FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Concept explainers
Question
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 2 steps
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- The Leto Construction Company began work on a $12.000 contract on 1/1/20. Planned completion was in 2022. The Percentage-of Completion method a used Given the following December 31 2021 $4.200 6,300 5,100 6,000 2020 2022 $11,650 $2,500 Costs incumed to dute Esbinated costs to compiete Bitingu to date Collections to date 7,600 4.000 3,800 12,000 11,900 The 12/31/21 belance of Construction in Progress is Select one O. $4300 Ob S5040 O $5.000 Od $4200 O $4800arrow_forwardA price company from time to time embarks on a research program when a special project seems to offer possibilities in 2019 the company expands $325,000 on a research project, but by the end of 2019, it is possible to determine whether any benefits will be driven from it. What account should be charged from 325,000 and how should be shown in the financial statement? Additional engineering and consulting costs incurred in 2021 are required to advance the design of the project in the manufacturing stage. Total $60,000. These costs enhance the design of the product considerably. Discuss the proper account treatment for this cost.arrow_forwardConstruction costs: 2020: $100,000 2021: $186,000 2022: $464,000 Estimated Costs to Complete: 2020: $400,000 2021: $464,000 2022: $0 Total Contract Price: $700,00O Assuming this company uses the percentage of completion method, how much Gross Profit/Loss will the company recognize in 2021? O $464,000 O $(90,000) O $(22,000) O $50,000arrow_forward
- During 2020, Tamarisk Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $405,900 $766,500 $1,076,000 Estimated costs to complete 584,100 328,500 -0- Billings to date 300,000 893,000 1,610,000 Collections to date 267,000 809,000 1,435,000 (a) Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $ Gross profit recognized in 2021 Gross profit recognized in 2022 2$ eTextbook and Media List of Accounts Save for Later Attempts: unlimited Submit Answer %24 %24arrow_forwardOn April 12, 2021, Jacob’s Construction contracted to build a 400 Unit Apartment Complex at a contract price of $85 million. The schedule of expected (which equals actual) cash collections and contract direct costs (excluding SG&A) is as follows: Year Cash Collections Cost Incurred 2021 $60 million $ 45 million 2022 20 million 27 million Total $80 million $72 million Calculate the Gross Profit for the Total Contract Calculate the Gross Margin for the Total Contract Calculate the revenue for 2021 Calculate the revenue for 2022 Calculate the gross profit for 2021 Calculate the gross profit for 2022 Calculate the gross margin for 2021 Calculate the gross margin for 2022arrow_forwardB Company is recognizing income from long-term construction contracts. In 2020, B entered into a fixed contract to construct a fly-over connecting Luzon and Mindanao for P65,000,000. Estimated costs and contract costs incurred up to 2023 were as follows: Year Cost incurred Estimated cost at completion Progress billings 15,000,000 6,000,000 25,000,000 19,000,000 2020 15,000,000 60,000,000 62,000,000 66,000,000 63,000,000 2021 6,700,000 2022 24,500,000 16,800,000 2023 Using percentage of completion method, compute for the following: 1. Realized gross profit in 2021 2. CIP, net of progress billings as of 2022 3. Revenue earned in 2023arrow_forward
- Rogers Ltd. has entered into a contract beginning in February 2020 to build two warehouses for ocean Ltd. The contract is a non-cancellable fixed price contract for $9.4 million. The following data pertain to the construction period. 2020 2021 2022 Costs for the year $3,285,000 4,015,000 1,800,000 Estimated costs to complete 4,015,000 1,825,000 -0- Progress billings for the year (non-refundable) 2,960,000 3,440,000 3,000,000 Cash collected for the year 2,605,000 3,490,000 3,305,000 a) Using the percentage-of-completion method, calculate the percent complete for each year of the contract. b) Calculate the amount of the gross profit to be recognized each year of the contract. c) Prepare the journal entries for 2020 and 2021. (Use Materials, Cash, Payables for costs incurred to date.) d) What is the balance in the Contract Asset/Liability account at December 31, 2020 and 2021? Show how the construction contract would be reported on the SFP…arrow_forwardColorado Inc. constructed a factory during 2020 and 2021 under contract with Pacific Machinery Co. Relevant data are summarized below: Contract price Cost Gross profit Contract billings $3,000,000 2020 1,200,000 2021 600,000 2020 800,000 2021 400,000 2020 1,500,000 2021 1,500,000 Colorado Inc. recognizes revenue over time with respect to this contract. In its December 31, 2020, balance sheet, Colorado would report: ● The contract asset, cost and profit in excess of billings, $500,000. The contract liability, billings in excess of cost, of $300,000. The contract asset, contract amount in excess of billings, of $1,500,000. The contract asset, deferred profit, of $400,000.arrow_forwardDuring 2020, Pearl Company started a construction job with a contract price of $1,610,000. The job was completed in 2022. The following information is available. 2020 2021 2022 Costs incurred to date $393,900 $760,380 $1,059,000 Estimated costs to complete 616,100 341,620 –0– Billings to date 299,000 905,000 1,610,000 Collections to date 268,000 818,000 1,421,000 Compute the amount of gross profit to be recognized each year, assuming the percentage-of-completion method is used. Gross profit recognized in 2020 $enter a dollar amount Gross profit recognized in 2021 $enter a dollar amount Gross profit recognized in 2022 $enter a dollar amount eTextbook and Media List of Accounts Prepare all necessary journal entries for 2021. (Credit account titles are automatically indented when amount is entered. Do not…arrow_forward
- Crane Construction Co. uses the percentage-of-completion method. In 2021, Crane began work on a contract for $24475000; it was completed in 2022. The following cost data pertain to this contract: Year Ended December 31 2021 2022 Cost incurred during the year $8350000 $6150000 Estimated costs to complete at the end of year 5739000 If the completed-contract method of accounting was used, the amount of gross profit to be recognized for years 2021 and 2022 would be 2021 2022 $9975000. $(411000). $0. $10386000. $10386000. $0. $0. $9975000. O Oarrow_forwardA company uses the percentage-of-completion method of accounting. In 2020, the company began work a project, which had a contract price of $22,300. Other details follow: 2020 2021 Costs incurred to date $6,000 $18,000 Estimated costs to complete, as of December 31 14,000 -0- Billings to date 11,460 16,830 Collections to date 9,470 14,650 In the journal entry to record progress billings for 2021, how much should Billings on Construction in Process be debited/credited? (Just enter the amount. DO NOT put a plus or minus sign in front of the amount.)arrow_forwardA company uses the percentage-of-completion method of accounting. In 2020, the company began work a project, which had a contract price of $23,700. Other details follow: 2020 2021 Costs incurred to date $6,000 $18,000 Estimated costs to complete, as of December 31 14,000 -0- Billings to date 11,350 17,460 Collections to date 9,390 16,260 At the end of 2020, what is the inventory/current liability related to the construction of this project? (Very important: if the company reports a current liability, then put a minus sign in front of the amount. If the company reports an inventory, then no plus or minus sign is needed.) (Do not round your answers in any part of the computation.)arrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education