In 2021, Crane Corporation began construction work under a three-year contract. The contract price is $ 480000. Crane uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2021, follow: Balance Sheet Accounts receivable—construction contract billings $ 192000 Construction in progress $ 600000 Less contract billings 480000 Costs and recognized profit in excess of billings 120000 Income Statement Income (before tax) on the contract recognized in 2021 $ 120000 How much cash was collected in 2021 on this contract? $ 480000 $ 48000 $ 288000 $ 192000
In 2021, Crane Corporation began construction work under a three-year contract. The contract price is $ 480000. Crane uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2021, follow: Balance Sheet Accounts receivable—construction contract billings $ 192000 Construction in progress $ 600000 Less contract billings 480000 Costs and recognized profit in excess of billings 120000 Income Statement Income (before tax) on the contract recognized in 2021 $ 120000 How much cash was collected in 2021 on this contract? $ 480000 $ 48000 $ 288000 $ 192000
Intermediate Accounting: Reporting And Analysis
3rd Edition
ISBN:9781337788281
Author:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:James M. Wahlen, Jefferson P. Jones, Donald Pagach
Chapter17: Advanced Issues In Revenue Recognition
Section: Chapter Questions
Problem 6P
Related questions
Question
100%
In 2021, Crane Corporation began construction work under a three-year contract. The contract price is $ 480000. Crane uses the percentage-of-completion method for financial accounting purposes. The income to be recognized each year is based on the proportion of costs incurred to total estimated costs for completing the contract. The financial statement presentations relating to this contract at December 31, 2021, follow:
Balance Sheet | ||
$ 192000 | ||
Construction in progress | $ 600000 | |
Less contract billings | 480000 | |
Costs and recognized profit in excess of billings | 120000 |
Income Statement | ||
Income (before tax) on the contract recognized in 2021 | $ 120000 |
How much cash was collected in 2021 on this contract?
$ 480000
$ 48000
$ 288000
$ 192000
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution!
Trending now
This is a popular solution!
Step by step
Solved in 2 steps
Recommended textbooks for you
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Intermediate Accounting: Reporting And Analysis
Accounting
ISBN:
9781337788281
Author:
James M. Wahlen, Jefferson P. Jones, Donald Pagach
Publisher:
Cengage Learning
Individual Income Taxes
Accounting
ISBN:
9780357109731
Author:
Hoffman
Publisher:
CENGAGE LEARNING - CONSIGNMENT