Practical Management Science
Practical Management Science
6th Edition
ISBN: 9781337406659
Author: WINSTON, Wayne L.
Publisher: Cengage,
Bartleby Related Questions Icon

Related questions

bartleby

Concept explainers

Topic Video
Question
  1. Normal completion time and accelerated completion time
  2. Steps that can be taken to crash the project to the shortest time at the lowest cost.
    • Hint: Determine each step's cost and the duration of the project at that stage. 
**Project Time and Cost Analysis for Home Redesign**

Kelly Melford and her team are engaged in redesigning a client's home. The client has requested the project be completed sooner than initially planned. To accommodate this request, Kelly tasked her assistant with gathering relevant project data, which is presented in the table below. The information outlines the timelines and costs associated with each activity, expressed in weeks.

| Activity | Normal Time (weeks) | Crash Time (weeks) | Immediate Predecessors | Normal Cost | Crash Cost |
|----------|---------------------|--------------------|------------------------|-------------|------------|
| A        | 10                  | 9                  | --                     | $11,000     | $15,000    |
| B        | 15                  | 13                 | --                     | $20,000     | $25,000    |
| C        | 10                  | 6                  | A                      | $9,000      | $20,000    |
| D        | 20                  | 18                 | A                      | $25,000     | $30,000    |
| E        | 15                  | 10                 | C                      | $20,000     | $35,000    |
| F        | 17                  | 15                 | B                      | $20,000     | $30,000    |
| G        | 12                  | 10                 | B                      | $15,000     | $25,000    |
| H        | 9                   | 8                  | D, F                   | $12,000     | $18,000    |
| I        | 7                   | 6                  | G, H                   | $10,000     | $15,000    |

**Explanation:**

- **Activities**: Each activity is labeled from A to I.
- **Normal Time**: The standard duration required to complete each activity.
- **Crash Time**: The reduced time required to complete each activity at an additional cost.
- **Immediate Predecessors**: Activities that must be completed before the current activity can start.
- **Normal Cost**: The estimated cost for completing the activity in its normal time.
- **Crash Cost**: The cost incurred for completing the activity in the reduced crash time.

This table is utilized for project management decisions, helping Kelly’s team weigh the benefits of reducing project time against the increase
expand button
Transcribed Image Text:**Project Time and Cost Analysis for Home Redesign** Kelly Melford and her team are engaged in redesigning a client's home. The client has requested the project be completed sooner than initially planned. To accommodate this request, Kelly tasked her assistant with gathering relevant project data, which is presented in the table below. The information outlines the timelines and costs associated with each activity, expressed in weeks. | Activity | Normal Time (weeks) | Crash Time (weeks) | Immediate Predecessors | Normal Cost | Crash Cost | |----------|---------------------|--------------------|------------------------|-------------|------------| | A | 10 | 9 | -- | $11,000 | $15,000 | | B | 15 | 13 | -- | $20,000 | $25,000 | | C | 10 | 6 | A | $9,000 | $20,000 | | D | 20 | 18 | A | $25,000 | $30,000 | | E | 15 | 10 | C | $20,000 | $35,000 | | F | 17 | 15 | B | $20,000 | $30,000 | | G | 12 | 10 | B | $15,000 | $25,000 | | H | 9 | 8 | D, F | $12,000 | $18,000 | | I | 7 | 6 | G, H | $10,000 | $15,000 | **Explanation:** - **Activities**: Each activity is labeled from A to I. - **Normal Time**: The standard duration required to complete each activity. - **Crash Time**: The reduced time required to complete each activity at an additional cost. - **Immediate Predecessors**: Activities that must be completed before the current activity can start. - **Normal Cost**: The estimated cost for completing the activity in its normal time. - **Crash Cost**: The cost incurred for completing the activity in the reduced crash time. This table is utilized for project management decisions, helping Kelly’s team weigh the benefits of reducing project time against the increase
Expert Solution
Check Mark
Knowledge Booster
Background pattern image
Operations Management
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.
Similar questions
SEE MORE QUESTIONS
Recommended textbooks for you
Text book image
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Text book image
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Text book image
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Text book image
Business in Action
Operations Management
ISBN:9780135198100
Author:BOVEE
Publisher:PEARSON CO
Text book image
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Text book image
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.