-C-D-I-J.
The duration of the critical path is 43 weeks.
16 20 36
36
36 5 41
36
43
36 7 43
22 L 32
0
0
22 10 32
End
Transcribed Image Text:Start # 0 H 22 18 22 2) The critical path is A-C-D-I-J. The duration of the critical path is 43 weeks. 16 20 36 36 36 5 41 36 43 36 7 43 22 L 32 0 0 22 10 32 End
1
2
3
4
5
6
7
st
00
8
9
10
11
12
13
14
15
16
17
18
85 00
19
20
21
A B
с
Forward Pass
ES
LS
0
0
0
2
0
DUR EF
Activity
SLACK LF
5
A
0
D
3
B
2
Backward Pass
5
5
3
4
E
11 11 15
5
4
E
F
G
H
5 8 13
с
5 0 13
4 10 14
F
18 14 28
4 18 22
H
15 11 33
J
13
K
3₂
L M
16
D
13 0 16
14 8 22
G
28 14
36
N
O
16 20
I
16 0
a
36
36
Q
R
38
36 5
K
2 43
36
36
22
S
33
7
J
0
F-16
T
L
11
41
10 32
43
43
43
Transcribed Image Text:1 2 3 4 5 6 7 st 00 8 9 10 11 12 13 14 15 16 17 18 85 00 19 20 21 A B с Forward Pass ES LS 0 0 0 2 0 DUR EF Activity SLACK LF 5 A 0 D 3 B 2 Backward Pass 5 5 3 4 E 11 11 15 5 4 E F G H 5 8 13 с 5 0 13 4 10 14 F 18 14 28 4 18 22 H 15 11 33 J 13 K 3₂ L M 16 D 13 0 16 14 8 22 G 28 14 36 N O 16 20 I 16 0 a 36 36 Q R 38 36 5 K 2 43 36 36 22 S 33 7 J 0 F-16 T L 11 41 10 32 43 43 43
Solution
Bartleby Expert
SEE SOLUTION
Follow-up Question

6C.  Change the time of at least two activities that can reduce the overall project duration, draw the new critical path and the new Gantt chart.

 

First:  Repeat 6B by changing the task time of any 2 or 3 tasks that will result in a smaller project duration.  

Please note that changing only terminal tasks (ending tasks) will not give you any credit as it is easy to reduce the duration of the project by changing the duration of the last task.   

To make the reduced task time more visible you can colour them RED and write about them.   

Second: identify the critical part and explain it.  Explain if the critical path has changed and why? or why not?

 

Third:  Explain your answer for the new (shorter) project duration.  This can be done by describing the process and the observations done once the answer has been found.  

Fourth: Draw the new project’s Gantt chart 

Fifth: Explain the Gantt chart by emphasizing the observations made.  State your conclusions.  

 

thank you 

Solution
Bartleby Expert
SEE SOLUTION
Follow-up Question

Draw the project’s Gantt chart

-First: The project’s Gantt chart needs to be done.   

-Second: Explain the Gantt chart by emphasizing the observations made.  State your conclusions.   

Solution
Bartleby Expert
SEE SOLUTION
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Practical Management Science
Practical Management Science
Operations Management
ISBN:
9781337406659
Author:
WINSTON, Wayne L.
Publisher:
Cengage,
Operations Management
Operations Management
Operations Management
ISBN:
9781259667473
Author:
William J Stevenson
Publisher:
McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi…
Operations and Supply Chain Management (Mcgraw-hi…
Operations Management
ISBN:
9781259666100
Author:
F. Robert Jacobs, Richard B Chase
Publisher:
McGraw-Hill Education
Business in Action
Business in Action
Operations Management
ISBN:
9780135198100
Author:
BOVEE
Publisher:
PEARSON CO
Purchasing and Supply Chain Management
Purchasing and Supply Chain Management
Operations Management
ISBN:
9781285869681
Author:
Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:
Cengage Learning
Production and Operations Analysis, Seventh Editi…
Production and Operations Analysis, Seventh Editi…
Operations Management
ISBN:
9781478623069
Author:
Steven Nahmias, Tava Lennon Olsen
Publisher:
Waveland Press, Inc.