If one additional worker could be hired, to which resource should this worker be assigned? Calculate the new process capacity in units/hr.

Cornerstones of Cost Management (Cornerstones Series)
4th Edition
ISBN:9781305970663
Author:Don R. Hansen, Maryanne M. Mowen
Publisher:Don R. Hansen, Maryanne M. Mowen
Chapter15: Lean Accounting And Productivity Measurement
Section: Chapter Questions
Problem 19E: A manufacturing cell within a value stream is structured with four processes and associated...
icon
Related questions
Question
(Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the
demand rate is 8 units/hour.
The process activities are always performed in the following sequence.
Resource 1 has a processing time of 5 minutes per unit.
Resource 2 has a processing time of 4 minutes per unit.
Resource 3 has a processing time of 6 minutes per unit.
Resource 1 is staffed by worker A and A's wage rate is $13 per hour.
Resource 2 is staffed by worker B and B's wage rate is $13 per hour.
Resource 3 is staffed by worker C and C's wage rate is $20 per hour.
If one additional worker could be hired, to which resource should this worker be assigned?
Calculate the new process capacity in units/hr.
O Assign the new worker to Resource 3. The process capacity is 12 units per hour.
O Assign the new worker to Resource 3. The process capacity is 10 units per hour.
O Assign the new worker to Resource 1. The process capacity is 20 units per hour.
O Assign the new worker to Resource 2. The process capacity is 15 units per hour.
Transcribed Image Text:(Chapter 4: Process Improvement) Consider a process consisting of three resources. Assume the demand rate is 8 units/hour. The process activities are always performed in the following sequence. Resource 1 has a processing time of 5 minutes per unit. Resource 2 has a processing time of 4 minutes per unit. Resource 3 has a processing time of 6 minutes per unit. Resource 1 is staffed by worker A and A's wage rate is $13 per hour. Resource 2 is staffed by worker B and B's wage rate is $13 per hour. Resource 3 is staffed by worker C and C's wage rate is $20 per hour. If one additional worker could be hired, to which resource should this worker be assigned? Calculate the new process capacity in units/hr. O Assign the new worker to Resource 3. The process capacity is 12 units per hour. O Assign the new worker to Resource 3. The process capacity is 10 units per hour. O Assign the new worker to Resource 1. The process capacity is 20 units per hour. O Assign the new worker to Resource 2. The process capacity is 15 units per hour.
Expert Solution
steps

Step by step

Solved in 3 steps with 1 images

Blurred answer
Knowledge Booster
Cost classification
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, accounting and related others by exploring similar questions and additional content below.
Similar questions
  • SEE MORE QUESTIONS
Recommended textbooks for you
Cornerstones of Cost Management (Cornerstones Ser…
Cornerstones of Cost Management (Cornerstones Ser…
Accounting
ISBN:
9781305970663
Author:
Don R. Hansen, Maryanne M. Mowen
Publisher:
Cengage Learning