A company needs to design an assembly line to produce portable electric generators. They plan to use the assembly-line 6 hours each day to produce 2160 generators daily. The following table describes the tasks involved in the assembly of portable electric generator:
IMMEDIATE
TASK PREDECESSORS TIME (seconds)
==== =========== ==============
a none 3
b none 5
c a,b 6
d none 7
e c,d 9
Use the Longest Processing Time Rule (LPT) to design this assembly line.
How many workstations are required by your design?
A. | 7 | |
B. | 5 | |
C. | 4 | |
D. | 6 | |
E. | 3 |