Question
Hip Replacements, Inc., has a master production
its newest model, as shown below, a setup cost of $50, a holding
cost per week of $2, beginning inventory of 0, and lead time of
1 week. What are the costs of using lot-for-lot for this l0-week
period?
WEEK 1 2 3 4 5 6 7 8 9 10
Gross requirements 0 0 50 0 0 35 15 0 100 0
Scheduled receipts
Projected on hand 0 0 0 0 0 0 0 0 0 00
Net requirements 0 0 50 0 0 35 15 0 100
Planned order receipts 50 35 15 100
Planned order releases 50 35 15 100
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
This is a popular solution
Trending nowThis is a popular solution!
Step by stepSolved in 2 steps with 1 images
Knowledge Booster
Learn more about
Need a deep-dive on the concept behind this application? Look no further. Learn more about this topic, operations-management and related others by exploring similar questions and additional content below.Similar questions
- Complete the MPS record below for a single item. (Enter your responses as integers. A response of "0" is equivalent to being not applicable.) Order Policy: 100 units Lead Time: 1 week February Item: A Quantity on Hand: 80 Forecast Customer orders (booked) Projected on-hand inventory MPS quantity 1 60 35 20 0 January 2 70 15 3 18 8 60 90 BID 4 40 0 LE Week 5 45 30 6 45 70 7 55 0 8 50 0arrow_forward2.7 Which of the following help explain how the Reorder Point (ROP) works in conjunction with the Economic Order Quantity (Q), the number of orders (N) and the time between orders (T)? a) The Economic Order Quantity (Q) and the Annual Demand (D) are used to determine the number of Order (N) b) The number of orders (N) and the number of days that a firm works (W) are used to determine the time span between orders (T) c) Orders are placed every T days unless the inventory on hand fall to or below the Reorder Point d) Only a and b e) f) Only b and c All of a, b and c 2.8 The objective of Inventory Management is to balance inventory investment (cost) and customer service. a) TRUE b) False 2.9 The Economic Order Quantity (EOQ), the number of orders, the Reorder Point (ROP), the time between orders are important analytics in Inventory Management. a) TRUE b) FALSE 2.10 The number of working days for a firm is an important input in calculating the components of the Economic Order Quantity…arrow_forwardComplete the master productin schedule based on thefollowing information:Week 1 2 3 4 5 6 7 8 9Forecast 320 100 30 110 40 240 290 60 410Customer Orders 60 50 80 20 60 60 0 0 0Projected On-Hand Inventory 600MPS ReleasedMPS DueAvailable-to-promise (ATP) Scheduled production whenever projected on-had inventory drops below 30MPS lot size: 300Production lead time or lead time for MPS releases 1arrow_forward
- Assume you are the manager of a shop that assembles power tools. You have just received an order for 55 chain saws, which are to be shipped at the start of week 8. Pertinent information on the saws follows: Item Lead Time (weeks) On Hand Saw A B C D E F 2 1 2 2 1 1 2 Gross requirements Scheduled receipts Projected on hand Net requirements Planned order receipt Planned order release Ĉ E(3) & E(2) LT = 1 week Lot size: Lot-for-Lot 15 10 5 65 20 10 30 Skip Extension Tip: Double click to open in new tab Show Transcribed Text Develop the material requirements plan for component E using lot-for-lot ordering for all items. (Leave no cells blank - be certain to enter "0" wherever required.) Components A(2), B(1), C(4) E(3), D(1) D (2), F(3) E(2), D (2) Beg. Inv. 1 2 3 190 5 210 6arrow_forward25 If safety stock is desired, it should be built into which portion of MRP? Select one: a. none b. finished goods c. raw materials d. any e. either raw materials or finished goodsarrow_forwardConsider the following information. PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 100 Q = 60, LT= 3 weeks, Safety Stock = 5 1 70 70 PART X Gross Requirements Scheduled Receipts Projected On-Hand Inventory 100 Planned Order Releases 1 70 70 100 2 0 > X WEEK 3 40 Compute the planned order releases and projected on-hand inventory for component part X. Round your answers to the nearest whole number. If your answer is zero, enter "0". 2 0 4 0 100 WEEK 3 40 5 160 60 4 0 40 0 X 5 160 Check My Work -60 0arrow_forward
- Keebock, a maker of outstanding running shoes, keeps the soles of its size 13 running shoes in inventory for one period at a cost of $.25 per unit. The setup costs are $50. Beginninginventory is zero, and lead time is I week. Shown here are the net requirements per period. Determine Keebock's cost based ona) EOQ. b) Lot-for-lot.arrow_forwardFlora is preparing for her busy season and is building 2500 Model A fountains. Calculate the gross requirements for each component assuming that there is no beginning inventory. Component Immediate Parent Usage per Parent Lead Time (weeks) Beginning Inventory A none — 1 0 B A 2 2 250 C A 1 6 500 D A 3 3 750 E A 2 2 750 F B 4 2 3000 G B 2 4 1000 H D 3 2 5000 I D 2 4 5000 J E 1 8 1000 K E 5 1 5000 L E 2 4 2500 M F 3 3 250 N F 6 3 2560 O H 2 4 0 P K 1 2 500 Q K 2 3 1000arrow_forwardFill in the partially completed inventory record shown herearrow_forward
- The Alpha Beta Company produces two products; A and B, that are made from components C and D. Given the follow-ing product structures, master scheduling requirements, and inventory information, determine when orders shouldbe released for A, B, C, and D and the size of those orders.arrow_forwardExplain how is ordering in small lot sizes essential for just in time implementation and what benefi are epected to be achieved ?arrow_forwardFlora's Fabulous Fontains top product is its Model A. Calculate the minimum replenishment time to build 2500 Model A fountains given the following beginning inventories. Use the following information: Component ImmediateParent Usage perParent Lead Time(weeks) BeginningInventory A none − 2 0 B A 2 2 250 C A 1 6 500 D A 3 3 750 E A 2 2 750 F B 4 2 3000 G B 2 4 1000 H D 3 2 5000 I D 2 4 5000 J E 1 11 1000 K E 5 1 5000 L E 2 4 2500 M F 3 3 250 N F 6 3 2560 O H 2 4 0 P K 1 2 500 Q K 2 3 1000 (a) = (enter a number of weeks) weeksarrow_forward
arrow_back_ios
SEE MORE QUESTIONS
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.