Concept explainers
I was brought in as the project manager of an advanced vehicle development project during the detailed design phase. The previous project manager had to resign from our company due to health reasons. My customer was the U.S. Department of Transportation. I had a team of six automotive design engineers working on my team. When I came into the project, the first thing I did was to learn the advanced vehicle specifications and the deliverables’ timeline. Then I learned the responsibilities and capabilities of every team member. I went to Washington, DC from California to meet with my customer’s project manager and to generate a close rapport with him.
According to the original schedule, we were about two weeks late and the project was running over budget by 6% when I took over. One thing that bothered me was that my customer’s project manager was accustomed to phoning my team’s design engineers and ordering minor variations to the specifications without my knowledge. Nothing was documented and we were drifting away from the original project technical specifications. Apparently, the previous project manager closed his eyes to these minor specification variations and my customer’s project manager got used to forcing these minor specification changes on my design engineers.
The first thing I did was to have an emergency team meeting. I went over all pending redlines that were not released through document control. The original specifications were still at revision A. I asked my team members not to accept any changes to the specifications without my knowledge. If a specification change was requested by the customer over the telephone, it did not matter how minor the change request was, it had to go through me. We all agreed to the new strict specification change rules. I revised the specifications to revision B and sent it to my customer’s project manager for his approval.
Then I asked my customer’s project manager to travel to our plant so that we could finalize the revised technical specifications. I sat with him for three days face-to-face to go over each redline and got his final approval for revision B to the contract’s technical specifications. I told him that we were falling behind in the project due to the minor changes that were piling up. I asked him politely to go through all the changes with me whether they were minor or not. I told him he could talk to the individual design engineers as many times as he wished, but if there was a change looming on the horizon, he had to go through me. I emphasized that if the change was urgent, I could redline the technical specifications, sign it, and release it to the responsible design engineer that same day. Then I could have the technical specifications go through an official revision after piling up a couple of minor changes. If a change were going to affect the project schedule and cost, then I would provide him with my new schedule and cost estimates. I then could get the change approved and implemented only after his written concurrence with me regarding the new project schedule and project cost. He agreed with me on all my scope change procedures.
I kept the project technical specifications current. I made sure that changes went through our document control with top priority. I always kept my design engineers on top of the technical specifications. I reviewed all the changes during our weekly team meetings. When the project design phase was completed after nine months, the technical specifications were at revision K.
Similar technical specification control rules apply between your subcontractors and your company. Your customer should not be able to go to your subcontractor directly and ask for a scope change.
Technical specifications make up one of the critical legs of a project structure. The other three critical legs of the project structure are the schedule, the cost, and the team. If one of those legs is out of sync, the project will start to wobble, lose control, and sink. As project managers, we will definitely fail. Keeping the scope changes of a project under tight control without causing your customer to become frustrated and angry is a must.
LESSONS LEARNED FROM THIS PROJECT EVENT
• Taking on a project in the middle of execution is very courageous and risky.
• You must absorb and evaluate all aspects of your new project very fast.
• You must initiate changes to project activities that you see as inappropriate.
• It is always quite challenging to be able to change old established habits in a project environment.
Source: Atesmen, K. (2015). Project Management Case Studies and Lessons Learnt. Boca Raton:
Taylor & Francis Group.
1.2. “Nothing was documented, and we were drifting away from the original project technical specifications”.
Briefly discuss the draw backs of adding unapproved changes during project implementation
Step by stepSolved in 2 steps
- How do Product Owners and Business Analysts collaborate to ensure the project meets business needs?arrow_forwardTalk about your thoughts around the dangers of assuming during the business definition phase. What might need to take place to avoid high risk misconceptions about project scope and purposearrow_forwardIn all my years of working, I have never once employed a top-down design approach. Let let us know if this is the case. If you said "yes," elaborate on your thoughts. Using at least one example, explain how top-down design aided the project managers in getting the job done.arrow_forward
- find information on major technology project. Then, assign yourself as a project manager for the project and start managing it by: o Identifying the stakeholders for the project. o Identify the business, organization and technology aspects related to the project. o Define the personality of the organization undertaking the project by applying the four frames of organizations. o Choose the organizational structure that in your opinion will suit the project and can you provide a justification of why you select this type of structure. o Which project lifecycle model is most suited for the project. Provide a justification for the answerarrow_forwardas part of my Agile project management, I am being asked to explain the 12 Agile Manifesto elements, and the 10 Agile principles.i find this confusing as, to date, I have located 12 Agile principles, but nothing that specifically relates to manifesto elements appreciate your thoughts thanks Paularrow_forwardYour organization has decided to hire 2 new project managers. As you know when someone is hired from outside the organization there is a tendency for employees to have their own philosophy as it relates to managing projects. Given what you read in Chapters 5 and 6 in our text book, create a list of 5 best practices you believe are important to help the new employees understand how to estimate project times and costs as well as developing a project plan (Note: You can use your current organization to complete this discussion. Consider this an opportunity to right any wrongs you currently see in your organization).arrow_forward
- You have received a promotion to the position of project manager, but you are unsure if it would be more beneficial for you to remain in your current role or to hunt for a job that focuses more on management. Before determining whether or not to take the job, you should discuss it with the person you are important with.arrow_forwardExplain a situation where you have used project evaluation. How would it have been made better with the use of the information in Chapter 11? Would it have been? Why or why not?arrow_forwardPlease original work Talk about what needs to be done as part of closing a project. Why are these activities important? List several questions that you would ask during a post-project evaluation and describe changes that you would make in your next project to improve based upon possible responses to the questions. Please cite references (please include web links)arrow_forward
- Understanding BusinessManagementISBN:9781259929434Author:William NickelsPublisher:McGraw-Hill EducationManagement (14th Edition)ManagementISBN:9780134527604Author:Stephen P. Robbins, Mary A. CoulterPublisher:PEARSONSpreadsheet Modeling & Decision Analysis: A Pract...ManagementISBN:9781305947412Author:Cliff RagsdalePublisher:Cengage Learning
- Management Information Systems: Managing The Digi...ManagementISBN:9780135191798Author:Kenneth C. Laudon, Jane P. LaudonPublisher:PEARSONBusiness Essentials (12th Edition) (What's New in...ManagementISBN:9780134728391Author:Ronald J. Ebert, Ricky W. GriffinPublisher:PEARSONFundamentals of Management (10th Edition)ManagementISBN:9780134237473Author:Stephen P. Robbins, Mary A. Coulter, David A. De CenzoPublisher:PEARSON