![FINANCIAL ACCOUNTING](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
FINANCIAL ACCOUNTING
10th Edition
ISBN: 9781259964947
Author: Libby
Publisher: MCG
expand_more
expand_more
format_list_bulleted
Question
![In 2020, Crane Contractors began construction on an office building. The building was expected to cost $46,310,000 in total, and
was expected to be completed in early 2022. The customer was to pay Crane $48,760,000 for the building. Crane was able to use
percentage-of-completion accounting for the project, and at the end of 2020 had accumulated $11,577,500 in cost. Crane
estimated that the costs to complete the construction were in line with the original expected total costs.
During 2021, there was a lumber shortage, a strike by construction workers, and various other incidents that dramatically raised
costs in the construction industry. As a result, at the end of 2021, Crane estimated that the office building would cost $4,780,000
in total. To the end of 2021, Crane had spent $38,828,400 on constructing the office building.
Calculate the revenue to be recognized by Crane for the 2021 fiscal year.
Revenue to be recognized
$
$24,867,600
Prepare the journal entry to record revenue, construction expenses. (Credit account titles are automatically indented
when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account
titles and enter 0 for the amounts.)
Account Titles and Explanation
Debit
Credit](https://content.bartleby.com/qna-images/question/382f4aed-7fd6-46cb-ab45-6e234d2bc043/de5e296f-d399-48ee-849d-d6b54b8a0982/6abtoj4_thumbnail.png)
Transcribed Image Text:In 2020, Crane Contractors began construction on an office building. The building was expected to cost $46,310,000 in total, and
was expected to be completed in early 2022. The customer was to pay Crane $48,760,000 for the building. Crane was able to use
percentage-of-completion accounting for the project, and at the end of 2020 had accumulated $11,577,500 in cost. Crane
estimated that the costs to complete the construction were in line with the original expected total costs.
During 2021, there was a lumber shortage, a strike by construction workers, and various other incidents that dramatically raised
costs in the construction industry. As a result, at the end of 2021, Crane estimated that the office building would cost $4,780,000
in total. To the end of 2021, Crane had spent $38,828,400 on constructing the office building.
Calculate the revenue to be recognized by Crane for the 2021 fiscal year.
Revenue to be recognized
$
$24,867,600
Prepare the journal entry to record revenue, construction expenses. (Credit account titles are automatically indented
when the amount is entered. Do not indent manually. If no entry is required, select "No Entry" for the account
titles and enter 0 for the amounts.)
Account Titles and Explanation
Debit
Credit
Expert Solution
![Check Mark](/static/check-mark.png)
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps
![Blurred answer](/static/blurred-answer.jpg)
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.Similar questions
- Blossom Construction is constructing an office building under contract for Cannon Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1450000 each quarter. The total contract price is $18492000 and Blossom estimates total costs of $17650000. Blossom estimates that the building will take 3 years to complete, and commences construction on January 2, 2018. At December 31, 2018, Blossom estimates that it is 30% complete with the construction, based on costs incurred. What is the total amount of Revenue from Long- Term Contracts recognized for 2018 and what is the balance in the Accounts Receivable account assuming Cannon Company has not yet made its last quarterly payment? Revenue $6164000 $5547600 $5295000 $5295000 O Option A Option B O Option C Accounts Receivable $6164000 $1450000 $1450000 $6164000arrow_forwardYellowStone Construction is constructing an office building under contract for LimeStone Company and uses the percentage-of-completion method. The contract calls for progress billings and payments of $1300000 each quarter. The total contract price is $15600000 and YellowStone estimates total costs of $17500000. YellowStone estimates that the building will take 3 years to complete, and commences construction on January 2, 2021. At December 31, 2022, YellowStone Construction estimates that it is 75% complete with the building; however, the estimate of total costs to be incurred has risen to $17750000 due to unanticipated price increases.YellowStone Construction completes the remaining 25% of the building construction on December 31, 2023, as scheduled. At that time the total costs of construction are $18500000. What is the total amount of Revenue from Long-Term Contracts and Construction Expenses that YellowStone will recognize for the year ended December 31, 2023? Revenue Expenses…arrow_forwardBeck Construction Company began work on a new building project on January 1, 2023. The project is to be completed by December 31, 2025, for a fixed price of $149 million. The following are the actual costs incurred and estimates of remaining costs to complete the project that were made by Beck's accounting staff: Years 2023 2024 2025 Actual costs incurred in each year $ 42 million $ 69 million, $ 47 million Required: What amount of gross profit (or loss) would Beck record on this project in each year, assuming that Beck recognizes revenue for this project upon completion of the project? Years 2023 2024 2025 Note: Enter "None" if there is no requirement of recognizing profit or loss. Loss amounts should be indicated with a minus sign. Enter your answers in millions (1.e., 10,000,000 should be entered as 10). Estimated remaining costs to complete the project (measured at December 31 of each year) $ 84 million $ 69 million $0 million Gross Profit (or Loss) recognized million million…arrow_forward
- Indiana Co. began a construction project in 2018 with a contract price of $160 million to be received when the project is completed in 2020. During 2018, Indiana incurred $36 million of costs and estimates an additional $82 million of costs to complete the project. Indiana recognizes revenue over time and for this project recognizes revenue over time according to the percentage of the project that has been completed. Suppose that, in 2019, Indiana incurred additional costs of $66 million and estimated an additional $54 million in costs to complete the project. Indiana (Do not round your percentage calculated): Multiple Choice Recognized $13.2 million gross profit on the project in 2019. Recognized $10.2 million loss on the project in 2019. Recognized $3.00 million loss on the project in 2019. Recognized $10.2 million gross profit on the project in 2019.arrow_forwardOn February 1, 2023, Sandhill Contractors agreed to construct a building at a contract price of $3,460,000. The total estimated construction costs would be $1,890,000 and the project would be finished in 2025. Information relating to the costs and billings for this contract is as follows: Total costs incurred to date Estimated costs to complete Customer billings to date Collections to date 2023 Gross profit/ (loss) 689,850 1,200,150 1,100,000 1,000,000 2023 2024 573050 $1,162,000 $ 2,365,000 913,000 1,890,000 1,750,000 2025 Calculate the gross profit / (loss) that should be recognized for 2023, 2024, and 2025 using the percentage completion method. (Enter negative amounts using either a negative sign preceding the number e.g. -45 or parentheses e.g. (45). Round percentage complete to 1 decimal place, e.g. 15.2% and final answers to O decimal places, e.g. 5,125.) 2024 -0- 3,460,000 2,950,000 -107450 $ LA 2025 40450arrow_forwardSwifty Construction Company has entered into a contract beginning January 1, 2020, to build a parking complex. It has been estimated that the complex will cost $598,000 and will take 3 years to construct. The complex will be billed to the purchasing company at $894,000. The following data pertain to the construction period. 2020 2021 2022 Costs to date $263,120 $412,620 $607,000 Estimated costs to complete 334,880 185,380 –0– Progress billings to date 272,000 545,000 894,000 Cash collected to date 242,000 495,000 894,000 (a) Using the percentage-of-completion method, compute the estimated gross profit that would be recognized during each year of the construction period. (If answer is 0, please enter 0. Do not leave any fields blank.) Gross profit recognized in 2020 $ Gross profit recognized in 2021 $ Gross profit recognized in 2022 $ (b) Using the completed-contract method, compute the estimated…arrow_forward
- 1. Prepare a schedule showing the revenue, cost and gross profit earned each year using thepercentage of completion method, using the engineer’s estimate as a measure ofcompletion.2. Prepare all journal entries required to reflect the contract3. Prepare journal entries for 2020 assuming zero profit method is used.arrow_forwardManson Construction Corp. has consistently used the percentage-of-completion method. In 2020, Manson started work on a $10,500,000 construction contract that was completed in 2021. The following information was taken from Manson’s 2020 accounting records: Billings to date $3,300,000 Costs incurred 3,150,000 Collections to date 2,100,000 Estimated costs to complete 6,300,000 What is the amount of revenue that will be recorded in 2020? In 2020, Pop Construction Corp. began work on a contract for $ 3,700,000. Other details follow: 2020 Costs incurred during the year.................................................................... $ 1,800,000 Estimated costs to complete as of December 31................................... 1,200,000 Billings during the year................................................................................. 1,650,000 Collections during the…arrow_forwardSalmania Co. began working on a project on August 2019, to construct a BD8,250,000 bridge that is expected to be completed in October 2020, at an estimated cost of BD6,000,000. At the end of 2019, the costs to date were BD2,400,000 and the estimated total costs to complete had not changed. The progress billings during 2019 were BD1,600,000 and the cash collected during 2019 was BD1,475,000. Salmania uses the percentage-of-completion method. What amount would be reported in Construction in Process at December 31, 2019?arrow_forward
- On February 1, 2021, Arrow Construction Company entered into a three-year construction contract to build a bridge for a price of $8,000,000. During 2021, costs of $2,000,000 were incurred, with estimated costs of $4,000,000 yet to be incurred. Billings of $2,500,000 were sent, and cash collected was $2,250,000. In 2022, costs incurred were $2,500,000 with remaining costs estimated to be $3,600,000. 2022 billings were $2,750,000, and $2,475,000 cash was collected. The project was completed in 2023 after additional costs of $3,800,000 were incurred. The company's fiscal year-end is December 31. This project does not qualify for revenue recognition over time. Required: 1. Calculate the amount of revenue and gross profit or loss to be recognized in each of the three years. 2a. Prepare journal entries for 2021 to record the transactions described (credit "various accounts" for construction costs incurred). 2b. Prepare journal entries for 2022 to record the transactions described (credit…arrow_forwardIn 2024, KP Building Incorporated began work on a four-year construction project (called Cincy One). The contract price is $460 million. KP recognizes revenue on this contract over time according to percentage of completion. At the end of 2024, the following financial statement information indicates the results to date for Cincy One: INCOME STATEMENT: Gross profit (before-taxes) recognized in 2024 $ 43 million BALANCE SHEET: Accounts receivable from construction billings $ 30 million Construction in progress $ 86 million Less: Billings on construction $ (96 million) Net billings in excess of construction in progress $ 10 million Required: Compute the following, placing your answer in the spaces provided and showing supporting computations below. Note: Round your percentage answer to the nearest whole number. Enter your answers in millions (i.e., 10,000,000 should be entered as 10).arrow_forwardCullumber, Inc. began work on a $7,164,000 contract in 2020 to construct an office building. During 2020, Cullumber, Inc. incurred costs of $1,960,630, billed its customers for $1,255,000, and collected $920,000. At December 31, 2020, the estimated additional costs to complete the project total $3,338,370.Prepare Cullumber’s 2020 journal entries using the percentage-of-completion method. (Credit account titles are automatically indented when amount is entered. Do not indent manually. For costs incurred use account Materials, Cash, Payables. If no entry is required, select "No entry" for the account titles and enter 0 for the amounts.) Account Titles and Explanation Debit Credit enter an account title to record costs incurred enter a debit amount enter a credit amount enter an account title to record costs incurred enter a debit amount enter a credit amount (To record costs incurred.) enter an account title to record billings enter a debit amount…arrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- AccountingAccountingISBN:9781337272094Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.Publisher:Cengage Learning,Accounting Information SystemsAccountingISBN:9781337619202Author:Hall, James A.Publisher:Cengage Learning,
- Horngren's Cost Accounting: A Managerial Emphasis...AccountingISBN:9780134475585Author:Srikant M. Datar, Madhav V. RajanPublisher:PEARSONIntermediate AccountingAccountingISBN:9781259722660Author:J. David Spiceland, Mark W. Nelson, Wayne M ThomasPublisher:McGraw-Hill EducationFinancial and Managerial AccountingAccountingISBN:9781259726705Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting PrinciplesPublisher:McGraw-Hill Education
![Text book image](https://compass-isbn-assets.s3.amazonaws.com/isbn_cover_images/9781259964947/9781259964947_smallCoverImage.jpg)
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337272094/9781337272094_smallCoverImage.gif)
Accounting
Accounting
ISBN:9781337272094
Author:WARREN, Carl S., Reeve, James M., Duchac, Jonathan E.
Publisher:Cengage Learning,
![Text book image](https://www.bartleby.com/isbn_cover_images/9781337619202/9781337619202_smallCoverImage.gif)
Accounting Information Systems
Accounting
ISBN:9781337619202
Author:Hall, James A.
Publisher:Cengage Learning,
![Text book image](https://www.bartleby.com/isbn_cover_images/9780134475585/9780134475585_smallCoverImage.gif)
Horngren's Cost Accounting: A Managerial Emphasis...
Accounting
ISBN:9780134475585
Author:Srikant M. Datar, Madhav V. Rajan
Publisher:PEARSON
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259722660/9781259722660_smallCoverImage.gif)
Intermediate Accounting
Accounting
ISBN:9781259722660
Author:J. David Spiceland, Mark W. Nelson, Wayne M Thomas
Publisher:McGraw-Hill Education
![Text book image](https://www.bartleby.com/isbn_cover_images/9781259726705/9781259726705_smallCoverImage.gif)
Financial and Managerial Accounting
Accounting
ISBN:9781259726705
Author:John J Wild, Ken W. Shaw, Barbara Chiappetta Fundamental Accounting Principles
Publisher:McGraw-Hill Education