Concept explainers
Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000.
Total construction costs incurred in each year were as follows:
20X5: $2,700,000
20X6: $4,500,000
20X7: $1,800,000
Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project.
Company also billed the client and collected the following payments
Year Billings Payments Received
20X5: $2,300,000 $2,100,000
20X6: $4,900,000 $4,700,000
20X7: $3,750,000 $4,150,000
Required: Calculate Net income for the construction project for each of the three years:
a) Completed contract method?
20X5: $______________ 20X6: $__________________ 20X7____________________.
b) Percentage-of-completion method? (basis: estimated costs to complete)
20X5: $______________ 20X6: $__________________ 20X7____________________.
Trending nowThis is a popular solution!
Step by stepSolved in 3 steps with 3 images
- On February 1, 2015, Jaddua Johnston Contractors agreed to construct a building for Satish Thapa at a contract price of $5,800,000. Johnston estimated total construction cost would be $4,000,000 and the project would be finished in 2017. Information relating to the costs and billings for this contract is as follows: 2015 2016 2017 Totals Total costs incurred to-date $ 1,500,000 $ 2,640,000 $ 4,600,000 $ 8,740,000 Estimated costs to complete 2,500,000 1,760,000 4,260,000 Customer billings to-date |Collections to-date 2,200,000 11,800,000 2,000,000 4,000,000 3,500,000 5,600,000 5,500,000 11,000,000 Required: (1) prepare a schedule showing gross profit to be recognized each year under % completion method. (2)Compute the gross profit to be recognized in 2017 under the completed-contract method. (3) Prepare Journal entries for 2016 under % of completion method. #(1) Schedule of gross profit recognized under % of Completion method: 2015 2016 2017arrow_forwardSheridan Construction Co. uses the percentage-of-completion method. In 2024, Sheridan began work on a contract for $21300000; it was completed in 2025. The following cost data pertain to this contract: Cost incurred during the year Estimated costs to complete at the end of year Year Ended December 31 $8516000. $2990000. $3680000. $3684000. 2024 $7254000 4836000 2025 $5530000 The amount of gross profit to be recognized on the income statement for the year ended December 31, 2025 isarrow_forwardTullis Construction enters into a long-term fixed price contract to build an office tower for $10,600,000. In the first year of the contract Tullis incurs $3,000,000 of cost and the engineers determined that the remaining costs to complete the project are $5,000,000. Tullis billed $5,000,000 in year 1 and collected $3,100,000 by the end of the end of the year. How should Tullis report Construction in Progress and Billings on Construction in Progress at the end of year 1 on the balance sheet assuming the use of the completed - contract method? O A. asset of $2,000,000 O B. liability of $1,900,000 O C. asset of $1,900,000 O D. liability of $2,000,000arrow_forward
- G Company agreed to build a building for K Corporations. The contract price is $4,200,000. Data pertaining to expected and actual costs incurred for building is providing below: Year Costs 2017 $740,000 2018 $1,650,000 2019 $750,500 G Company completed the building in the year 2019. Calculate the amount of net income from 2017 to 2019. (Use the percentage-of-completion method and round all the percentages to zero decimal places) Net Income for 2017, 2018, and 2019 are $840,000, $2,120,000, and $1,040,000, respectively. Net Income for 2017, 2018, and 2019 are $268,000, $576,000, and $257,500, respectively. Net Income for 2017, 2018, and 2019 are $249,651, $556,655, and $253,194, respectively. Net Income for 2017, 2018, and 2019 are $830,400, $1,351,500, and $827.880, respectively.arrow_forwardDomesticarrow_forwardThe Market Company won a contract to build a shopping center at a price of $300 million. The following schedule details the estimated and actual costs of construction each year as well as the total estimated cost. What amount of revenue will be recognized in Yr. 1 using the percentage completion method? Yr 1 $40,000,000 Yr. 2 $60,000,000 Yr. 3 $70,000,000 Yr. 4 $30,000,000 Total $200,000,000 Select one: a. $60,000,000 b. $50,000,000 c. $0 d. $40,000,000 e. $300,000,000arrow_forward
- Star Construction Corporation has a contract to construct a building for $10,950,000. The building is controlled by the customer throughout the term of the contract. Total costs to complete the building were originally estimated at $8,850,000. Construction commenced on 4 February 20×5. Actual costs were in line with estimated costs for 20×5 and 20×6. In 20×7, actual costs exceeded estimated costs by $150,000. Total construction costs incurred in each year were as follows: 20X5: $2,700,00020X6: $4,500,00020X7: $1,800,000 Progress billings based on the amount of work completed were collected each year. Star Construction uses the percentage-of-completion method. The percentage-of-completion is based on costs incurred compared with estimated total costs of the project. Company also billed the client and collected the following payments Year Billings Payments Received 20X5: $2,300,000 $2,100,000 20X6: $4,900,000 $4,700,000 20X7: $3,750,000 $4,150,000…arrow_forwardPlease help mearrow_forwardA construction company entered into a fixed-price contract to build a soccer stadium for $15,000,000. Construction costs incurred during the first year were $3,675,000, and estimated costs to complete at the end of the year were $6,825,000. The company recognizes revenue over time according to percentage of completion. Fixed-price contract amount: $15,000,000 Construction costs incurred in first year: $3,675,000 Estimated costs to complete at end of first year: $6,825,000 How much revenue and gross profit or loss will appear in the company’s income statement in the first year of the contract? Percentage of completion at end of first year Revenue Gross profit (loss) Nothing in this area will be graded, but it will be submitted with your assignment.arrow_forward
- Oriole Construction Company began operations on January 1, 2025. During the year, Oriole Construction entered into a contract with Winds Corp. to construct a manufacturing facility. At that time, Oriole estimated that it would take 5 years to complete the facility at a total cost of $4.484,000. The total contract price for construction of the facility is $5,972,000. During the year, Oriole incurred $1,082,400 in construction costs related to the construction project. The estimated cost to complete the contract is $4,329,600. Winds Corp. was billed and paid 25% of the contract price. (a) Prepare schedules to compute the amount of gross profit to be recognized for the year ended December 31, 2025, and the amount to be shown as "costs and recognized profit in excess of billings" or "billings in excess of costs and recognized profit" at December 31, 2025, under each of the following methods. (Enter negative amounts using either a negative sign preceding the number eg.-45 or parentheses…arrow_forwardA construction company entered into a fixed-price contract to build an office building for $42 million. Construction costs incurred during the first year were $12 million, and estimated costs to complete at the end of the year were $28 million. The company recognizes revenue over time according to percentage of completion. How much revenue and gross profit or loss will appear in the company's income statement in the first year of the contract? Note: Enter your answers in whole dollars and not in millions (i.e., $4 million should be entered as $4,000,000). Revenuearrow_forwardJohnson Inc. enters into a $300,000 contract for the purchase of customized equipment with Builder Inc. The construction of the equipment is expected to take two years. Johnson Inc. owns the work in process during the two-year period but will not take possession of the equipment until completed. The contractor will bill Johnson monthly for performance completed to date. After year-one, Builder Inc. incurred costs of $120,000 and expects remaining costs to be $108,000. Builder Inc. has billed Johnson $150,000 in total for the year. Johnson has paid $135,000 to Builder Inc. Determine the amount of revenue and expenses that Builder Inc. should recognize in the first year of the contract. a. Revenue Expenses $157,895 $120,000 b. Revenue Expenses $150,000 $114,000 c. Revenue Expenses $78,947 $120,000 d. Revenue Expenses $0 $0 e. Revenue Expenses $150,000 $120,000arrow_forward
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education