Question
Expected length of a project is 37.16 days and the variance of its length is 6.14 days. What is the probability that the project is completed within 40 days?
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 1 images
Knowledge Booster
Similar questions
- Two activities on the same critical path are candidates for crashing on a CPM network. Activity details are in the table below. To cut one day from the project's duration, activity ________ should be crashed first, adding ________ to project cost.arrow_forwardsniparrow_forwardWhat is the latest day you could start activity B? Number What is the latest day you could finish activity D? Number What is the slack time for activity G? Number days What would be the overall duration of the project if activity E were increased by 5 days, from 2 to 7 days? Number daysarrow_forward
- A project consists of five activities listed below. The project network is shown for the activities. The critical path is B-C-E and the expected completion time is 8. Optimistic Most Probable Pessimistic Activity Time (hr) Time (hr) Time (hr) A Floor sanding 3 4 5 B Paint mixing 0.5 1 1.5 C Ceiling painting 1 5.5 7 D Wall painting 1 2 9 E Floor buffing 1 2 3 What is the probability that the project can be completed within 9 hr.?arrow_forwardActivity A can start as soon as the project starts, and set the earliest start time for activity an equal to 0. With an expected activity time of 5 weeks. Using this information what is the earliest finish time for activity A?arrow_forwardA project with Earned Value (EV) = $1000, Actual Cost (AC) = $800 and Planned Value (PV) = $800. What is the Schedule Variance (SV)?arrow_forward
- Answer all. What are the critical activities? What is the expected project duration? calculate the variance of the project What is the standard deviation (te) for the project? Suppose that management allotted 13-unit time for the project. What is the probability that we will meet the 13-unit time deadline? If management wants to have a 0.99 probability of meeting the time, what should be the scheduled project duration?arrow_forward1. A project was planned using PERT with three-time estimates. The expected completion time of the project was determined to be 40 weeks. The variance of the critical path is 9. (e) The project manager wishes to set the due date for the completion of the project so that there is a 90% chance of finishing on schedule. Thus, there would only be a 10% chance the project would take longer than this due date. What should this due date be?arrow_forward13.42 Activity A is worth $100, is complete, and actually cost $150 Activity B is worth $500, is 75% complete, and has actually cost $400 so far Activity C is worth $500, is 25% complete, and has actually cost $200 so far. What is the estimated cost to completion for the project?arrow_forward
- Dave Fletcher was able to determine the activity times for constructing his laser scanning machine. Fletcher would like to determine ES, EF, LS, LF, and slack for each activity. The total project completion time and the critical path should also be determined. Here are the activity times: Activity Time (weeks) Immediate Predecessor(s) Activity Time (weeks) Immediate Predecessor(s)A 6 - E 5 BB 8 - F 6 BC 2 A G 9 C, ED 3 A H 7 D , F Dave's earilest start (ES) and earliest finish (EF) are: Activity ES EF A 0 6 B 0 ? C D E F G Harrow_forwardA project is set to be completed in 12 months with an estimated budget cost of $520,000. 6 months have passed, and expenses were $240,000. The completion of work is set to be $270,000 What is the planned value PV of the project? What is the actual cost AC of the project? What is the earned value EV of the project? Find the SPI and CPI of the project. Is the project ahead or behind schedule? Is the project under or over budget? What is the estimated cost to complete the project?arrow_forwardRisk reduction and risk transfer are two techniques that can be used to manage risk in a project. Using suitable examples, explain both risk reduction and risk transfer.arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.