Given the following project (all times are in days):
refer the pic please
All activities, except for activity b , may be partially crashed.(i.e. partial crashing for activity b only, is not allowed.)
1. Draw the network and find the critical path, time, and total cost for an all-normal level of project activity.
Expert Solution
This question has been solved!
Explore an expertly crafted, step-by-step solution for a thorough understanding of key concepts.
Step by stepSolved in 3 steps with 3 images
Knowledge Booster
Similar questions
- I only need help with part d-2, please help! The following CPM network has estimates of the normal time in weeks listed for the activities: a. Identify the critical path. A-C-D-E-G A-C-D-F-G A-B-D-E-G A-B-D-F-G b. What is the length of time to complete the project? 25 weeks c. Which activities have slack, and how much? C, 1 week; E, 2 weeks. D, 1 week; E, 2 weeks. B, 2 weeks; E, 2 weeks. C, 2 weeks; F, 3 weeks. Here is a table of normal and crash times and costs. ACTIVITY NORMAL TIME CRASH TIME NORMAL COST CRASH COST A 7 6 $ 7,000 $ 8,000 B 2 1 5,000 7,000 C 4 3 9,000 10,200 D 5 4 3,000 4,500 E 2 1 2,000 3,000 F 4 2 4,000 7,000 G 5 4 5,000 8,000 d-1. Which activities would you shorten to cut two weeks from the schedule in a rational fashion? A, C A, E B, D B, C d-2. What would be the total incremental cost? I only need help with this question please.arrow_forwardProject ALPHA has 6 activities from A to F as follows: Activity Duration Preceded By A A A B E F E Legend: Early Start Duration Early Finish Acitivity ID Late Start Float (Slack) Late Finish Which Activity (activities) is (are) called a "merged activity"? A C B B D A C E В D D B D A F A F E Select one: A A when it is a backward pass D and E F none of the given answersarrow_forwardConsider the following activities for a project. Answer the questions below. a. Assume the durations given are high confidence, create a network chart (don’t considerresources yet), and identify the critical path. What is the duration of the project? b. You aren’t quite ready to apply the critical chain project management yet, but you do want toeliminate multi-tasking. Eliminate any resource contention in your network. Identify the criticalpath now? What is the duration of the project? c. Apply the critical chain project management approach to this project. Create a new view ofyour project network, include a project buffer and any needed feeding buffers. What is the criticalchain? What is the duration of the project now?arrow_forward
- Problem 2: Chicago Project You are asked to manage an upcoming project for a client based in Chicago. Your supervisor, Susan, asked you to determine if the project will be completed in 2 months (60 days). Susan sent you the estimated time durations (in days) for the project. The information is given below: 4. Your supervisor was told that the client would like to complete the project in 56 days. Which path in the project network has the greatest risk of running over this new deadline of 56 days? 5. Prepare a report for Susan regarding your findings. Include your recommended strategy to finish the project in the least possible time.arrow_forwardProblem: PERT/CPM(Critical Path Method) Using CPM find the minimum number of days to finish the project. For each activity find out the earliest start and finish time as well as latest start and finish time. Consider each week is equal to five days. Activity A BCD 40 I с E F G H I Predecessor A,D A IAE OF H А D Duration (Most Likely) 13 days 4 days 4 days 14 days 4 days 2 Weeks 12 days 2 Days 1 Weekarrow_forward
arrow_back_ios
arrow_forward_ios
Recommended textbooks for you
- Practical Management ScienceOperations ManagementISBN:9781337406659Author:WINSTON, Wayne L.Publisher:Cengage,Operations ManagementOperations ManagementISBN:9781259667473Author:William J StevensonPublisher:McGraw-Hill EducationOperations and Supply Chain Management (Mcgraw-hi...Operations ManagementISBN:9781259666100Author:F. Robert Jacobs, Richard B ChasePublisher:McGraw-Hill Education
- Purchasing and Supply Chain ManagementOperations ManagementISBN:9781285869681Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. PattersonPublisher:Cengage LearningProduction and Operations Analysis, Seventh Editi...Operations ManagementISBN:9781478623069Author:Steven Nahmias, Tava Lennon OlsenPublisher:Waveland Press, Inc.
Practical Management Science
Operations Management
ISBN:9781337406659
Author:WINSTON, Wayne L.
Publisher:Cengage,
Operations Management
Operations Management
ISBN:9781259667473
Author:William J Stevenson
Publisher:McGraw-Hill Education
Operations and Supply Chain Management (Mcgraw-hi...
Operations Management
ISBN:9781259666100
Author:F. Robert Jacobs, Richard B Chase
Publisher:McGraw-Hill Education
Purchasing and Supply Chain Management
Operations Management
ISBN:9781285869681
Author:Robert M. Monczka, Robert B. Handfield, Larry C. Giunipero, James L. Patterson
Publisher:Cengage Learning
Production and Operations Analysis, Seventh Editi...
Operations Management
ISBN:9781478623069
Author:Steven Nahmias, Tava Lennon Olsen
Publisher:Waveland Press, Inc.